Project Summary

Project 2007-212-00 - Okanogan Basin Locally Adapted Steelhead Broodstock Step 1 and 2 (Casimer Bar)
Project Number:
2007-212-00
Title:
Okanogan Basin Locally Adapted Steelhead Broodstock Step 1 and 2 (Casimer Bar)
Summary:
The work under this contract will provide an evaluation of the existing Cassimer Bar Hatchery. A project Masterplan will be produced that meets the requirements of the NPCC's 3 step process. The Masterplan will be based on a goal of an estimated production level of 200,000 steelhead smolts to supplement natural reproduction within the Okanogan River basin.
Proposer:
None
Proponent Orgs:
Colville Confederated Tribes (Tribe)
D J Warren and Associates, Inc. (Private)
Starting FY:
2007
Ending FY:
2032
Stage:
Implementation - Project Status Report
Area:
Province Subbasin %
Columbia Cascade Okanogan 100.00%
Purpose:
Artificial Production
Emphasis:
Supplementation
Focal Species:
Steelhead - Upper Columbia River DPS
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Special:
None

No photos have been uploaded yet for this project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

Expense SOY Budget Working Budget Contracted Amount Modified Contract Amount Expenditures *
FY2017 (Previous) $0 $0 $0 $0 $0

Fish Accord - Colville $0 $0 $0 $0
FY2018 (Current) $0 $0 $0 $0 $0

Post 2018 - Colville $0 $0 $0 $0
FY2019 (Next) $0 $0 $0 $0

Capital SOY Budget Working Budget Contracted Amount Modified Contract Amount Expenditures *
FY2017 (Previous) $0 $0 $0 $0 $0

Fish Accord - Colville $0 $0 $0 $0
FY2018 (Current) $0 $0 $0 $0

FY2019 (Next) $0 $0 $0 $0

* Expenditures data includes accruals and are based on data through 31-May-2018

Decided Budget Transfers  (FY2017 - FY2019)

Acct FY Acct Type Amount Fund Budget Decision Date
FY2017 Capital $0 From: Fish Accord - Colville Fish Accord Review 05/02/2008
FY2017 Expense $300,000 From: Fish Accord - Colville Fish Accord Review 05/02/2008
FY2017 Expense $65,521 From: Fish Accord - Colville Fish Accord project COLA 11/21/2008
FY2017 Expense $85,176 From: Fish Accord - Colville CCT Accord budget transfers (cleanup of FY08/09/10/11) 5/12/2011 05/13/2011
FY2017 Expense $47,518 To: Fish Accord - Colville CCT (2009-007-00) establish FY13-17 budget 03/08/2012
FY2017 Expense $19,167 From: Fish Accord - Colville CCT (2007-212-00) adjust FY09-13 budgets 05/14/2012
FY2017 Expense $373,272 From: Fish Accord - Colville CCT (2007-212-00) adjust FY09-13 budgets 05/14/2012
FY2017 Expense $47,518 From: Fish Accord - Colville CCT (2009-007-00) un-do FY16-FY17 project adjustments 09/10/2012
FY2017 Expense $15,226 To: Fish Accord - Colville Accord Budget Transfers (CTUIR-Capital, CCT) 05/14/2013
FY2017 Expense $47,518 To: Fish Accord - Colville CCT (2009-007-00) establish FY16-17 budget 07/29/2013
FY2017 Expense $400,000 To: Fish Accord - Colville CCT Budget Adjustments (from 9/30/2013 coordination meeting) 01/30/2014
FY2017 Expense $200,000 To: Fish Accord - Colville CCT Budget Adjustments (from 9/30/2013 coordination meeting) 01/30/2014
FY2017 Expense $29,159 From: Fish Accord - Colville Accord Budget Transfers (CCT, CTUIR) 12/8/2014 12/09/2014
FY2017 Expense $180,474 From: Fish Accord - Colville Accord Budget Transfers (CCT, CTUIR) 12/8/2014 12/09/2014
FY2017 Expense $271,491 To: Fish Accord - Colville Accord Budget Transfers (CCT, CTUIR) 12/8/2014 12/09/2014
FY2017 Expense $100,992 From: Fish Accord - Colville Accord Transfers (CCT/CRITFC) 1/14/15 01/15/2015
FY2017 Expense $219,526 To: Fish Accord - Colville Accord Budget Transfers (CCT, Idaho) 8/27/2015 08/28/2015
FY2018 Expense $0 From: Post 2018 - Colville FY18 Initial Planning Budgets (CCT) 7/26/2017 07/27/2017

