View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Mountain Columbia | Flathead | 100.00% |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
6358 SOW | Miller Ecological Consultants, Inc. | 1995-025-00 FLATHEAD RIVER INSTREAM FLOW INVESTIGATION | History | $155,900 | 8/21/2001 - 9/30/2003 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 0 |
Completed: | 0 |
On time: | 0 |
Status Reports | |
---|---|
Completed: | 0 |
On time: | 0 |
Avg Days Late: | None |
Name | Role | Organization |
---|---|---|
Ronald Morinaka (Inactive) | Project Manager | Bonneville Power Administration |