| Effective implementation management and timely contract administration |
A: 119. Manage and administer projects |
|
04/30/2028 |
|
| Prioritized projects based on the most current data |
B: 114. Identify, evaluate and select new project sites where management rights can be gained to allow for valley bottom, wetland and drainage restoration. |
|
04/30/2028 |
|
| Prioritized projects based on the most current data |
C: 114. Identify and select restoration projects within Hangman Initiative Project Sites |
|
10/01/2027 |
|
| Completed Environmental Compliance as Needed |
D: 165. NEPA analysis and documentation as needed |
|
04/30/2028 |
|
| Coordination with Watershed and Subbasin Restoration Partners |
F: 191. Coordinate with other Tribal Partners and local agencies to maximize restoration benefits |
|
04/30/2028 |
|
| Comprehensive hydrogeologic dataset, including continuous groundwater-level records, mapped distribution of wells and springs and a detailed geologic stratigraphic column. |
G: 115. Assess the Affect of Shallow Aquifer Drainage on Hangman Stream Flow |
|
04/30/2028 |
|
| Maintain Database of Culvert locations, condition and replacement priority |
H: 115. Complete Culvert and Road Assessments within tributaries of Hangman Creek that contain Priority 1 Streams |
|
04/30/2028 |
|
| Report detailing strategy for implementing restoration actions in Priority 1 Tributaries in the Hangman Watershed. |
I: 115. Conduct Channel and Riparian Assessments in Priority 1 Streams |
|
04/30/2028 |
|
| Annually Update Project List |
J: 161. Update Priority 1 Redband Habitat Improvement Strategy with the most recent data from fish habitat assessments and surveys in Hangman Creek |
|
04/30/2028 |
|
| Produce design and Permitting for Culvert Replacement |
K: 175. Produce Designs for Culvert Replacements that are intended to improve redband access to Priority 1 Stream Reaches |
|
04/30/2028 |
|
| Complete Culvert Project and Provide Final Metrics |
L: 184. Install new culverts that improve redband access to Priority 1 Streams according to designs specific to the each location |
|
04/30/2028 |
|
| Produce Final Project Ready Design and Permits |
M: 175. Produce Designs for large woody debris (LWD) additions to improve redband habitats in Priority 1 Streams |
|
04/30/2028 |
|
| Complete Projects and Provide Final Metrics |
N: 29. Install LWD structures in specified locations according to designs intended to improve redband habitats in Priority 1 Streams |
|
04/30/2028 |
|
| Provide Final Metrics |
O: 29. Add spawning gravels to Priority 1 Stream Reaches as designated in the Fish Habitat Improvement Strategy |
|
04/30/2028 |
|
| Complete Planting and Provide Final Metrics |
P: 47. Plant vegetation along Priority 1 Stream Reaches as specified in the Fish Habitat Improvement Strategy |
|
04/30/2028 |
|
| Construction Management Complete |
Q: 100. Construction Management of hnleq’ntsutis he nehchen project. |
|
02/29/2028 |
|
| Railroad berm removal |
R: 180. Remove Railway Berms on T1030/A342 |
|
04/30/2028 |
|
| Completed channel construction |
S: 30. Realign Channel and Connect to Floodplain - hnleq’ntsutis he nehchen |
|
04/28/2028 |
|
| Hardwoods and Conifers planted |
T: 47. Plant Vegetation on hnleq’ntsutis he nehchen properties |
|
04/30/2028 |
|
| Deliverables |
U: 175. Produce Feasibility Design in Hangman Creek Ending at Andrew Springs Creek |
|
04/28/2028 |
|
| 70% stream restoration design completion |
V: 175. Produce design for new properties on Hangman Creek ending at HWY 95 |
|
04/28/2028 |
|
| Deliverables |
W: 47. Plant Vegetation Along New Constructed Channel within Shaw Property |
|
04/30/2028 |
|
| Native grass planting |
X: 47. Plant native grasses within the narrow drainage bottoms north of Old Sanders Road that remain within the BPA held Conservation Easement established in 2005. |
|
04/30/2028 |
|
| Approximately 1.2 Miles stream bank on the North Fork of Rock Creek planted with willow. |
Y: 47. Plant Willows in the along approximately 1.2 miles of the North Fork of Rock Creek |
|
04/30/2028 |
|
| Vegetation Maintained in the Hangman Watershed |
Z: 198. Maintain vegetation planted in previous years within the Hangman Valley Bottom and select tributaries. |
|
04/28/2028 |
|
| Completed Land Management Plans for BPA Mitigation properties. |
AA: 193. Produce Management Plan for the BPA Mitigation Property in the Hangman Watershed |
|
04/30/2028 |
|
| Produce accessible, error-checked datasets |
AB: 157. Monitor water temperature in Hangman Creek |
|
04/28/2028 |
|
| Deliverable: An accessible, error-checked data set with metadata |
AC: 162. Analyze stream temperature data in Hangman Creek |
|
01/14/2028 |
|
| Completed Hanging Tree Monument Property Management Plan |
AD: 174. Produce a manage plan for the Hanging Tree Monument Project Site on the Mainstem of Hangman Creek |
|
04/30/2028 |
|
| Close on Property Purchase |
AE: 172. Conduct Pre-Acquisition Activities for Property and/or Easement Acquisition of Lands within Priority Areas Identified in Appropriate Prioritization Plans. |
|
04/30/2028 |
|
| Completed Progress (Annual) Report |
AF: 132. Complete report of activities, successes, findings and resulting adaptive management changes for the period 5/1/2026 to 4/30/2028. |
|
04/30/2028 |
|