Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74325: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Project Number:
Title:
Nez Perce Harvest Monitoring on Snake and Clearwater Rivers
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 50.00%
Upper Snake Snake Upper 50.00%
Contract Number:
74325
Contract Title:
2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Contract Continuation:
Previous: Next:
70630: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
  • 74017 REL 1: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Contract Status:
Closed
Contract Description:
This project describes the Nez Perce Tribe's efforts to monitor currently ongoing NPT fisheries.  Sampling strategies are designed to provide greater data precision in treaty catch reports and exploitation rates during select Nez Perce fishery seasons.  Harvest management is intertwined with all Columbia Basin artificial production programs and affects the status of naturally produced stocks as well.  The Nez Perce Tribe has monitored its fisheries primarily by funding sources outside the Northwest Power Planning Council (NPPC) process.  However, the subbasin planning process has documented the need to incorporate this very important aspect of fisheries management within the existing Fish and Wildlife Program.  

The current SOW has three major areas of activity.  Tribal Management Plans and Fishery Implementation Plans will be prepared to assure both incidental and direct take of ESA listed species does not jeopardize their existence.  The bulk of the work of the SOW in involved in actual on the ground harvest monitoring in Snake, Salmon and Clearwater rivers and their tributaries and in the Zone 6 fishery (Bonneville Dam to McNary Dam, including some Below Bonneville fishing).  In addition, there will be work to design and verify the monitoring techniques and disseminate the monitoring data to cooperating agencies on a regular basis.
Account Type(s):
Expense
Contract Start Date:
12/01/2016
Contract End Date:
11/30/2017
Current Contract Value:
$346,269
Expenditures:
$346,269

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Lisa Dexter Bonneville Power Administration No Interested Party lldexter@bpa.gov (503) 230-3893
Arleen Henry Nez Perce Tribe Yes Administrative Contact arleenh@nezperce.org (208) 621-3833
Makary Hutson Bonneville Power Administration Yes Interested Party (503) 230-7667
David Johnson Nez Perce Tribe No Supervisor davej@nezperce.org (208) 621-3736
Travis Kessler Bonneville Power Administration No Interested Party tdkessler@bpa.gov (503) 230-5468
Andre L'Heureux Bonneville Power Administration Yes F&W Approver allheureux@bpa.gov (503) 230-4482
Joseph Oatman Nez Perce Tribe Yes Contract Manager joeo@nezperce.org (208) 843-7320x3730
David Roberts Bonneville Power Administration Yes COR daroberts@bpa.gov (503) 230-4511
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Gregory Smith Bonneville Power Administration Yes Interested Party gmsmith@bpa.gov (503) 230-5049
Dave Statler Nez Perce Tribe Yes Technical Contact daves@nezperce.org (208) 621-3575
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Jack Yearout Nez Perce Tribe No Technical Contact jacky@nezperce.org (208) 621-4638
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental Compliance Documentation B: 165. Produce Environmental Compliance Documentation 11/30/2017 11/30/2017
Project Management, Planning and Budgetary Processes C: 119. Project Management & Planning plus Budgetary Processes 11/30/2017 11/30/2017
BA's for tribal harvest and TMP's for selected subbasins D: 174. Prepare Annual Tribal Mmanagement Plans and Fishery Implementation Plans 11/30/2017 11/30/2017
Develop Harvest Monitoring Methodology E: 156. Develop annual harvest monitoring methodology 10/30/2017 10/30/2017
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets F: 157. Implement harvest monitoring methodology and disseminate harvest monitoring results (Creel Sur 11/30/2017 11/30/2017
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets G: 157. Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring results (In-season 11/30/2017 11/30/2017
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets H: 157. Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring Results (Post-seas 11/30/2017 11/30/2017
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets I: 157. Implement Harvest Monitoring methodology and Disseminate Harvest Monitoring Results (Gill net) 11/30/2017 11/30/2017
Completed 2014 Annual Report J: 132. PLACEHOLDER: Annual Report for the period 1/1/14 - 12/31/14 02/15/2017 03/31/2017
Completed 2015 Annual Report K: 132. Submit Progress Report for the period Jan 2015 to Dec 2015 10/31/2017 10/30/2017
Submit CY 2015 BiOp RPA Report in cbfish.org L: 202. BiOp RPA Report for CY 2015 04/30/2017 04/30/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 174 Produce Plan
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 12/01/2016
B 165 Produce Environmental Compliance Documentation 12/01/2016
C 119 Project Management & Planning plus Budgetary Processes 12/01/2016
D 174 Prepare Annual Tribal Mmanagement Plans and Fishery Implementation Plans 12/01/2016
E 156 Develop annual harvest monitoring methodology 12/01/2016
F 157 Implement harvest monitoring methodology and disseminate harvest monitoring results (Creel Sur 12/01/2016
G 157 Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring results (In-season 12/01/2016
H 157 Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring Results (Post-seas 12/01/2016
I 157 Implement Harvest Monitoring methodology and Disseminate Harvest Monitoring Results (Gill net) 12/01/2016
J 132 PLACEHOLDER: Annual Report for the period 1/1/14 - 12/31/14 12/01/2016
K 132 Submit Progress Report for the period Jan 2015 to Dec 2015 12/01/2016
L 202 BiOp RPA Report for CY 2015