SOW Report
Contract 87084: 1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Project Number:
Title:
Lolo/Selway River Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
87084
Contract Title:
1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
84370: 1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
  • 89558: 1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
The Lolo Creek Watershed Restoration project (1996-077-02) has been an on-going project of the Nez Perce Tribe Fisheries Watershed Program and BPA since 1996. This unique and successful restoration partnership is implemented through agreements between the Nez Perce - Clearwater National Forests (NPCNFs), Nez Perce Tribe (NPT), and Bonneville Power Administration (BPA). The ultimate goal of the project is to restore the physical and biological characteristics of the watershed to provide quality habitat for anadromous and resident fish species that support the historical, cultural, and economic practices of the Nez Perce Tribe. In 2016, the Lolo Creek project was combined with the Selway River project, a newly funded BiOp effort initiated in 2011 to perform high priority watershed restoration actions in the Selway River watershed.

The Lolo Creek watershed contains proposed critical habitat for listed steelhead trout, potential critical habitat for bull trout, and has moderate habitat potential for Spring Chinook salmon. Restoration in this watershed focuses on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing effects, fish passage barriers, and noxious weed infestations. Fish passage and habitat connectivity actions are prioritized primarily at road/stream crossings on both private and federal land, and native riparian revegetation and continuous riparian protection are also high priority actions.

The Selway River Watershed contains critical habitat for listed steelhead trout, potential critical habitat for bull trout, and has moderate habitat potential for Spring Chinook salmon. Restoration follows a ridge top to ridge top approach with implementation focused on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing effects, aquatic habitat connectivity, and exotic, invasive plant encroachment. The cost share for this project has been contributed by the Nez Perce - Clearwater National Forests who provides approximately 20% match including cash and in-kind contributions. Project planning and implementation responsibilities are also shared with the Nez Perce - Clearwater National Forests.

Completed contract work in the Lolo Watershed includes culvert prioritization and assessment, installation of an off-site water source, 31 culvert replacements, 11 culvert removals, 2600 ft. of stream bank stabilization, 14 large wood structures, 108.5 miles of road decommissioning, 23 miles of fence installation and maintenance, and over 24,000 native riparian trees and shrubs planted.

Completed contract work in the Selway Watershed includes culvert prioritization and assessment, installation of 10 culvert replacements, and 41 miles road decommissioning surveys.  

The following agencies and entities will collaborate with local partners to identify the highest priority locations and a corresponding suite of restorations actions to address critical limiting factors in the Lolo Creek Watershed: BPA, NPT, Nez Perce-Clearwater National Forests, IDFG, IDL, Potlatch Corp., BLM, NRCS, and the county SWCD. This collaborative, inclusive, evidence-based, and strategic process has been ongoing for several years, leading to the development of an Atlas prioritization framework in 2019. The Lolo Atlas framework contains a prioritized list of areas and specific restoration actions to be implemented over the next 10 years or more. The Atlas framework is a living document and is managed adaptively and modified as projects are implemented and as new data and research evidence becomes available to inform restoration.

Projects that have been considered and prioritized through the Atlas process, and that are planned for implementation this contract period, include: addressing fish passage barriers in several creeks; increasing habitat complexity at lower Lolo Creek; design work at the Selway irrigation diversion; and fencing, riparian planting, and invasive plants treatment.
Account Type(s):
Expense
Contract Start Date:
02/01/2021
Contract End Date:
01/31/2022
Current Contract Value:
$601,604
Expenditures:
$601,604

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

Contract(s):

87084

Location: 46.351048° N, -115.760941° E

Dimensions: 4608 x 3456

Contract(s):

87084

Dimensions: 3968 x 2976

Contract(s):

87084

Dimensions: 4608 x 3456

Contract(s):

87084

Dimensions: 2953 x 2137

Contract(s):

87084

Location: 45.995915° N, -114.838911° E

Dimensions: 4608 x 3456

Contract(s):

