Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
NEPA compliance documentation completed and submitted | B: 165. Obtain Permits and submit copies to BPA Environmental Compliance group | 09/30/2026 | ||
Effective implementation management and timely contract administration | C: 119. Manage and Administer project associated with RDC Maintenance | 09/30/2027 | ||
Replace Mechanical Building Generator and Fuel Storage | D: 61. UMATILLA HATCHERY – Replace Mechanical Building Generator and Fuel Storage | 09/30/2027 | ||
Replace Ranney Well House Generator and Fuel Storage | E: 61. UMATILLA HATCHERY – Replace Ranney Well House Generator and Fuel Storage | 09/30/2027 | ||
Replace Hatchery Building Roof | F: 61. UMATILLA HATCHERY – Replace Hatchery Building Roof | 09/30/2027 | ||
Mechanical Building Domestic Water System Rehab | G: 61. UMATILLA HATCHERY – Mechanical Building Domestic Water System Rehab | 09/30/2027 | ||
Replace Mechanical Building Roof | H: 61. UMATILLA HATCHERY – Replace Mechanical Building Roof | 09/30/2027 | ||
Replace Ranney Well House Roof | I: 61. UMATILLA HATCHERY – Replace Ranney Wall House Roof | 09/30/2027 | ||
Residence Updates | J: 61. UMATILLA HATCHERY – Residence Updates | 09/30/2027 | ||
Replace Carports with Detached Garages | K: 61. UMATILLA HATCHERY – Replace Carports with Detached Garages | 09/30/2027 | ||
Construct and Install New Chiller System | L: 61. UMATILLA HATCHERY – Replace Chiller System | 09/30/2026 | ||
Produce Annual Operation Plan - Not Required | M: 174. Produce Plan - Not Required under this contract | 09/30/2027 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU |
|
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened) |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | |||||||
B | 165 | Obtain Permits and submit copies to BPA Environmental Compliance group | |||||||
C | 119 | Manage and Administer project associated with RDC Maintenance | |||||||
D | 61 | UMATILLA HATCHERY – Replace Mechanical Building Generator and Fuel Storage | |||||||
E | 61 | UMATILLA HATCHERY – Replace Ranney Well House Generator and Fuel Storage | |||||||
F | 61 | UMATILLA HATCHERY – Replace Hatchery Building Roof | 04/17/2024 | ||||||
G | 61 | UMATILLA HATCHERY – Mechanical Building Domestic Water System Rehab | 04/29/2024 | ||||||
H | 61 | UMATILLA HATCHERY – Replace Mechanical Building Roof | 04/17/2024 | ||||||
I | 61 | UMATILLA HATCHERY – Replace Ranney Wall House Roof | 04/17/2024 | ||||||
J | 61 | UMATILLA HATCHERY – Residence Updates | 04/17/2024 | ||||||
K | 61 | UMATILLA HATCHERY – Replace Carports with Detached Garages | |||||||
L | 61 | UMATILLA HATCHERY – Replace Chiller System | 04/29/2024 | ||||||
M | 174 | Produce Plan - Not Required under this contract | 04/17/2024 | ||||||
N | 132 | Annual Report - Not Required |