Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 92647: 2010-004-00 EXP CREST ESTUARY HABITAT RESTORATION (CREST)
Project Number:
Title:
CREST Estuary Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia River Estuary Columbia Estuary 100.00%
Contract Number:
92647
Contract Title:
2010-004-00 EXP CREST ESTUARY HABITAT RESTORATION (CREST)
Contract Continuation:
Previous: Next:
88130: 2010-004-00 EXP CREST ESTUARY HABITAT RESTORATION (CREST)
Contract Status:
Issued
Contract Description:
CREST proposes to continue to implement estuary habitat restoration projects during this contract period. Projects developed, designed, and permitted during previous contract periods will move to construction. CREST will continue to develop and design BPA-approved new restoration projects working with landowners, stakeholders, and subcontracted design and engineering consultants. CREST will also continue to invest staff time in community outreach and project development including participating in regional meetings with BPA, the Corps, as well as partner coordination forums such as the Estuary Partnership's Science Work Group (SWG). CREST biologists will conduct Level 3 pre and post project evaluation (Action Effectiveness Monitoring; AEMR) at our restoration sites in coordination with partners and the Columbia Estuary Ecosystem Restoration Program (CEERP).  

Restoration of estuary habitat focuses on habitat opportunity, capacity, and realized function critical to the recovery of threatened/endangered salmon utilizing the Columbia River Estuary. CREST Habitat Restoration Program Deliverables include:
    1) Development of BPA-approved estuary habitat restoration projects.
    2) Presenting and prioritizing restoration projects based on guidance from BPA and the Expert Regional Technical Group (ERTG)
    3) Incorporating design feedback from the ERTG, Project Review Committee (PRC) and partners.
    4) Design, permit, and implementation of 2-5 estuarine restoration projects each year.
    5) Conduct CEERP Level 3 Action Effectiveness Monitoring and Research (AEMR) of restoration projects in coordination with regional partners.

The following projects are currently in full design, engineering, and permitting and will move to construction in 2023 and 2024:

• Wolf Bay: This project will create two new openings through a large railroad berm, opening up 44 acres of floodplain habitat in Reach B of the lower Columbia River. New channel openings, riparian plantings, and other habitat improvements are planned for the site
• South Tongue Point: Project will create 6 new tidal channel networks, a 1/2 mile flow-through side channel, and various other side channel extensions.
• Palensky Wildlife Corridor: Continuing on the recently completed Palensky restoration project, this wildlife corridor will focus on creating a safe migratory route underneath Hwy 30 for amphibians to transit between the uplands of Forest Park and the floodplain wetlands of the Palensky Wildlife Area: A 54" diameter culvert with native substrate and light boxes will be installed underneath the highway. 600 linear feet of directional wall will be constructed to direct migratory wildlife towards the new underpass.
• Agency Creek: Project will install a new 40' long bridge into the 22 acre site. Four breaches throughout an existing levee to provide better floodplain connectivity across the site. Wetland and riparian plantings.
• Warren Slough: A new 60' long bridge will be installed to provide full fish passage to the 22 acres of floodplain habitat. Wetland and riparian plantings to improve wetland function.


The following projects are currently in feasibility and will begin design, engineering, and permitting phases and will move to construction in 2025-2028:

• Carr Slough: Designs for the Carr Slough project will occur in 2023 and 2024. This project will entail breaching the existing railroad berm to create full fish access and hydrologic connectivity to approximately 121 acres of floodplain wetland habitat directly off of the mainstem Columbia River. Other project actions include creation of additional tidal channels, increased channel sinousity, marshplain lowering, and riparian and emergent plantings.
• Netul Landing: Designs for the Netul Landing project will be finalized in 2023. The project involves breaching an existing levee, creation of new tidal channel, new culverts, and construction of a setback levee. The project will open up full fish access to 24 acres of floodplain habitat along the Lewis and Clark River.
• Toaheedliini: Designs for the Toaheedliini project will be completed during 2023 and 2024. Restoration actions for this project will include removing sections of the deauthorized levee along the Walluski River in multiple locations to an elevation that matches the interior marshplain elevation. Additional excavation will also occur in the interior of the wetland to enhance the wetland channel network to further improve tidal connectivity and fish access. The site will be revegetated with native plants following construction.
• Hogan Ranch: Designs for Hogan Ranch will occur during 2023 and 2024. Restoration treatments include new tidal channels, installation of bridges, and marshplain lowering to expand floodplain wetland habitat.
• Deep River/Mint Farm: Designs for Deep River/Mint Farm will occur during 2023 and 2024. Restoration actions include levee breaches, installation of bridges, construction of a setback levee, filling of artificial channels, and marshplain plantings and enhancements.
• Crosel Creek: Designs to occur in 2024 and 2025. Project will focus on wetland enhancement and reconnection of historic tidal channels throughout the 55 acre site.
• Colewort Creek: Ph3: Designs to commence in 2024 and 2025. Restoration actions include installation of new bridge or large box culvert, removal of sections of levee, and reconnection of tidal channels.
• Aaron/McNary: Designs to occur in 2023 through 2025. Restoration actions include breaching multiple new openings into the 386 acre site, construction of new bridges, excavation of tidal channels, and marshplain treatments.