87084

Dimensions: 2048 x 1536


Full Name Organization Write Permission Contact Role Email Work Phone
Marcie Carter Nez Perce Tribe Yes Supervisor marciec@nezperce.org (208) 621-3534
Elizabeth Eastman Nez Perce Tribe No Technical Contact elizabethe@nezperce.org (208) 621-3558
Arleen Henry Nez Perce Tribe No Technical Contact arleenh@nezperce.org (208) 621-3833
Eric Leitzinger Bonneville Power Administration Yes F&W Approver ejleitzinger@bpa.gov (503) 230-3534
Jennifer Lord Bonneville Power Administration Yes COR jklord@bpa.gov (503) 230-5192
Ed Main Nez Perce Tribe No Technical Contact edwardm@nezperce.org (208) 621-3539
Jennifer McKenna Bonneville Power Administration No CO Assistant jmmckenna@bpa.gov (503) 314-8915
Justin Peterson Nez Perce Tribe Yes Contract Manager justinp@nezperce.org (208) 621-3545
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Emmit Taylor, Jr. Nez Perce Tribe No Technical Contact emmitt@nezperce.org (208) 621-3544
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental Compliance Documentation Submitted to BPA A: 165. Environmental Compliance for Projects on Forest Service Lands 01/31/2022 12/31/2021
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces B: 114. Use ATLAS Matrix to Prioritize and Select Projects 01/31/2022 12/31/2021
Finalize installation of beaver dam analogs and monitor their effectiveness H: 29. Construct Beaver Dam Analogs on Jim Brown and/or Musselshell creeks 09/30/2021 08/31/2021
Install large wood (1-3 wood structures) to help maintain channel configuration and provide additional fish habitat I: 29. Lower Lolo Creek Large Wood Installation 10/31/2021 09/15/2021
Decommission approximately 0.14 mile of road along mainstem Lolo Creek J: 33. Lower Lolo Creek Road Decommissioning 09/30/2021 09/14/2021
Finalize O'Hara Rock Pit Designs L: 175. O'Hara Rock Pit Channel Realignment Design 01/31/2022
Finalize Designs for irrigation improvements at up to 2 diversion structures M: 175. Selway Irrigation Diversion Design 01/31/2022 12/31/2021
Fence Maintained N: 186. Maintain Fence 01/31/2022 12/31/2021
Riparian Planting on previous project sites in the Lolo Creek watershed O: 47. Riparian Planting 01/31/2022 12/31/2021
Treat Exotic Invasive Species P: 199. Treat Exotic Invasive Species on USFS and Private Lands 01/31/2022 12/31/2021
Complete surveys/Complete UAV monitoring flights and submit flight logs Q: 115. Collect stream, meadow, road data/Project monitoring and inventory via UAV (i.e., drone) to develop and prioritize future projects 01/31/2022 12/31/2021
Review of Partner Projects R: 122. Review and Technical Assistance for Proposed Partner Actions 01/31/2022 12/31/2021
Watershed Coordination S: 191. Coordinate with Regional Partners 01/31/2022 12/31/2021
Manage Projects and Administrative duties T: 119. Manage Projects and Administrative duties 01/31/2022 12/31/2021
Attach 2021 Annual Report V: 132. Annual Report February 2021 - January 2022 06/15/2021 06/15/2021
Complete Crocker Creek Design W: 175. Crocker Creek Barrier Replacement Design 01/31/2022 12/31/2021
USFS 5150 Road Improvement Design Survey X: 175. USFS 5150 Road Design Survey 01/31/2022 12/31/2021
Finalize Yoosa Creek Acclimation Site Passage Feasibility Study Y: 175. Yoosa Creek Passage Improvement Feasibility Design 01/31/2022 12/31/2021
Finalize and Submit Geotechnical Survey Report Z: 115. Chamook Road Decommissioning Geo Technical Surveys 01/31/2022 12/31/2021
Finalize O'Hara Bridge Replacement Design AA: 175. O'Hara Creek Bridge Design 01/31/2022 12/31/2021
Finalize Swiftwater Creek Box Culvert Design AB: 175. Swiftwater Creek Box Culvert Passage Improvement Design 01/31/2022
Implement Elk Creek Diversion Design Improvements AC: 208. Elk Creek Irrigation Diversion Upgrades 09/30/2021 09/30/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 115 Produce Inventory or Assessment
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 3 instances of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 7 instances of WE 175 Produce Design
  • 2 instances of WE 208 Irrigation Infrastructure Construction or Replacement
Lamprey, Pacific (Entosphenus tridentata)
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 7 instances of WE 175 Produce Design
  • 1 instance of WE 208 Irrigation Infrastructure Construction or Replacement
Freshwater Mussels
  • 1 instance of WE 175 Produce Design
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance for Projects on Forest Service Lands
B 114 Use ATLAS Matrix to Prioritize and Select Projects
C 85 Mike White Creek Barrier Replacement 01/04/2021
D 30 Mike White Creek Channel Reconstruction
E 85 Crocker Creek Barrier Replacement
F 208 Musselshell Meadow Irrigation Diversion Removal
G 181 Musselshell Meadow Wetland Improvements
H 29 Construct Beaver Dam Analogs on Jim Brown and/or Musselshell creeks 06/01/2021
I 29 Lower Lolo Creek Large Wood Installation 05/26/2021
J 33 Lower Lolo Creek Road Decommissioning 05/26/2021
K 38 USFS Road 5150 Improvement
L 175 O'Hara Rock Pit Channel Realignment Design 01/04/2021
M 175 Selway Irrigation Diversion Design 01/04/2021
N 186 Maintain Fence 01/27/2021
O 47 Riparian Planting 01/27/2021
P 199 Treat Exotic Invasive Species on USFS and Private Lands 01/27/2021
Q 115 Collect stream, meadow, road data/Project monitoring and inventory via UAV (i.e., drone) to develop and prioritize future projects 01/27/2021
R 122 Review and Technical Assistance for Proposed Partner Actions
S 191 Coordinate with Regional Partners
T 119 Manage Projects and Administrative duties
U 185 Periodic Status Reports for BPA
V 132 Annual Report February 2021 - January 2022
W 175 Crocker Creek Barrier Replacement Design 01/04/2021
X 175 USFS 5150 Road Design Survey 01/04/2021
Y 175 Yoosa Creek Passage Improvement Feasibility Design 01/04/2021
Z 115 Chamook Road Decommissioning Geo Technical Surveys 01/04/2021
AA 175 O'Hara Creek Bridge Design 01/04/2021
AB 175 Swiftwater Creek Box Culvert Passage Improvement Design 01/04/2021
AC 208 Elk Creek Irrigation Diversion Upgrades 09/01/2021