Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 84068 REL 28: 2007-402-00 EXP FY26 EXP SBT SNAKE RIVER SOCKEYE M&E/HABITAT
Project Number:
Project Title:
Snake River Sockeye Captive Propagation
Project Stage:
Implementation
Project Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
84068 REL 28
Contract Title:
2007-402-00 EXP FY26 EXP SBT SNAKE RIVER SOCKEYE M&E/HABITAT
Contract Continuation:
Previous: Next:
84068 REL 18: 2007-402-00 EXP SBT SNAKE RIVER SOCKEYE M&E/HABITAT
Contract Status:
Issued
Contract Description:
The goals of the Shoshone Bannock Tribes Sockeye Research Program include to assess habitat limitations as it pertains to Snake River Sockeye Salmon (Oncorhynchus nerka) preservation and recovery, to implement activities necessary to increase and\or reestablish O. nerka productivity in nursery areas in the historic range of Snake River sockeye salmon, and to investigate fish community dynamics in lake nursery areas, including interactions between resident and anadromous O. nerka in present or potential Sawtooth Valley production areas.  We will collaborate with the IDFG to determine release strategies, and assess fish performance from introduction into the lakes to smolt migration through adult returns as well as provide input to the Technical Oversight Committee for annual strategies regarding the fate of returning adults.

FY26 Contract objectives include: 1) monitor limnological parameters of the Sawtooth Valley lakes to assess lake productivity; 2) monitor sockeye salmon smolt migration from the production of wild/residual/captive adults in Pettit and Alturas lakes;  3) monitor the number of mature kokanee spawning in Fishhook and Alturas Lake creeks and estimate fry recruitment in each system; 4) trap and enumerate returning adults to Pettit Lake; 5) conduct Sockeye and kokanee salmon population surveys; 6) evaluate potential competition and predation between stocked juvenile Sockeye Salmon and a variety of fish species in Pettit, and Alturas lakes; and 7) assist IDFG with captive broodstock production activities and supply IDFG with requested RM&E and RPA/BiOp data.  
Account Type(s):
Expense
Contract Start Date:
12/01/2025
Contract End Date:
11/30/2026
Current Contract Value:
$547,924
Expenditures:
$120,573

* Expenditures data includes accruals and are based on data through 28-Feb-2026.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Accrual category:
RM&E
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
NEPA Compliance, IDFG Collection Permit, NOAA and IDEQ permit reports submitted A: 165. NEPA clearance, NOAA/IDEQ/IDFG Permits 11/15/2026
Complete collection of all limnological variables B: 157. Complete data collection for all limnological variables 11/15/2026
Evaluate Sockeye Salmon smolt migration C: 157. Evaluate Sockeye Salmon smolt migration from Pettit and Alturas lakes 11/15/2026
PIT Tag Sockeye Salmon smolts D: 158. PIT Tag Sockeye Salmon smolts 06/18/2026
Complete all adult O. nerka spawning and hydroacoustic surveys E: 157. Estimate O. nerka populations in Sawtooth Valley lakes and creeks 11/15/2026
Complete all milestones associated to analyze/interpret data F: 162. Provide recommendations on lake fertilization and fish stocking based upon summarized data from limnology results and Sockeye population estimates. 11/15/2026
Fertilization/nutrient supplementation of approved selected lake(s) G: 44. Nutrient Enhancement 10/25/2026
Attend and participate in SBSTOC meetings H: 191. Stanley Basin Sockeye Technical Oversight Committee (SBSTOC) Meetings 11/22/2026
Completed Progress (Annual) Report I: 132. Submit Progress Report for the period 1.01.2025 to 12.31.2025 08/15/2026
Effective implementation management and timely contract administration K: 119. Manage and Administer contract associated with SBT Snake River Sockeye Salmon Project 11/30/2026

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 44 Enhance Nutrients in Water Bodies
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 NEPA clearance, NOAA/IDEQ/IDFG Permits
B 157 Complete data collection for all limnological variables
C 157 Evaluate Sockeye Salmon smolt migration from Pettit and Alturas lakes
D 158 PIT Tag Sockeye Salmon smolts
E 157 Estimate O. nerka populations in Sawtooth Valley lakes and creeks
F 162 Provide recommendations on lake fertilization and fish stocking based upon summarized data from limnology results and Sockeye population estimates.
G 44 Nutrient Enhancement
H 191 Stanley Basin Sockeye Technical Oversight Committee (SBSTOC) Meetings
I 132 Submit Progress Report for the period 1.01.2025 to 12.31.2025
J 185 Periodic Status Reports for BPA
K 119 Manage and Administer contract associated with SBT Snake River Sockeye Salmon Project