| Province | Subbasin | % |
|---|---|---|
| Basinwide | - | 100.00% |
| Previous: | Next: |
|---|---|
| n/a |
* Expenditures data includes accruals and are based on data through 31-Oct-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Environmental Compliance Complete. | B: 165. Complete all necessary EC | 07/01/2027 | ||
| Completed Progress (Annual) Report | C: 132. Submit Annual Report for the period October 2025 thru September 2027 | 09/30/2027 | ||
| Effective implementation management and timely contract administration | D: 119. Routine administration of contract | 09/30/2027 | ||
| Final design complete for Palisades Creek Weir. | E: 175. Design Palisades Creek Weir-South Fork Snake River | 04/15/2026 | ||
| Complete final design for Rainey Creek Weir. | F: 175. Design Rainey Creek Weir-South Fork Snake River | 05/15/2026 | ||
| Complete construction of the Palisades Creek Weir. | G: 184. Construct Palisades Creek Weir-South Fork Snake River | 01/31/2027 | ||
| Complete construction of Rainey Creek Weir | H: 184. Construct Rainey Creek Weir-South Fork Snake River | 12/31/2026 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Cutthroat Trout, Yellowstone (O. c. bouvieri) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | |||||||
| B | 165 | Complete all necessary EC | |||||||
| C | 132 | Submit Annual Report for the period October 2025 thru September 2027 | |||||||
| D | 119 | Routine administration of contract | |||||||
| E | 175 | Design Palisades Creek Weir-South Fork Snake River | |||||||
| F | 175 | Design Rainey Creek Weir-South Fork Snake River | |||||||
| G | 184 | Construct Palisades Creek Weir-South Fork Snake River | |||||||
| H | 184 | Construct Rainey Creek Weir-South Fork Snake River |