Project Summary

Project 1988-053-02 - Ne Or Hatchery Master Plan - C
Project Number:
1988-053-02
Title:
Ne Or Hatchery Master Plan - C
Summary:
Build incubation/juvenile rearing capabilities at the existing South Fork Walla Walla spring chinook adult holding and spawning facility to rear spring chinook for acclimation/release in the Umatilla Basin.
Proposer:
None
Proponent Orgs:
Umatilla Confederated Tribes (CTUIR) (Tribe)
Starting FY:
Ending FY:
Stage:
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Purpose:
Artificial Production
Emphasis:
Supplementation
Focal Species:
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

No photos have been uploaded yet for this project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

* Expenditures data includes accruals and are based on data through 30-Jun-2017

No Decided Budget Transfers

Pending Budget Decision?  No


No Project Cost Share

Fiscal Year Cost Share Partner Total Proposed
Contribution
Total Confirmed
Contribution

Contracts

The table below contains contracts with the following statuses: Active, Complete, History, Issued.
Capital Contracts:
Number Contractor Name Title Status Contracted Amount Dates
4114 SOW Umatilla Confederated Tribes (CTUIR) 1988-053-11 NEOH MASTER PLAN - CTUIR-UMATILLA-PARAMETRIX History $5,223 3/23/2001 - 5/6/2003



Annual Progress Reports
Expected (since FY2004):0
Completed:0
On time:0
Status Reports
Completed:0
On time:0
Avg Days Late:None



No assessments are available for this project.
Project Relationships: None

Name Role Organization
Jonathan Mccloud Project Manager Bonneville Power Administration