Contract 76808: 2010-001-00 EXP COIC ICICLE CREEK FLOW RESTORATION PROJECT
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
76808
Contract Title:
2010-001-00 EXP COIC ICICLE CREEK FLOW RESTORATION PROJECT
Contract Continuation:
Previous: Next:
n/a
  • 83222: 2010-001-00 CAP COIC ICICLE CREEK FLOW RESTORATION PROJECT
Contract Status:
Closed
Contract Description:
CCR-39848:

This contract change will accomplish adding funding to procure materials for the implementation of a pressurized irrigation system. Through this contracting action, the contract will be converted from Expense to Capital.  The contract end date will be extended.  Lastly, additional cultural resources work needs to be completed, including mitigation and an MOA with BPA.

The contractor Washington Water Trust (WWT), its designated agents, sub-consultants and project stakeholders will be available, responsive and collaboratively address contract related issues during the term of the contract. Contract issues include but are not limited to technical, policy, regulatory, project management and associated elements related to the project. Successful execution of this contract is contingent on alignment of the preceding contract issues with the BPI and BPA contracting processes, project management plans, design review protocols (including but not limited to BPA RRT design review, Technical and Design Team guidance, review, input, comments, integration, stakeholder congruence with proposed actions and decisions rendered by 1) the project executive team (BPA, UCSRB, WWT). Arbitration and dispute resolution will occur relative to the following two tier escalation ladder: 1) conference with the project Executive Team and 2) Direct consultation between program managers.
Account Type(s):
Capital
Contract Start Date:
09/21/2017
Contract End Date:
09/20/2019
Current Contract Value:
$123,730
Expenditures:
$123,730

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Coordinate with BPA on the Environmental Compliance Permitting Processes A: 165. Environmental Compliance Coordination w/BPA 09/20/2019 09/20/2019
Proficiently Manage Contract & Project B: 119. Project Managment 09/20/2019 09/20/2019
Coordinate with local and regional stakeholders C: 191. Coordinate with Stakeholders, BPA, UCSRB in the Icicle Watershed 09/20/2018 11/15/2017
Project Design Compliance w/HIP3 D: 175. Coordinate w/BPA to Comply w/HIP3 05/15/2019 05/31/2019
Screen Design Compliance w/HIP3 E: 69. Coordinate w/BPA to Comply w/HIP3 09/20/2019 09/20/2019
Checklist Developed F: 154. Develop Checklist 09/20/2018 09/21/2017
Track Progress Toward Water Protection G: 164. Track Progress for Water Protection 09/20/2019 09/20/2019
Pipeline and Pump Station Design Compliance w/HIP3 H: 203. Perform Pre-implementation Tasks 05/15/2019 05/31/2019
Pipeline, lateral and appurtenances. K: 203. Purchase Pipe 09/20/2019
MOA and Site Development Plan incorporating all mitigation actions. L: 165. Environmental Compliance Coordination with BPA 12/31/2018 12/01/2018
Fish Screen Installed. M: 69. NMFS-Compliant Self Cleaning Fish Screen (submerged cone, air blast, or equivalent) 09/20/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 2 instances of WE 203 Install Water Conservation Measure
  • 2 instances of WE 69 Install Fish Screen
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 1 instance of WE 164 Acquire Water Instream

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance Coordination w/BPA 07/01/2017
B 119 Project Managment 07/01/2017
C 191 Coordinate with Stakeholders, BPA, UCSRB in the Icicle Watershed 07/01/2017
D 175 Coordinate w/BPA to Comply w/HIP3
E 69 Coordinate w/BPA to Comply w/HIP3
F 154 Develop Checklist 07/01/2017
G 164 Track Progress for Water Protection
H 203 Perform Pre-implementation Tasks
I 185 Periodic Status Reports for BPA 07/01/2017
J 132 (no report is required per COTR) 09/21/2017
K 203 Purchase Pipe
L 165 Environmental Compliance Coordination with BPA 09/21/2017
M 69 NMFS-Compliant Self Cleaning Fish Screen (submerged cone, air blast, or equivalent)