Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74314 REL 117: 1998-019-00 EXP WIND RIVER WATERSHED - WDFW
Project Number:
Title:
Wind River Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Wind 100.00%
Contract Number:
74314 REL 117
Contract Title:
1998-019-00 EXP WIND RIVER WATERSHED - WDFW
Contract Continuation:
Previous: Next:
74314 REL 82: 1998-019-00 EXP WIND RIVER WATERSHED - WDFW
Contract Status:
Closed
Contract Description:
Objectives of WDFW Wind River Steelhead Project:

1)  Long term collection of accurate and precise Status and Trend information for Upper Gorge (Wind River) Summer Steelhead Major Population Group (MPG) within the  ESA Threatened Lower Columbia Steelhead DPS
a. VSP Parameters (Abundance, Productivity, Spatial Structure, Diversity) collected at basin and sub-basin spatial scales for multiple age classes.
b.  Report on Coordinated Data Assessments High Level Indicators (HLIs) including:
     Natural Origin Spawner Abundance (NOSA)
     Juveniles per Spawner (JpS)
     Recruits per Spawner (RpS)
     Smolt to Adult Return rate (SAR)
c.  Wild steelhead life cycle monitoring in a watershed with no hatchery program and limited hydrosystem impacts to serve as a reference population for understanding hydrosystem and hatchery impacts on steelhead throughout the Columbia Basin.

2)  Implement Before-After (BA) and Before-After-Control-Impact (BACI) study designs using steelhead smolt and adult abundance, productivity, and biological attributes collected as part of a long term status and trend project to measure and report on steelhead responses to Hemlock Dam Removal.

a.  Determine change in migration timing, adult age (including repeat spawner rate), and adult number (including summer versus winter run) of Trout Creek steelhead before and after removal of Hemlock Dam.
b.  Determine change in the number of steelhead a) smolts b) parr, c) parr-to-smolt ratio, and d) age at smoltification based on smolt trapping at TC, UW, and PC before and after removal of Hemlock Dam.
c.  Determine change in survival of steelhead smolts from Trout Creek before and after removal of Hemlock Dam.
d.  Determine if there is a change in smolt-to-adult return and freshwater productivity from Trout Creek before and after removal of Hemlock Dam.  Null Hypothesis: There is no change in productivity and/or capacity estimate from spawner-recruit analysis before and after dam removal.
Account Type(s):
Expense
Contract Start Date:
09/01/2020
Contract End Date:
08/31/2021
Current Contract Value:
$177,148
Expenditures:
$177,148

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
NOAA-Fisheries Scientific Research Permit A: 165. NOAA-Fisheries ESA Research Permit 08/31/2021 08/31/2021
Juvenile Out-Migrant Trapping - 2021 B: 157. Juvenile Outmigrant Trapping 07/15/2021 07/15/2021
Adult Trapping and Snorkel Surveys C: 157. Collect Adult Abundance Data Via Mark-Resight 08/31/2021 08/31/2021
Juvenile Tagging and PTAGIS Uploads D: 158. Juvenile Tagging 08/31/2021 08/31/2021
Adult Tagging and PTAGIS Uploads E: 158. Adult Tagging 08/31/2021 08/31/2021
Analyze/Interpret Juvenile Steelhead Data and Include Results in RM&E Calendar Year Technical F: 162. Juvenile Data Analysis 03/15/2021 03/15/2021
Analyze/Interpret Adult Steelhead Data and Include Results in RM&E Calendar Year Technical Rep G: 162. Adult Data Analysis 03/15/2021 03/15/2021
Calculate HLIs and Include Results in RM&E Calendar Year Technical Report H: 162. Coordinated Data Assessments HLIs 03/15/2021 03/15/2021
Summary Memos for Adult and Juvenile Steelhead Population Estimate I: 161. Summary Memos 08/31/2021 08/31/2021
Project Information Exchange J: 191. Exchange Project Activity and Progress Information with Partner Agencies 08/31/2021 08/31/2021
Produce Peer Review Journal Article on Fish Responses to Hemlock Dam Removal K: 183. Effects of Hemlock Dam Removal 08/31/2021
Deliverable: Receipt of NPCC Recommendation for Anadromous Fish Habitat and Artificial Production Review L: 141. Other Reports for BPA 08/31/2021 08/31/2021
Completed Annual Report N: 132. Submit 2019 RM&E Technical Report for the Period (Jan 2019) to (Dec 2019) 05/30/2021 05/30/2021
Completed Annual Report O: 132. Submit 2020 RM&E Technical Report for the Period (Jan 2020) to (Dec 2020) 08/30/2021
Effective implementation management and timely contract administration P: 119. Project Oversight 08/31/2021 08/31/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 183 Produce Journal Article
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 158 Mark/Tag Animals
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 3 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 NOAA-Fisheries ESA Research Permit
B 157 Juvenile Outmigrant Trapping 07/07/2020
C 157 Collect Adult Abundance Data Via Mark-Resight 07/07/2020
D 158 Juvenile Tagging 07/07/2020
E 158 Adult Tagging 07/07/2020
F 162 Juvenile Data Analysis
G 162 Adult Data Analysis
H 162 Coordinated Data Assessments HLIs
I 161 Summary Memos
J 191 Exchange Project Activity and Progress Information with Partner Agencies
K 183 Effects of Hemlock Dam Removal
L 141 Other Reports for BPA
M 185 Periodic Status Reports for BPA
N 132 Submit 2019 RM&E Technical Report for the Period (Jan 2019) to (Dec 2019)
O 132 Submit 2020 RM&E Technical Report for the Period (Jan 2020) to (Dec 2020)
P 119 Project Oversight