View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Columbia Cascade | Methow | 100.00% |
Description: Page: 4 Photo 1: Driven channel crossing pre-project. Project(s): 2005-010-00 Document: P114111 Dimensions: 750 x 499 Description: Page: 4 Photo 2: View of bridge entry at former crossing site. Project(s): 2005-010-00 Document: P114111 Dimensions: 750 x 499 Description: Page: 5 Photo 3: Pre-project undersized culvert. Project(s): 2005-010-00 Document: P114111 Dimensions: 999 x 655 Description: Page: 5 Photo 4: Meandering side-channel habitat post construction. Project(s): 2005-010-00 Document: P114111 Dimensions: 750 x 498 |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
32818 SOW | Methow Salmon Recovery Foundation | 2005-010-00 EXP UPA MACPHERSON SIDE CHANNEL | History | $57,620 | 5/15/2007 - 12/31/2008 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 1 |
Completed: | 0 |
On time: | 0 |
Status Reports | |
---|---|
Completed: | 5 |
On time: | 3 |
Avg Days Late: | 37 |
Count of Contract Deliverables | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Earliest Contract | Subsequent Contracts | Title | Contractor | Earliest Start | Latest End | Latest Status | Accepted Reports | Complete | Green | Yellow | Red | Total | % Green and Complete | Canceled |
32818 | 2005-010-00 EXP UPA MACPHERSON SIDE CHANNEL | Methow Salmon Recovery Foundation | 05/15/2007 | 12/31/2008 | History | 5 | 4 | 0 | 0 | 1 | 5 | 80.00% | 0 | |
Project Totals | 5 | 4 | 0 | 0 | 1 | 5 | 80.00% | 0 |
Assessment Number: | 2005-010-00-CAPITAL-20090618 |
---|---|
Project Number: | 2005-010-00 |
Review: | FY07-09 Solicitation Review |
Completed Date: | 2/27/2007 |
Capital Rating: | Does Not Qualify for Capital Funding |
Capital Asset Category: | None |
Comment: | None |
Name | Role | Organization |
---|---|---|
Greg Knott (Inactive) | Supervisor | Pacific Northwest National Laboratory |
Chris Johnson (Inactive) | Project Lead | Chewuch Basin Council |
Chris Eliassen (Inactive) | Administrative Contact | Methow Salmon Recovery Foundation |
Colleen Spiering (Inactive) | Env. Compliance Lead | Bonneville Power Administration |
Cecilia Brown (Inactive) | Project Manager | Bonneville Power Administration |
Paul Krueger (Inactive) | Supervisor | Bonneville Power Administration |