| Province | Subbasin | % |
|---|---|---|
| Blue Mountain | Grande Ronde | 100.00% |
| Previous: | Next: |
|---|---|
| n/a |
* Expenditures data includes accruals and are based on data through 31-Oct-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Environmental Permitting | A: 165. Complete and/or initiate Environmental Permitting for Project Activities | 12/31/2025 | ||
| Complete Fish Ladder at RM 42.5 Catherine Creek Acclimation Facility Construction | B: 184. Construct Fish Ladder on CC RM42.5 Catherine Creek Acclimation Facility | 12/31/2026 | ||
| Construction Management Complete | C: 100. Provide construction oversight and observation | 12/31/2026 | ||
| Effective implementation management and timely contract administration | D: 119. Project/Contract Administration | 12/31/2027 | ||
| Completion Report for Catherine Creek 42.5 Completed and Uploaded | E: 132. Catherine Creek RM 42.5 Fish Ladder Completion Report | 12/31/2027 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Lamprey, Pacific (Entosphenus tridentata) |
|
| Freshwater Mussels |
|
| Trout, Bull (S. confluentus) (Threatened) |
|
| Trout, Interior Redband (O. mykiss gairdnerii) |
|
| Whitefish, Mountain (Prosopium williamsoni) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Complete and/or initiate Environmental Permitting for Project Activities | |||||||
| B | 184 | Construct Fish Ladder on CC RM42.5 Catherine Creek Acclimation Facility | 09/23/2025 | ||||||
| C | 100 | Provide construction oversight and observation | |||||||
| D | 119 | Project/Contract Administration | |||||||
| E | 132 | Catherine Creek RM 42.5 Fish Ladder Completion Report | |||||||
| F | 185 | Quarterly Status Reports |