Views/Actions
Columbia Basin Fish and Wildlife Program
RSS Feed for updates to Project 2001-022-00 - 15 Mile Cr Orchard Pesticide Follow this via RSS feed. Help setting up RSS feeds?

Project Summary

Project 2001-022-00 - 15 Mile Cr Orchard Pesticide
Project Number:
2001-022-00
Title:
15 Mile Cr Orchard Pesticide
Summary:
None
Proposer:
None
Proponent Orgs:
Wy'East Resource Conservation and Development Area Council (Non-Profit)
Starting FY:
2001
Ending FY:
2006
Stage:
Area:
Province Subbasin %
Columbia Gorge Fifteenmile 100.00%
Purpose:
Habitat
Emphasis:
Restoration/Protection
Focal Species:
All Anadromous Fish
All Anadromous Salmonids
Bass, Largemouth
Bass, Smallmouth
Cutthroat Trout, Coastal - Resident Populations
Freshwater Mussels
OBSOLETE-Carp, Common
OBSOLETE-Catfish
OBSOLETE-Crappie, Black
OBSOLETE-Crappie, White
OBSOLETE-Perch, Yellow
OBSOLETE-Pikeminnow, Northern
OBSOLETE-Trout, Brown
OBSOLETE-Walleye
Sturgeon, White - All Populations except Kootenai R. DPS
Trout, Bull (threatened)
Trout, Rainbow
Whitefish, Mountain
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

Weather station with Mount Hood in the background. This station serves as a repeater for orchards in south Wasco Co.

Figure Name: Photo 1

Document ID: 00005254-2

Document: Fifteenmile Creek Orchard Pesticide Pollution Risk Study

Page Number: 4

Project: 2001-022-00

Contract: 5254

Weather station with tipping design developed by IFP Coordinator, Mike Omeg.

Figure Name: Photo 2

Document ID: 00005254-2

Document: Fifteenmile Creek Orchard Pesticide Pollution Risk Study

Page Number: 5

Project: 2001-022-00

Contract: 5254

Technician Mike Land installing a weather station for the Crook County Juniper project.

Figure Name: Photo 3

Document ID: 00005254-2

Document: Fifteenmile Creek Orchard Pesticide Pollution Risk Study

Page Number: 6

Project: 2001-022-00

Contract: 5254

Wy’East works closely with NRCS to implement IFP practices in area orchards.

Figure Name: Photo 4

Document ID: 00005254-2

Document: Fifteenmile Creek Orchard Pesticide Pollution Risk Study

Page Number: 7

Project: 2001-022-00

Contract: 5254

Leafroller moths caught in an electronic insect trap.

Figure Name: Photo 5

Document ID: 00005254-2

Document: Fifteenmile Creek Orchard Pesticide Pollution Risk Study

Page Number: 8

Project: 2001-022-00

Contract: 5254

Electronic insect traps like the one shown above were evaluated in 2004.

Figure Name: Photo 6

Document ID: 00005254-2

Document: Fifteenmile Creek Orchard Pesticide Pollution Risk Study

Page Number: 8

Project: 2001-022-00

Contract: 5254

Wy’East sponsored field days for growers to meet and discuss pest and disease management. Growers were able to see IFP practices at work.

Figure Name: Photo 7

Document ID: 00005254-2

Document: Fifteenmile Creek Orchard Pesticide Pollution Risk Study

Page Number: 9

Project: 2001-022-00

Contract: 5254

Wasco County Fruit and Produce League Meeting at the Discovery Center in The Dalles, February 2004

Figure Name: Photo 8

Document ID: 00005254-2

Document: Fifteenmile Creek Orchard Pesticide Pollution Risk Study

Page Number: 10

Project: 2001-022-00

Contract: 5254

Wy’East is cooperating with OSU and NRCS to demonstrate pest management practices which limit spray drift. A low volume sprayer is pictured above.

Figure Name: Photo 9

Document ID: 00005254-2

Document: Fifteenmile Creek Orchard Pesticide Pollution Risk Study

Page Number: 12

Project: 2001-022-00

Contract: 5254

IFP Project Management Team

Figure Name: Photo 10

Document ID: 00005254-2

Document: Fifteenmile Creek Orchard Pesticide Pollution Risk Study

Page Number: 14

Project: 2001-022-00

Contract: 5254


Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

Expense SOY Budget Working Budget Contracted Amount Modified Contract Amount Expenditures *
FY2017 (Previous) $0 $0 $0 $0

FY2018 (Current) $0 $0 $0 $0

FY2019 (Next) $0 $0 $0 $0

* Expenditures data includes accruals and are based on data through 30-Sep-2017

No Decided Budget Transfers

Pending Budget Decision?  No


No Project Cost Share

Fiscal Year Cost Share Partner Total Proposed
Contribution
Total Confirmed
Contribution

No Current Contracts




Annual Progress Reports
Expected (since FY2004):1
Completed:1
On time:1
Status Reports
Completed:2
On time:1
Avg Days Late:66

Earliest Subsequent           Accepted Count of Contract Deliverables
Contract Contract(s) Title Contractor Start End Status Reports Complete Green Yellow Red Total % Green and Complete Canceled
5254 2001-022-00 15 MILE CREEK ORCHARD PESTICIDE POLLUTION RISK STUDY Wy'East Resource Conservation and Development Area Council 05/2001 05/2001 Closed 2 10 0 0 0 10 100.00% 0
Project Totals 2 10 0 0 0 10 100.00% 0


No assessments are available for this project.
Project Relationships: None

Name Role Organization
Mike Omeg (Inactive) Project Lead Wy'East Resource Conservation and Development Area Council
Sarah Branum (Inactive) Project Manager Bonneville Power Administration