Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 75023: 2007-395-00 EXP NPT LOCHSA WATERSHED RESTORATION
Project Number:
Title:
Protect and Restore Lochsa Watershed
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
75023
Contract Title:
2007-395-00 EXP NPT LOCHSA WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
71057: 2007-395-00 EXP NPT LOCHSA WATERSHED RESTORATION
  • 74017 REL 21: 2007-395-00 EXP PROTECT & RESTORE UPPER LOCHSA
Contract Status:
Closed
Contract Description:
Project/Contract History:

This project is a component of the Nez Perce-Clearwater National Forests-Nez Perce Tribe Watershed Restoration Partnership.  This project represents a combination of two ongoing BPA and NPT restoration projects, Project 1996-077-03, Project 2002-074-00, and an extension of the project area to include the entire Lochsa Watershed rather than just the upper subwatersheds.  This project unification has significantly increased administrative and financial efficiency in order to maximize the direct benefit to fish and wildlife.

Restoration follows a ridge top to ridge top approach with implementation focused on decreasing sediment inputs into area streams, increasing aquatic habitat connectivity, decreasing resource impacts from roads, and eradicating exotic, invasive plants. The cost share for this project has been contributed by the Nez Perce-Clearwater National Forests who provides an approximate 18% match including cash and in-kind contributions. Project planning and implementation responsibilities are also shared with the Forest.

To date, the partnership has re-opened access to 88.95 miles of habitat, removed 521 miles of road through decommissioning or abandonment, improved 35.4 miles of road, planted 791 acres of vegetation, and treated over 2,997 acres of invasive, non-native plants. Major actions proposed for the 2014-18 funding cycle include over 18 miles of habitat re-opened through barrier removal/replacement, 119 miles of road decommissioning, 35 miles of road improvement or relocation, 250 acres of planting, 5,000 acres of weed treatment, approximately 1,500 feet of channel reconstruction, and addition of large woody material to approximately 0.5 miles of stream.

FY 2017 Contract Implementation:

FY 17 implementation includes the removal of up to11 miles of roads (to reduce sediment inputs to streams), up to 3 culvert replacements (to improve hydrologic capacity and reduce potential sediment delivery, as well as  provide habitat connectivity), planting up to1,200 native riparian shrubs, installing large wood into Wawa’aalamnime Creek to provide habitat complexity, and continued planning and coordination for future habitat improvement projects as identified in the 2016 ATLAS strategic prioritization framework.

NPT Watershed personnel will also conduct invasive plant treatment, continued invasive inventory, and continue an inventory of roads and culverts throughout the Lochsa watershed in order to identify fish passage barriers and road associated risks to aquatic species.  

Matching Costs Summary 2017: In 2017 the Nez Perce-Clearwater National Forests will provide approximately 18% of project costs for road decommissioning/improvement and culvert replacement, which includes project planning, contract administration, and implementation as described in the existing MOU with BPA.    

The Lochsa project continues to work with an environmental non-profit organization to pursue the purchase of, and return to federal ownership of, nearly 40,000 acres of privately held timberlands in the upper Lochsa. This land acquisition was identified as the highest priority protection and restoration action within the three highest priority Subwatersheds during the development of the BPA facilitated Lochsa ATLAS strategic prioritization framework.
Account Type(s):
Expense
Contract Start Date:
02/01/2017
Contract End Date:
01/31/2018
Current Contract Value:
$1,296,022
Expenditures:
$1,296,022

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Marcie Carter Nez Perce Tribe Yes Supervisor marciec@nezperce.org (208) 621-3534
Anne Connor US Forest Service (USFS) No Technical Contact aconnor@fs.fed.us (208) 476-8235
David Forestieri Nez Perce Tribe Yes Contract Manager dforestieri@nezperce.org (208) 942-0318
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
Curtis Johnson Nez Perce Tribe Yes Interested Party curtisj@nezperce.org (208) 942-0327
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance documentation submitted to BPA A: 165. Provide Necessary Environmental Compliance Documentation to BPA 05/31/2017 05/31/2017
Provide periodic review of proposed partner actions B: 191. Review of Proposed Partner Actions 01/31/2018 12/31/2017
11 Miles of Roads Decommissioned C: 33. Brushy Fork Face Road Decommissioning 10/31/2017 10/31/2017
107 Road Relocation D: 33. Relocate Lower 107 Road 10/31/2017 10/31/2017
Replace West Fork Deadman Creek Culvert E: 184. Replace the West Fork Deadman Creek Culvert 10/31/2017 10/31/2017
Replace Pete King Creek Culvert F: 184. Replace Pete King Creek Culvert 10/31/2017 10/31/2017
Erosion Prevented for Culverts and Roads G: 55. Erosion Control on Culvert Replacements and Decommissioned roads 10/31/2017 10/31/2017
Waw'aa'lamnine Large Wood Structures H: 29. Waw'aa'lamnine Large wood placement 10/31/2017
Invasive Plant Species Treated by Mechanical and Chemical Methods I: 199. Treat Exotic Invasive Species 11/30/2017 11/30/2017
Decommissioned roads and culvert replacement site native revegetation J: 47. Restoration Plant Collection and Planting 11/30/2017 11/30/2017
Designs for Future Project Implementation K: 175. Designs for Road Decommissioning/Improvement, Channel Reconstruction & Culvert Replacement 01/31/2018 12/31/2017
Lochsa Private Land Acquisition L: 172. Lochsa Lands Acquisition 01/31/2018
Road and Culvert Inventory M: 115. Road and Culvert Inventory 11/15/2017 11/15/2017
Completed Weed Inventory and Data Analysis N: 115. Inventory of Invasive Plants 01/31/2018 12/31/2017
Updated Database O: 160. Input & Analyze Road, Weed, and Culvert Data 12/31/2017 12/31/2017
FY 2018 Contract Package and FY 2017 Accrual Estimate P: 119. Management, Coordination, and Communication 11/30/2017 11/30/2017
Final FY 2017 annual report Q: 132. Submit Annual Report for 2/1/2017 - 1/31/2018 01/31/2018 01/31/2018

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 2 instances of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 115 Produce Inventory or Assessment

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide Necessary Environmental Compliance Documentation to BPA 02/01/2017
B 191 Review of Proposed Partner Actions 12/01/2016
C 33 Brushy Fork Face Road Decommissioning 12/30/2016
D 33 Relocate Lower 107 Road 12/21/2016
E 184 Replace the West Fork Deadman Creek Culvert 12/21/2016
F 184 Replace Pete King Creek Culvert 12/21/2016
G 55 Erosion Control on Culvert Replacements and Decommissioned roads 12/21/2016
H 29 Waw'aa'lamnine Large wood placement 07/28/2017
I 199 Treat Exotic Invasive Species 12/21/2016
J 47 Restoration Plant Collection and Planting 12/21/2016
K 175 Designs for Road Decommissioning/Improvement, Channel Reconstruction & Culvert Replacement 12/28/2016
L 172 Lochsa Lands Acquisition 12/01/2016
M 115 Road and Culvert Inventory 12/21/2016
N 115 Inventory of Invasive Plants 12/21/2016
O 160 Input & Analyze Road, Weed, and Culvert Data 12/01/2016
P 119 Management, Coordination, and Communication 12/01/2016
Q 132 Submit Annual Report for 2/1/2017 - 1/31/2018 12/01/2016
R 185 Periodic Status Reports for BPA 12/01/2016