Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 80023: 2010-073-00 EXP USFWS CWTD TRANSLOCATIONS
Project Number:
Title:
Columbia Land Trust Estuarine Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia River Estuary Columbia Estuary 50.00%
Elochoman 5.00%
Grays 5.00%
Lower Columbia Columbia Lower 30.00%
Kalama 5.00%
Sandy 5.00%
Contract Number:
80023
Contract Title:
2010-073-00 EXP USFWS CWTD TRANSLOCATIONS
Contract Continuation:
Previous: Next:
n/a
  • 83590: 2010-073-00 EXP USFWS CWTD TRANSLOCATIONS (USFWS)
Contract Status:
Closed
Contract Description:
Julia Butler Hansen Refuge for the Columbian White-tailed Deer (JBH Refuge) was established to conserve Columbian White-tailed Deer (CWTD). The Tenasillahe Island Unit supports one of two “protected” and “viable” subpopulations of CWTD, which facilitated the US Fish and Wildlife Service’s (Service) reclassification of the CWTD from endangered to threatened status in 2016. The subpopulation on Tenasillahe Island Unit currently exceeds the Refuge’s management goals.  Bonneville Power Administration will provide funding to JBH Refuge to further recovery of the species, by translocating up to 50 deer from Tenasillahe Island to Columbia Stock Ranch (CSR) to establish a new subpopulation of CWTD.
Account Type(s):
Expense
Contract Start Date:
08/01/2018
Contract End Date:
10/31/2019
Current Contract Value:
$203,843
Expenditures:
$203,843

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Iaa
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Anne Creason Bonneville Power Administration Yes COR amcreason@bpa.gov (503) 230-3859
Jackie Ferrier US Fish and Wildlife Service (USFWS) Yes Supervisor jackie_ferrier@fws.gov
Paul Meyers US Fish and Wildlife Service (USFWS) Yes Contract Manager paul_meyers@fws.gov (360) 795-3915
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration A: 119. Administrative tasks for BPA 07/31/2019 09/30/2019
Environmental compliance documentation B: 165. Environmental Compliance 07/31/2019 08/02/2019
Translocate and monitor up to 30 deer D: 190. Translocate CWTD from Tenasillahe Island to Columbia Stock Ranch 10/31/2019
Completed Annual Report E: 132. Submit Progress Report for the period (AUG 2018) to (JUL 2019) 10/31/2019 10/31/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Administrative tasks for BPA 08/01/2018
B 165 Environmental Compliance 08/01/2018
C 185 Periodic Status Reports for BPA 08/01/2018
D 190 Translocate CWTD from Tenasillahe Island to Columbia Stock Ranch
E 132 Submit Progress Report for the period (AUG 2018) to (JUL 2019) 08/01/2018