CREST is also pursuing various projects at the feasibility design stage. These projects include South Crane Lake, Fort Stevens, Clatsop Fairgrounds, Malarkey Ranch, and Mansfield/Mafre.

CREST will pursue cost share for project engineering and construction during this contract period from the National Park Service, Oregon Watershed Enhancement Board, Salmon Recovery Funding Board, United States Fish and Wildlife Service, National Oceanic and Atmospheric Administration, Lower Columbia River Estuary Partnership, and other funding sources.  

Within this contract, major work elements are directly related to implementation of previously designed projects and on engineering and permitting for outyear projects. Additional actions focus on action effectiveness monitoring, community outreach and project development.  

Projects in development will be subject to review by the Estuary Partnership's Project Review Committee (PRC) at 30% design and review and assignment of project benefits by the Expert Regional Technical Group (ERTG) at 60% design.  All projects in the estuary are also subject to cost benefit analysis and approval by BPA.  Each of the projects CREST is proposing during this contract undergoes a cost/PBU preliminary review and final scoring by ERTG.  If at any time during the scientific review and the ERTG process it is determined that proposed restoration projects do not meet BPA criteria for implementation, CREST will work with BPA to address these issues.

Post project evaluation (Level 3 AEMR) will be conducted by CREST biologists at many projects including: North Unit: Ph1, Gnat Creek: Ph2, Karlson Island, North Unit: Ph2, Sharnelle-Fee, Bear/Mary/Ferris, Dairy Creek, Government Island, McCarthy: Ph2, John Day Crossing, West Sand Island, Woodland Islands, Hungry Harbor, Palensky, Dalton Lake, South Tongue Point, and Aldrich Point.

Both pre and post project monitoring will be conducted at Wolf Bay, Warren Slough, and Agency Creek.  Pre project monitoring at Toaheedliini, Carr Slough, Netul Landing, Hogan Ranch, Mint Farm, Crosel Creek, Colewort: Ph3, and Aaron/McNary will occur during this contract period.  Project monitoring is used at restoration sites to better quantify use and habitat lift for individual restoration sites and to inform benefits of restoration actions at projects in development.
Account Type(s):
Expense
Contract Start Date:
07/01/2023
Contract End Date:
06/30/2025
Current Contract Value:
$6,279,217
Expenditures:
$1,568,694

