Project Summary

Project 1996-034-01 - Methow River Valley Irrigation District
Project Number:
1996-034-01
Title:
Methow River Valley Irrigation District
Summary:
This project was initiated 1996. It started out as a screen and diversion replacement project. Due to numerous legal challenges by the State of Washington and the Irrigation disstrict it to several years to finally implement a project. Screen replacement at both the Methow and Twisp diversions was completed in 2004. As of 2006 the only active work is follow-up vegetation work.
Proposer:
None
Proponent Orgs:
Methow Valley Irrigation District (Govt - Local)
Starting FY:
1996
Ending FY:
2006
Stage:
Area:
Province Subbasin %
Columbia Cascade Methow 100.00%
Purpose:
Habitat
Emphasis:
Restoration/Protection
Focal Species:
Chinook - Upper Columbia River Spring ESU (endangered)
Steelhead - Upper Columbia River DPS (threatened)
Trout, Bull (threatened)
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

No photos have been uploaded yet for this project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

Expense SOY Budget Working Budget Contracted Amount Modified Contract Amount Expenditures *
FY2016 (Previous) $0 $0 $0 $0

FY2017 (Current) $0 $0 $0 $0

FY2018 (Next) $0 $0 $0 $0

Capital SOY Budget Working Budget Contracted Amount Modified Contract Amount Expenditures *
FY2016 (Previous) $0 $0 $0 $0

FY2017 (Current) $0 $0 $0 $0

FY2018 (Next) $0 $0 $0 $0

* Expenditures data includes accruals and are based on data through 30-Apr-2017

No Decided Budget Transfers

Pending Budget Decision?  No


No Project Cost Share

Fiscal Year Cost Share Partner Total Proposed
Contribution
Total Confirmed
Contribution

Contracts

The table below contains contracts with the following statuses: Active, Complete, History, Issued.
Capital Contracts:
Number Contractor Name Title Status Contracted Amount Dates
5676 SOW IRZ Consulting LLC 1996-034-01 METHOW VALLEY IRRIGATION DISTRICT CONCEPTUAL WATER History $183,092 4/1/2001 - 12/31/2002
9656 REL 1 SOW Craven Consulting Group METHOW VALLEY IRRIGATION REHAB PROJECT 1996-034-01 History $40,108 10/8/2002 - 5/31/2004
422 REL 35 SOW MWH Global, Inc. 1996-034-01 METHOW VALLEY IRRIGATION DISTRICT REHABILITATION PROJ History $32,585 8/15/2003 - 9/30/2004
422 REL 38 SOW MWH Global, Inc. PI 199603401 MVID FISH SCREEN REPLACEMENT History $1,003,795 3/16/2004 - 9/30/2005
18326 SOW Okanogan Conservation District PI 199603401 METHOW VALLEY IRRIGATION DIST. REVEGETATION History $10,707 6/7/2004 - 9/30/2005
Expense Contracts:
Number Contractor Name Title Status Contracted Amount Dates
4048 SOW Dunau Associates 1996-034-01 METHOW RIVER VALLEY IRRIGATION DIST. REHABILITATION History $46,364 3/20/2001 - 12/31/2002
5606 SOW Washington Department of Ecology 1996-034-01 METHOW VALLEY IRRIGATION DISTRICT REHAB History $1,189,102 7/2/2001 - 9/30/2004
598 REL 2 SOW MWH Global, Inc. METHOW VALLEY BIOLOGICAL ASSESSMENT History $21,100 8/1/2000 - 11/30/2001
27006 SOW Okanogan Conservation District 1996-034-01 EXP METHOW VALLEY IRRIGATION DIST. REVEGETATION History $5,713 4/1/2006 - 3/31/2007



Annual Progress Reports
Expected (since FY2004):0
Completed:0
On time:0
Status Reports
Completed:4
On time:0
Avg Days Late:34

Earliest Subsequent           Accepted Count of Contract Deliverables
Contract Contract(s) Title Contractor Start End Status Reports Complete Green Yellow Red Total % Green and Complete Canceled
18326 27006 PI 199603401 METHOW VALLEY IRRIGATION DIST. REVEGETATION Okanogan Conservation District 06/2004 06/2004 History 4 3 0 0 0 3 100.00% 0
Project Totals 4 3 0 0 0 3 100.00% 0


No assessments are available for this project.
Project Relationships: None

Name Role Organization
Greg Knott (Inactive) Project Lead Pacific Northwest National Laboratory
Linda Hermeston (Inactive) Project Manager Bonneville Power Administration
Bob Anderson (Inactive) Project Lead Okanogan Conservation District