View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Basinwide | - | 100.00% |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
24097 REL 8 SOW | Northwest Edison | FISH HATCHERY LIGHTING PROJECTS AT SPOKANE, FORD & COLVILLE | History | $26,997 | 11/5/2007 - 1/31/2008 |
35742 REL 1 SOW | EMP2 Inc. | COLVILLE FISH HATCHERY PUMPING SYSTEM | History | $14,932 | 3/1/2008 - 5/30/2008 |
21290 REL 18 SOW | EMP2 Inc. | SPOKANE TRIBAL HATCHERY | History | $6,088 | 8/29/2008 - 9/30/2008 |
24076 REL 22 SOW | Amtech Lighting Services, Inc. | OAK SPRINGS FISH HATCHERY RETROFIT LIGHTING | History | $15,960 | 9/1/2008 - 9/30/2008 |
24098 REL 8 SOW | 4J Electric Inc DBA Engel Electric | LYONS FERRY AND NEZ PIERCE FISH HATCHERIES | History | $28,313 | 9/12/2008 - 11/30/2008 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 0 |
Completed: | 0 |
On time: | 0 |
Status Reports | |
---|---|
Completed: | 0 |
On time: | 0 |
Avg Days Late: | None |
Assessment Number: | 2005-011-00-CAPITAL-20090618 |
---|---|
Project Number: | 2005-011-00 |
Review: | FY07-09 Solicitation Review |
Completed Date: | 2/27/2007 |
Capital Rating: | Does Not Qualify for Capital Funding |
Capital Asset Category: | None |
Comment: | None |
Name | Role | Organization |
---|---|---|
Bradley Miller (Inactive) | Project Lead | Bonneville Power Administration |
Gregory Baesler (Inactive) | Project Manager | Bonneville Power Administration |
Paul Krueger (Inactive) | Supervisor | Bonneville Power Administration |