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Obtain and provide BPA with Environmental Compliance Documentation B: 165. Produce EC for projects 06/30/2025
Effective implementation management and timely contract administration C: 119. Manage and Administer Projects 06/30/2025
Work With Landowners and WWR if approached about potential project D: 114. Meet with stakeholders when approached with new project 06/30/2025
Regional Data Sharing and CEERP Coordination Meetings E: 191. Participate in Regional Data Sharing; CEERP Coordination 06/30/2025
Collect pre-construction Level 3 AEMR data F: 157. AEMR (Level 3): Collect PRE-Construction AEMR Level 3 data 06/30/2025
Collect Post-construction Level 2 & Level 3 AEMR data G: 157. AEMR (Level 3): Collect POST-Construction AEMR Level 3 data 06/30/2025
Collect Pre- and Post-construction Level 3 AEMR data H: 157. AEMR (Level 3): Collect PRE & POST-Construction AEMR Level 3 data 06/30/2025
Deliverable: An accessible, error-checked data set with metadata I: 162. Analyze Level 3 AEMR Data 06/30/2025
Completed Annual Report to BPA-- July 2022-June 2023 L: 132. Submit Annual Progress Report for the period (July 2022) to (June 2023) 07/15/2023 07/14/2023
Completed Annual Report--July 2023--June 2024 M: 132. Submit Annual Progress Report for the period (July 2023) to (June 2024) 07/15/2024
Initiate discussions with landowner and preliminary feasibility work N: 114. MALARKEY RANCH - COORDINATION with Stakeholders/Partners 06/30/2025
Initiate discussions with landowner and preliminary feasibility work O: 114. MANSFIELD/MAFRE - COORDINATION with Stakeholders/Partners 06/30/2025
Conduct Feasibility Work for FORT STEVENS project P: 114. FORT STEVENS - FEASIBILITY 06/30/2025
Conduct Feasibility Work for SOUTH CRANE LAKE project Q: 114. SOUTH CRANE LAKE - FEASIBILITY 06/30/2025
Conduct Feasibility Work for CLATSOP FAIRGROUNDS project R: 114. CLATSOP FAIRGROUNDS - FEASIBILITY 06/30/2025
CARR SLOUGH-- Design S: 175. CARR SLOUGH - DESIGN--100% 06/30/2025
TOAHEEDLIINI-- Design T: 175. TOAHEEDLIINI - DESIGN--100% 03/31/2025
HOGAN RANCH-- Design U: 175. HOGAN RANCH - DESIGN--100% 06/30/2025
DEEP RIVER/MINT FARM-- Design V: 175. DEEP RIVER/MINT FARM TIDAL RECONNECTIONS - DESIGN--100% 06/30/2025
CROSEL CREEK-- Design W: 175. CROSEL CREEK - DESIGN--100% 06/30/2025
COLEWORT CREEK Ph3--Design X: 175. COLEWORT CREEK: PHASE 3 - DESIGN--100% 06/30/2025
AARON/MCNARY-- Designs Y: 175. AARON/MCNARY - DESIGN--100% 06/30/2025
NETUL LANDING-- Design Z: 175. NETUL LANDING - DESIGN--100% 06/30/2025
Government Island-- Native Plant Revegetation AA: 47. GOVERNMENT ISLAND- CONSTRUCTION--Plantings 03/31/2025
Woodland Islands--Native Plant Revegetation AB: 47. WOODLAND ISLANDS - CONSTRUCTION--Plantings 03/31/2024 03/31/2024
Palensky--Plantings AC: 47. PALENSKY - FLOODPLAIN CONSTRUCTION--Plantings 03/31/2025
Dalton Lake--Plantings AD: 47. DALTON LAKE - CONSTRUCTION--Plantings 03/31/2025
Aldrich Point--Revegetation AE: 47. ALDRICH POINT - CONSTRUCTION--Plantings 03/31/2025
South Tongue Point--Completed channel construction AI: 30. SOUTH TONGUE POINT - CONSTRUCTION--Create Tidal Channels 10/31/2023 11/15/2023
South Tongue Point--Enhance Floodplain Habitat AJ: 180. SOUTH TONGUE POINT - CONSTRUCTION--Enhance Floodplain 10/31/2023 11/15/2023
South Tongue Point--Revegetation AK: 47. SOUTH TONGUE POINT - CONSTRUCTION--Plant Vegetation 03/31/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 4 instances of WE 30 Realign, Connect, and/or Create Channel
  • 9 instances of WE 47 Plant Vegetation
  • 2 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 3 instances of WE 184 Install Fish Passage Structure
  • 6 instances of WE 114 Identify and Select Projects
  • 8 instances of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Chum (Oncorhynchus keta) - Columbia River ESU (Threatened)
  • 4 instances of WE 30 Realign, Connect, and/or Create Channel
  • 9 instances of WE 47 Plant Vegetation
