View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Columbia River Estuary | Columbia Estuary | 100.00% |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
8791 SOW | National Oceanic and Atmospheric Administration | 1998-004-04 DEVELOPMENT OF CONCEPTUAL MODEL TO ASSESS ESTUARINE | Closed | $2,773 | 12/1/1998 - 4/15/2002 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 0 |
Completed: | 0 |
On time: | 0 |
Status Reports | |
---|---|
Completed: | 0 |
On time: | 0 |
Avg Days Late: | None |
Name | Role | Organization |
---|---|---|
Alan Ruger (Inactive) | Project Manager | Bonneville Power Administration |