Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
RSS Feed for updates to Project 2023-003-00 - Reserves Distribution Clause - Asset Management Follow this via RSS feed. Help setting up RSS feeds?

Project Summary

Project 2023-003-00 - Reserves Distribution Clause - Asset Management
Project Number:
2023-003-00
Title:
Reserves Distribution Clause - Asset Management
Summary:
This project provides a distinct location for contracts that support deferred and non-routine maintenance actions that will be addressed through funds made available under the FY22 Power Reserves Distribution Clause (RDC). Consistent with the Administrator’s January 2023 decision, these funds are intended to address, on an accelerated, one-time basis, high priority maintenance needs of existing assets.

This project contains one contract for each sponsor (13 in total). Some contracts address deferred and non-routine maintenance actions at multiple facilities. The specific maintenance action and facility is specified at the WE level. EFW leadership has targeted complete RDC execution by the end of FY28. Most contracts have a performance period of 2-3 years but some may be exteneded if necessary to accomplish all tasks.
Proposer:
Proponent Orgs:
Bonneville Power Administration (Govt - Federal)
Starting FY:
2023
Ending FY:
2025
BPA PM:
Stage:
Implementation - Project Status Report
Area:
Province Subbasin %
Basinwide - 100.00%
Purpose:
Artificial Production
Emphasis:
Supplementation
Focal Species:
Species Benefit:
Anadromous: 75.0%   Resident: 25.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

No photos have been uploaded yet for this Project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

Decided Budget Transfers  (FY2022 - FY2024)

Acct FY Acct Type Amount Fund Budget Decision Date
FY2023 Expense $1 From: Rate Distribution Clause (RDC) - Asset Management Add $1 to 2023-003-00 RDC--3/22/2023 03/22/2023

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2023   DRAFT
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2022

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
CR-363941 SOW Idaho Department of Fish and Game (IDFG) 2023-003-00 EXP IDFG RDC MAINTENANCE Pending $1 8/1/2023 - 7/31/2026
CR-364118 SOW Colville Confederated Tribes 2000-100-00 EXP CTCR RDC MAINTENANCE Pending $1 8/1/2023 - 7/31/2026
CR-364265 SOW Washington Department of Fish and Wildlife (WDFW) 2023-003-00 EXP WDFW RDC MAINTENANCE Pending $1 8/1/2023 - 7/31/2026
CR-364864 SOW Umatilla Confederated Tribes (CTUIR) 2023-003-00 EXP CTUIR RDC MAINTENANCE Pending $1 8/1/2023 - 7/31/2026
CR-364884 SOW Nez Perce Tribe 2023-003-00 EXP NPT RDC MAINTENANCE Pending $1 8/1/2023 - 7/31/2026
CR-364885 SOW Oregon Department of Fish and Wildlife 2023-003-00 EXP ODFW RDC MAINTENANCE Pending $1 8/1/2023 - 7/31/2026
CR-364904 SOW Spokane Tribe 2023-003-00 EXP STOI RDC MAINTENANCE Pending $1 8/1/2023 - 7/31/2026
CR-364906 SOW Confederated Tribes of Warm Springs 2023-003-00 EXP CTWS RDC MAINTENANCE Pending $1 8/1/2023 - 7/31/2025
CR-364917 SOW 2000-100-0000 EXP MFWP RDC Pending $1 8/1/2023 - 7/31/2024
CR-365217 SOW 2023-003-00 EXP YN RDC MAINTENANCE Pending $1 8/1/2023 - 7/31/2025
CR-365220 SOW Westland Irrigation District 2023-003-00 EXP WID RDC MAINTENANCE Pending $1 9/1/2023 - 8/31/2025



Annual Progress Reports
Expected (since FY2004):0
Completed:0
On time:0
Status Reports
Completed:0
On time:0
Avg Days Late:None



The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

No assessments are available for this project.
Project Relationships: None

Name Role Organization
Andrew Traylor Project Manager Bonneville Power Administration
Peter Lofy Supervisor Bonneville Power Administration
Maureen Kavanagh Project SME Bonneville Power Administration
Mary Haight Interested Party Bonneville Power Administration
Jonathan McCloud Project SME Bonneville Power Administration
Eric McOmie Project SME Bonneville Power Administration
Michelle O'Malley Project SME Bonneville Power Administration
Carlos Matthew Project SME Bonneville Power Administration
Carolyn Sharp Env. Compliance Lead Bonneville Power Administration
Edward Gresh Env. Compliance Lead Bonneville Power Administration
Mark Fritsch Project Lead Northwest Power and Conservation Council