  • 2 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 3 instances of WE 184 Install Fish Passage Structure
  • 6 instances of WE 114 Identify and Select Projects
  • 8 instances of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 4 instances of WE 30 Realign, Connect, and/or Create Channel
  • 9 instances of WE 47 Plant Vegetation
  • 2 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 3 instances of WE 184 Install Fish Passage Structure
  • 5 instances of WE 114 Identify and Select Projects
  • 8 instances of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (Oncorhynchus mykiss) - All Populations
  • 4 instances of WE 30 Realign, Connect, and/or Create Channel
  • 9 instances of WE 47 Plant Vegetation
  • 2 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 3 instances of WE 184 Install Fish Passage Structure
  • 5 instances of WE 114 Identify and Select Projects
  • 8 instances of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Wildlife
  • 1 instance of WE 36 Develop Terrestrial Habitat Features
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Produce EC for projects
C 119 Manage and Administer Projects
D 114 Meet with stakeholders when approached with new project
E 191 Participate in Regional Data Sharing; CEERP Coordination
F 157 AEMR (Level 3): Collect PRE-Construction AEMR Level 3 data 04/13/2023
G 157 AEMR (Level 3): Collect POST-Construction AEMR Level 3 data 04/13/2023
H 157 AEMR (Level 3): Collect PRE & POST-Construction AEMR Level 3 data 04/13/2023
I 162 Analyze Level 3 AEMR Data
J 132 Provide data for estuary 2023 EP AEMR RME Report
K 132 Provide data for estuary 2024 EP AEMR RME Report
L 132 Submit Annual Progress Report for the period (July 2022) to (June 2023)
M 132 Submit Annual Progress Report for the period (July 2023) to (June 2024)
N 114 MALARKEY RANCH - COORDINATION with Stakeholders/Partners
O 114 MANSFIELD/MAFRE - COORDINATION with Stakeholders/Partners
P 114 FORT STEVENS - FEASIBILITY
Q 114 SOUTH CRANE LAKE - FEASIBILITY
R 114 CLATSOP FAIRGROUNDS - FEASIBILITY
S 175 CARR SLOUGH - DESIGN--100% 04/13/2023
T 175 TOAHEEDLIINI - DESIGN--100% 04/13/2023
U 175 HOGAN RANCH - DESIGN--100% 04/13/2023
V 175 DEEP RIVER/MINT FARM TIDAL RECONNECTIONS - DESIGN--100% 04/13/2023
W 175 CROSEL CREEK - DESIGN--100% 04/13/2023
X 175 COLEWORT CREEK: PHASE 3 - DESIGN--100% 04/13/2023
Y 175 AARON/MCNARY - DESIGN--100% 04/13/2023
Z 175 NETUL LANDING - DESIGN--100% 04/13/2023
AA 47 GOVERNMENT ISLAND- CONSTRUCTION--Plantings 01/03/2024
AB 47 WOODLAND ISLANDS - CONSTRUCTION--Plantings 01/03/2024
AC 47 PALENSKY - FLOODPLAIN CONSTRUCTION--Plantings 01/03/2024
AD 47 DALTON LAKE - CONSTRUCTION--Plantings 01/03/2024
AE 47 ALDRICH POINT - CONSTRUCTION--Plantings 04/13/2023
AF 184 CANCELED: WOLF BAY RAILROAD - CONSTRUCTION--Install Bridge 04/13/2023
AG 30 CANCELED: WOLF BAY RAILROAD - CONSTRUCTION--Create New Channel 04/13/2023
AH 47 CANCELED: WOLF BAY RAILROAD - CONSTRUCTION--Plant Vegetation 04/13/2023
AI 30 SOUTH TONGUE POINT - CONSTRUCTION--Create Tidal Channels 04/13/2023
AJ 180 SOUTH TONGUE POINT - CONSTRUCTION--Enhance Floodplain 04/13/2023
AK 47 SOUTH TONGUE POINT - CONSTRUCTION--Plant Vegetation 04/13/2023
AL 36 CANCELED: PALENSKY - CONSTRUCTION--Highway 30 Wildlife Corridor--Underpass 04/13/2023
AM 40 CANCELED: PALENSKY - CONSTRUCTION--Highway 30 Wildlife Corridor--Directional Wall 04/13/2023
AN 47 CANCELED: PALENSKY - CONSTRUCTION-- Highway 30 Wildlife Corridor--Plant Vegetation 04/13/2023
AO 184 CANCELED: AGENCY CREEK RAILROAD - CONSTRUCTION--Install Bridge
AP 30 CANCELED: AGENCY CREEK RAILROAD - CONSTRUCTION--Create New Channel
AQ 180 CANCELED: AGENCY CREEK RAILROAD - CONSTRUCTION--Remove levee
AR 47 CANCELED: AGENCY CREEK RAILROAD - CONSTRUCTION--Plant Vegetation
AS 184 CANCELED: WARREN SLOUGH RAILROAD - CONSTRUCTION--Install Bridge
AT 30 CANCELED: WARREN SLOUGH RAILROAD - CONSTRUCTION--Create New Channel
AU 47 CANCELED: WARREN SLOUGH RAILROAD - CONSTRUCTION--Plant Vegetation