View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Middle Snake | Snake Upper Middle | 100.00% |
|
Description: Page: 1 Cover: Cover photo Project(s): 1998-002-00 Document: P107326 Dimensions: 332 x 199 Description: Page: 19 Figure 1: Distribution of desert (light circles) and montane (dark circles) study sites throughout southwestern Idaho and adjacent states. Project(s): 1998-002-00 Document: P107326 Dimensions: 977 x 1154 |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
4261
![]() |
Idaho Department of Fish and Game (IDFG) | 1998-002-00 ASSESSMENT OF SNAKE RIVER NATIVE SALMONIDS | Closed | $1,230,383 | 4/1/2001 - 6/30/2005 |
22947
![]() |
Idaho Department of Fish and Game (IDFG) | PI 1998-002-00 SNAKE RIVER NATIVE SALMONID ASSESSMENT | History | $320,806 | 7/1/2005 - 6/30/2006 |
28107
![]() |
Idaho Department of Fish and Game (IDFG) | 1998-002-00 ASSESSMENT OF SNAKE RIVER NATIVE SALMONIDS | History | $316,590 | 7/1/2006 - 6/30/2007 |
33645
![]() |
Idaho Department of Fish and Game (IDFG) | 1998-002-00 EXP ASSESSMENT OF SNAKE RIVER NATIVE SALMONIDS | History | $94,265 | 7/1/2007 - 6/30/2008 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 3 |
Completed: | 2 |
On time: | 2 |
Status Reports | |
---|---|
Completed: | 11 |
On time: | 2 |
Avg Days Late: | 46 |
Count of Contract Deliverables | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Earliest Contract | Subsequent Contracts | Title | Contractor | Earliest Start | Latest End | Latest Status | Accepted Reports | Complete | Green | Yellow | Red | Total | % Green and Complete | Canceled |
4261 | 22947, 28107, 33645 | 1998-002-00 EXP ASSESSMENT OF SNAKE RIVER NATIVE SALMONIDS | Idaho Department of Fish and Game (IDFG) | 04/01/2001 | 06/30/2008 | History | 11 | 22 | 4 | 0 | 2 | 28 | 92.86% | 0 |
Project Totals | 11 | 22 | 4 | 0 | 2 | 28 | 92.86% | 0 |
Assessment Number: | 1998-002-00-NPCC-20090924 |
---|---|
Project: | 1998-002-00 - Snake River Native Salmonid As |
Review: | FY07-09 Solicitation Review |
Approved Date: | 10/23/2006 |
Recommendation: | Fund |
Comments: |
Assessment Number: | 1998-002-00-ISRP-20060831 |
---|---|
Project: | 1998-002-00 - Snake River Native Salmonid As |
Review: | FY07-09 Solicitation Review |
Completed Date: | 8/31/2006 |
Final Round ISRP Date: | None |
Final Round ISRP Rating: | Meets Scientific Review Criteria |
Final Round ISRP Comment: | |
This is an exemplary outstanding proposal that continues the high standard of work and proposal writing previously presented by the sponsors. They are to be commended on a project that is clearly laid out, is marching steadily along toward its well-defined objectives, and is setting a standard for such work in the interior Rocky Mountain West. It should serve as a model for proposal writing and reporting of results for an ongoing proposal. The relationships to other projects section is exceptionally strong. The project history is very nicely done, with a truly impressive set of reports and manuscripts in press and already published.
|
|
Documentation Links: |
|
Assessment Number: | 1998-002-00-INLIEU-20090521 |
---|---|
Project Number: | 1998-002-00 |
Review: | FY07-09 Solicitation Review |
Completed Date: | 10/6/2006 |
In Lieu Rating: | Problems May Exist |
Cost Share Rating: | 3 - Does not appear reasonable |
Comment: | Population analysis and recovery planning; fishery managers authorized/required; need confirmation that cost-share is sufficient. |
Assessment Number: | 1998-002-00-CAPITAL-20090618 |
---|---|
Project Number: | 1998-002-00 |
Review: | FY07-09 Solicitation Review |
Completed Date: | 2/27/2007 |
Capital Rating: | Does Not Qualify for Capital Funding |
Capital Asset Category: | None |
Comment: | None |
Name | Role | Organization |
---|---|---|
Kevin (IDFG) Meyer (Inactive) | Project Lead | Idaho Department of Fish and Game (IDFG) |
Jeff Dillon | Supervisor | Idaho Department of Fish and Game (IDFG) |
Wynn Avocette (Inactive) | Project Manager | Bonneville Power Administration |
Dorothy Welch | Supervisor | Bonneville Power Administration |