Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 76220: 1998-019-00 EXP WIND RIVER WATERSHED UCD
Project Number:
Title:
Wind River Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Wind 100.00%
Contract Number:
76220
Contract Title:
1998-019-00 EXP WIND RIVER WATERSHED UCD
Contract Continuation:
Previous: Next:
72415: 1998-019-00 EXP WIND RIVER WATERSHED UCD
  • 79517: 1998-019-00 EXP WIND RIVER WATERSHED UCD
Contract Status:
Closed
Contract Description:
This contract supports and is part of the Wind River Watershed Project, initiated in 1998.  The project's focus is on restoration of Wind River steelhead.  In 1997, the Washington Department of Fish and Wildlife rated the status of the Wind River summer run steelhead as critical.  In 1998, the National Marine Fisheries Service listed the steelhead of the lower Columbia river as "threatened" under the Endangered Species Act.  Due to the status of this stock, the Wind River summer steelhead have the highest priority for recovery/restoration in the state of Washington's Lower Columbia Steelhead Conservation Initiative.  Project participants are the Underwood Conservation District (UCD), US Geological Survey, US Forest Service, and Washington Department of Fish and Wildlife.  

This contract continues Underwood Conservation District's support and participation in the project.  UCD will provide habitat restoration work in support of the recovery of the Wind River summer steelhead stock in 2017 and 2018.  Work will focus on further developing the design plans and permitting for the Little Wind River Habitat Enhancement Project, Phase IV, upstream of previous habitat work conducted by UCD.  Under the previous statement of work we selected the highest priority project that was the most ready to carry forward for implementation.  This project is being readied for potential implementation with BPA dollars in a subsequent contract.  Additional work involves maintaining vegetation at past planting sites and installing new plants at key restoration sites in the Wind River watershed.  Other work such as producing periodic (quarterly) status reports, the annual progress report, coordinating with project partners, producing environmental compliance documentation, stream temperature monitoring, as well as managing and administering the project will be funded at levels to allow continued maintenance of these activities.
Account Type(s):
Expense
Contract Start Date:
07/01/2017
Contract End Date:
06/30/2018
Current Contract Value:
$88,348
Expenditures:
$88,348

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Manage Project A: 119. Manage and Administer Projects 06/30/2018 06/30/2018
Submit Calendar-Year Annual Report for 2017 C: 132. Submit Progress Report for the Period Jan 01, 2017 - Dec 31, 2017 05/31/2018 06/29/2018
Provide Information to RM&E Leads for RPA Report D: 202. Support RM&E Leads with CY2017 BiOp RPA Report 03/15/2018 03/30/2018
Share Project Information E: 191. Share Project Activities Updates with Project Partners 06/30/2018 06/29/2018
Environmental Compliance is Complete F: 165. Environmental Compliance 06/30/2018 06/29/2018
Conceptual Site Plans for at Least 1 Future Habitat Enhancement Project G: 114. Identify and Develop Potential Steelhead Habitat Restoration Projects 06/30/2018 06/29/2018
Temperature, Stage, and DO Data Collected, Stored in Water Quality Database H: 157. Water Quality and Stage Monitoring 06/30/2018 06/29/2018
Plant Native Vegetation - Wind River at Stabler Bend I: 47. Plant Vegetation - Stabler Bend 06/30/2018 05/01/2018
Plant Native Vegetation - Little Wind River J: 47. Plant Vegetation - Little Wind 06/30/2018 05/01/2018
Former Planting Sites Replanted, Maintained, Enhanced K: 198. Enhance Vegetation - Stabler Bend and Little Wind 06/30/2018 06/01/2018
Complete Site Enhancement at Blue Hole L: 55. Enhance Steelhead Habitat at Blue Hole 06/30/2018 06/29/2018
Advance Project Design and Permitting M: 175. Produce Habitat Project Design at Little Wind, Phase IV 06/30/2018 06/30/2018

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage and Administer Projects 07/01/2017
B 185 Periodic Status Reports for BPA 07/01/2017
C 132 Submit Progress Report for the Period Jan 01, 2017 - Dec 31, 2017 07/01/2017
D 202 Support RM&E Leads with CY2017 BiOp RPA Report
E 191 Share Project Activities Updates with Project Partners 07/01/2017
F 165 Environmental Compliance 07/01/2017
G 114 Identify and Develop Potential Steelhead Habitat Restoration Projects 07/01/2017
H 157 Water Quality and Stage Monitoring 07/01/2017
I 47 Plant Vegetation - Stabler Bend 07/01/2017
J 47 Plant Vegetation - Little Wind 07/01/2017
K 198 Enhance Vegetation - Stabler Bend and Little Wind 07/01/2017
L 55 Enhance Steelhead Habitat at Blue Hole 07/01/2017
M 175 Produce Habitat Project Design at Little Wind, Phase IV 07/01/2017