View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Mountain Snake | Clearwater | 100.00% |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
429 REL 10 SOW | Fishpro, Inc. | 1983-350-02 HEATH FARMS, ALLOTMENT #1705 | Closed | $223,618 | 1/1/2000 - 12/31/2002 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 0 |
Completed: | 0 |
On time: | 0 |
Status Reports | |
---|---|
Completed: | 0 |
On time: | 0 |
Avg Days Late: | None |
Name | Role | Organization |
---|---|---|
Kenneth Kirkman (Inactive) | Project Manager | Bonneville Power Administration |