View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Mountain Columbia | Flathead | 100.00% |
Description: Page: 1 Cover: Cover map - Flathead Subbasin Project(s): 1996-087-01 Document: P104531 Dimensions: 628 x 676 Description: Page: 4 Figure 2: Pablo flume spanning Post Creek Project(s): 1996-087-01 Document: P104531 Dimensions: 695 x 521 Description: Page: 6 Figure 3: Riparian fencing installed along North Valley Creek protecting 31 acres. Project(s): 1996-087-01 Document: P104531 Dimensions: 622 x 500 Description: Page: 7 Figure 4: Proposed fence along Jocko River floodplain Project(s): 1996-087-01 Document: P104531 Dimensions: 597 x 461 |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
4374 SOW | Salish and Kootenai Confederated Tribes | 1996-087-01 WATERSHED COODINATION FOR THE FLATHEAD & KOOTENAIR | History | $307,727 | 3/1/2001 - 2/28/2005 |
24947 SOW | Salish and Kootenai Confederated Tribes | 1996-087-01 EXP MONTANA FOCUS WATERSHED COORDINATION | History | $65,899 | 3/1/2005 - 2/28/2006 |
26992 SOW | Salish and Kootenai Confederated Tribes | 1996-087-01 EXP WATERSHED COORDINATION FOR FLATHEAD | History | $75,912 | 3/1/2006 - 2/28/2007 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 2 |
Completed: | 2 |
On time: | 2 |
Status Reports | |
---|---|
Completed: | 5 |
On time: | 1 |
Avg Days Late: | 110 |
Count of Contract Deliverables | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Earliest Contract | Subsequent Contracts | Title | Contractor | Earliest Start | Latest End | Latest Status | Accepted Reports | Complete | Green | Yellow | Red | Total | % Green and Complete | Canceled |
4374 | 24947, 26992 | 1996-087-01 EXP WATERSHED COORDINATION FOR FLATHEAD | Salish and Kootenai Confederated Tribes | 03/01/2001 | 02/28/2007 | History | 5 | 8 | 0 | 0 | 0 | 8 | 100.00% | 0 |
Project Totals | 5 | 8 | 0 | 0 | 0 | 8 | 100.00% | 0 |
Assessment Number: | 1996-087-01-NPCC-20090924 |
---|---|
Project: | 1996-087-01 - Montana Focus Waterhsed Coordination |
Review: | FY07-09 Solicitation Review |
Approved Date: | 10/23/2006 |
Recommendation: | Fund |
Comments: |
Assessment Number: | 1996-087-01-ISRP-20060831 |
---|---|
Project: | 1996-087-01 - Montana Focus Waterhsed Coordination |
Review: | FY07-09 Solicitation Review |
Completed Date: | 8/31/2006 |
Final Round ISRP Date: | None |
Final Round ISRP Rating: | Not Applicable |
Final Round ISRP Comment: | |
This is a coordinator position description. Objectives are very general and stated in terms of improving various conditions associated with fish habitat, but there are no endpoints from which real progress can be assessed.
No monitoring results for project effectiveness are provided. Objectives are not described in measurable terms. Responsibilities do not seem to include any assessment to guide an adaptive management approach. There is only a brief statement for 2005 results regarding development of an offstream watering well, a project to divert wastewater, and funding negotiated for stream improvement of the Jocko River. Reviewers are provided no basis for assessing whether there is continued need/benefits from the position. Since the purpose of the position is to coordinate projects in the basin, perhaps it could be incorporated in Project 200200300. |
|
Documentation Links: |
|
Assessment Number: | 1996-087-01-INLIEU-20090521 |
---|---|
Project Number: | 1996-087-01 |
Review: | FY07-09 Solicitation Review |
Completed Date: | 10/6/2006 |
In Lieu Rating: | Problems May Exist |
Cost Share Rating: | 1 - Appears reasonable |
Comment: | Flathead watershed coordinator; other entities authorized/required; recommend confirmation that cost share is sufficient. |
Assessment Number: | 1996-087-01-CAPITAL-20090618 |
---|---|
Project Number: | 1996-087-01 |
Review: | FY07-09 Solicitation Review |
Completed Date: | 2/27/2007 |
Capital Rating: | Does Not Qualify for Capital Funding |
Capital Asset Category: | None |
Comment: | None |
Name | Role | Organization |
---|---|---|
Lynn DuCharme | Salish and Kootenai Confederated Tribes | |
Cecilia Brown (Inactive) | Project Manager | Bonneville Power Administration |
David Byrnes (Inactive) | Supervisor | Bonneville Power Administration |
Katie McDonald (Inactive) | Interested Party | Bonneville Power Administration |