| All administrative tasks fulfilled with timely quality products |
B: 119. Admin oversight for Exp Activities |
|
10/31/2019 |
10/31/2019 |
| Environmental Compliance complete |
C: 165. Environmental Compliance Documentation for all Exp actions |
|
10/31/2019 |
10/31/2019 |
| Annual Progress Report |
D: 132. Annual Progress Report (11-1-17 to 10-31-18) |
|
03/15/2019 |
03/27/2019 |
| Youth and Adult Presentations |
E: 99. Youth and adult presentations |
|
10/31/2019 |
10/31/2019 |
| Lampson Side Channel Entrance Final Design |
F: 175. Lampson Side Channel Entrance Final Design and Permitting |
|
10/31/2019 |
10/31/2019 |
| North Fork WW Push Up Dams Alternatives Assessment/Initial Design Complete |
G: 175. North Fork WW Push Up Dams Alternatives Assessment/Initial Design - NF8 |
|
10/31/2019 |
|
| North Fork WW Push Up Dam NF8 Alternatives Designed |
H: 175. North Fork WW Push Up Dams Alternatives Assessment/Initial Design - NF7 |
|
10/31/2019 |
|
| Couse Creek Fish Passage Construction Complete |
I: 184. Couse Creek Fish Passage Construction |
|
10/31/2019 |
|
| Walla Walla River at Tumulum Bridge Flow Gauge |
J: 148. Walla Walla River Flow Gauge at Tumulum Bridge |
|
10/31/2019 |
10/31/2019 |
| Eastside Recharge Delivery ASR Designs completed. |
K: 175. Eastside Recharge Delivery ASR Design |
|
10/31/2019 |
|
| Surface Water Data collected for fish passage and habitat water monitoring |
L: 157. Collect Surface Water Data for Fish Passage and Flow Restoration |
|
10/31/2019 |
10/31/2019 |
| Produce accessible, error-checked datasets |
M: 157. Collect Water Temperature Data for Fish Passage and Flow Restoration |
|
10/31/2019 |
10/31/2019 |
| Updated WWBWC Database |
N: 160. Maintain Surface Water Database for Water Monitoring |
|
10/31/2019 |
10/31/2019 |
| Maintain water temperature database |
O: 160. Maintain Water Temperature Database for Fish Habitat Monitoring |
|
10/31/2019 |
10/31/2019 |
| Results on the success of the Recharge Project, On-farm Efficiency, and Water Management |
P: 162. Analyze Surface Water Data for Fish Habitat Monitoring |
|
10/31/2019 |
10/31/2019 |
| Results on the success of the Recharge Project, On-farm Efficiency, and Water Management |
Q: 162. Analyze Water Temperature Data for Fish Habitat Monitoring |
|
10/31/2019 |
10/31/2019 |
| Watershed coordination |
R: 191. Walla Walla basin watershed coordination |
|
10/31/2019 |
10/31/2019 |
| Develop or update (out-year) prioritized Habitat Project list: upload to Pisces |
S: 114. Identify and select projects for Walla Walla Basin |
|
05/03/2019 |
05/03/2019 |