View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Columbia Plateau | John Day | 100.00% |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
21 REL 1 SOW | US Geological Survey (USGS) | 2000-52-00 UPSTREAM MIGRATION OF PACIFIC LAMPREYS IN JOHN DAY R. | Terminated | $199,495 | 4/17/2000 - 4/17/2003 |
6209 SOW | US Geological Survey (USGS) | 2000-052-00 UPSTREAM MIGRATION PACIFIC LAMPREYS-JOHN DAY | Closed | $25,887 | 8/13/2001 - 4/17/2003 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 0 |
Completed: | 0 |
On time: | 0 |
Status Reports | |
---|---|
Completed: | 0 |
On time: | 0 |
Avg Days Late: | None |
Name | Role | Organization |
---|---|---|
Deborah Docherty (Inactive) | Project Manager | Bonneville Power Administration |