| Province | Subbasin | % |
|---|---|---|
| Columbia Plateau | Walla Walla | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Joshua Ashline | Bonneville Power Administration | Yes | COR | jdashline@bpa.gov | (503) 230-3862 |
| Brian Burns | Tri-State Steelheaders | Yes | Contract Manager | brian.burns@tristatesteelheaders.com | (509) 529-3543 |
| Jay Chong | Bonneville Power Administration | Yes | Contracting Officer | jxchong@bpa.gov | (503) 230-4007 |
| Michael Lambert | Umatilla Confederated Tribes (CTUIR) | Yes | Supervisor | mikelambert@ctuir.org | (541) 429-7240 |
| Morgan Morris | Tri-State Steelheaders | Yes | Contract Manager | morgan@tristatesteelheaders.com | (509) 529-3543 |
| JESSICA POWER | Bonneville Power Administration | No | CO Assistant | jdpower@bpa.gov | (503) 230-4023 |
| Jacquelyn Schei | Bonneville Power Administration | No | Env. Compliance Lead | jlschei@bpa.gov | (503) 230-5893 |
| John Skidmore | Bonneville Power Administration | Yes | F&W Approver | jtskidmore@bpa.gov | (503) 230-5494 |
| David Talkington | Tri-State Steelheaders | No | Interested Party | david@tristatesteelheaders.com | (509) 529-3543 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Effective implementation management and timely contract administration | A: 119. Project Administration will be completed in a timely manner | 04/30/2024 | 06/30/2024 | |
| Environmental Compliance Coordination | B: 165. Environmental Compliance Documentation | 04/30/2024 | 06/30/2024 | |
| Plans and cost estimate | C: 175. Mill Creek Gose Street Fish Passage Design | 07/31/2024 | 07/31/2024 | |
| Project Expenses to complete fish passage improvements to 2,100 feet of the concrete channel | D: 184. Mill Creek Concrete Flume Passage Project | 04/30/2024 | 02/11/2024 | |
| Construction Management Complete | E: 100. Mill Creek Concrete Flume Passage Project | 04/01/2024 | 06/30/2024 | |
| Completed Annual Report | G: 132. Submit Progress Report for the period (May 1, 2023 to April 30, 2024) | 07/31/2024 | 07/31/2024 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (Oncorhynchus tshawytscha) - All Populations |
|
| Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
| Trout, Bull (S. confluentus) (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 119 | Project Administration will be completed in a timely manner | |||||||
| B | 165 | Environmental Compliance Documentation | |||||||
| C | 175 | Mill Creek Gose Street Fish Passage Design | 01/10/2024 | ||||||
| D | 184 | Mill Creek Concrete Flume Passage Project | 01/10/2024 | ||||||
| E | 100 | Mill Creek Concrete Flume Passage Project | |||||||
| F | 185 | Periodic Status Reports for BPA | |||||||
| G | 132 | Submit Progress Report for the period (May 1, 2023 to April 30, 2024) |