| Environmental and Cultural Compliance |
A: 165. Produce Environmental Compliance for Projects |
|
09/30/2028 |
|
| WDFW representation of the Lower Columbia River Estuary in internal WDFW prioritization and coordination meetings, as well as external prioritization and coordination meetings. |
B: 189. Participation in WFDW/BPA Coordination Internally and Externally |
|
09/30/2028 |
|
| Proceed with the next steps identified by team |
C: 191. Continue Conversations around a Lower Columbia River Programmatic Funding Strategy |
|
09/30/2028 |
|
| Regional Data Sharing and CEERP Coordination Meetings |
D: 191. Participate in Regional Data Sharing; CEERP Coordination |
|
09/30/2028 |
|
| Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish |
E: 114. Meet with stakeholders when approached with new project |
|
09/30/2028 |
|
| Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish |
F: 114. Chinook River -- Initial Feasibility |
|
09/30/2028 |
|
| Maintain habitat through tide gate operations and habitat maintenance |
G: 186. Chinook River -- Tide Gate Management |
|
09/30/2028 |
|
| Invasive species removed from Chinook Estuary with mechanical means |
H: 199. Chinook River -- Remove Invasive Species |
|
09/30/2028 |
|
| Host 3-4 meetings in the community of Chinook with private landowners and restoration practitioners |
I: 99. Chinook River -- Outreach and Education |
|
09/30/2028 |
|
| Alternatives Evaluation and 30% Design |
J: 114. Shillapoo (south unit) -- Feasibility |
|
09/30/2028 |
|
| Document outreach process |
K: 99. Shillapoo (south unit) -- Internal, Public, and stakeholder outreach |
|
09/30/2028 |
|
| Produce accessible, error-checked datasets |
L: 157. Shillapoo (south unit) -- Collect Pre-restoration groundwater data |
|
09/30/2028 |
|
| Deliverable: An accessible, error-checked data set with metadata |
M: 162. Shillapoo (south unit) -- Analyze pre-restoration groundwater data |
|
09/30/2028 |
|
| Host 2-4 Diking District/Public Meetings in the Skamokawa |
N: 99. Skomokawa - 1-2 more diking district/public meetings |
|
09/30/2028 |
|
| 30-90% Design - Skamokawa Creek |
O: 175. Skomokawa - 30-90% Design |
|
09/30/2028 |
|
| Produce accessible, error-checked datasets |
P: 157. Skomokawa - Collecting pre-restoration monitoring data |
|
09/30/2028 |
|
| Effective implementation management and timely contract administration |
Q: 119. BPA administrative tasks for contract |
|
09/30/2028 |
|
| Upload Year 1 Progress Report |
R: 132. Submit Year 1 Progress Report - October 1, 2025 to September 30, 2026 |
|
12/31/2026 |
|
| Upload Year 2 Progress Report |
S: 132. Submit Year 2 Progress Report - October 1, 2026 to September 30, 2027 |
|
12/31/2027 |
|