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2018
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2014 (Draft)
2013
2012
2011 $0 0 %
2010
2009
2008 $0 0 %
2007 $0 0 %

No Current Contracts




Annual Progress Reports
Expected (since FY2004):4
Completed:0
On time:0
Status Reports
Completed:44
On time:22
Avg Days Late:8

Earliest Subsequent           Accepted Count of Contract Deliverables
Contract Contract(s) Title Contractor Start End Status Reports Complete Green Yellow Red Total % Green and Complete Canceled
33902 2007-212-00 LOCALLY ADAPTED STEELHEAD BROODSTOCK - STEP ONE Colville Confederated Tribes 07/2007 07/2007 Closed 7 4 0 0 0 4 100.00% 0
41893 62525 200721200 EXP LOCALLY ADAPTED STEELHEAD BROODSTOCK - STEP 1 D J Warren and Associates, Inc. 04/2009 04/2009 Closed 21 7 0 0 8 15 46.67% 3
49014 62531 2007-212-00 EXP LOCALLY ADAPTED STEELHEAD BROODSTOCK- STEP REVIEW Colville Confederated Tribes 08/2010 08/2010 Closed 16 4 0 0 5 9 44.44% 0
Project Totals 44 15 0 0 13 28 53.57% 3


Review: RME / AP Category Review

2008 FCRPS BiOp Workgroup Assessment

Assessment Number: 2007-212-00-BIOP-20101105
Project Number: 2007-212-00
Review: RME / AP Category Review
Proposal Number: RMECAT-2007-212-00
Completed Date: None
2008 FCRPS BiOp Workgroup Rating: Response Requested
Comments: BiOp Workgroup Comments: Please identify:
1. Why your data is "not electronically available"; and
2. What data sets will not be "electronically available" for various deliverables. Please specify the deliverable that is not electronically available. (Note a data set includes the raw data collected and additional data on analysis). For example if there is a deliverable for population adult abundance or habitat, we expect your raw and synthesized data to be made available electronically.
- Your response may help BPA identify funding needs for data repositories or identify an existing data warehouse that your data could be stored.

The BiOp RM&E Workgroups made the following determinations regarding the proposal's ability or need to support BiOp Research, Monitoring and Evaluation (RME) RPAs. If you have questions regarding these RPA association conclusions, please contact your BPA COTR and they will help clarify, or they will arrange further discussion with the appropriate RM&E Workgroup Leads. BiOp RPA associations for the proposed work are: (0)
All Questionable RPA Associations () and
All Deleted RPA Associations (0)
Proponent Response:

 

Data is not electronically available because the project is not yet complete.  Upon completion of step-1 and Step-2 of the NWPPC 3-step process, the outcome of these process (Master plan (including HGMP), Production plan and M&E Plan) will be uploaded into Pisces, consistent with the contract deliverables that they address.  Further, upon the successful conclusion of the NWPPC 3-step process and implementation of the Okanogan River locally-adapted steelhead production program, data sets and synthesis of data associated with implementation (including hatchery production, adult management and M&E) will be provided electronically and uploaded into Pisces, consistent with contract deliverables developed for implementation.  Further, annual implementation reports will be provided to BPA and will also be electronically posted to the Colville Tribal F&W website (currently in development).

Although this project has not yet concluded the NWPPC 3-step process, it is anticipated that full implementation of this project will include data sets and synthesis of data that will include at a minimum: adult steelhead escapement abundance and origin (NOR and HOR proportions); hatchery broodstock origin, annual and 5-year running average PNI for Okanogan Basin steelhead, spawning distribution; spawn timing; hatchery and natural origin age-at-return, size-at-age and fecundity; and adult management (harvest and or adult extraction at weirs).  Juvenile data sets will include at a minimum: within hatchery life-stage survival and disease profile; juvenile hatchery production levels, release locations and dates; hatchery origin smolt survival to McNary Dam; hatchery juvenile marking/tagging data; juvenile emigration data (smolt abundance estimates, emigration timing and smolt size and age); and hatchery and natural origin SARs.  The conclusion of the NWPPC 3-step process is likely to include other implementation and monitoring elements in addition to those included above and will be incorporated into the implementation plan and reported electronically in Pisces, consistent with contract work elements and deliverables and included in annual implementation reports to BPA and posted to Colville Tribal F&W website (currently in development).

The proposal identified RPA 42.3 as an associated BiOp RPA, although not specifically an "RM&E RPA". If the Workgroup is specifically limiting its' review of RPAs to only "RM&E" RPAs then omitting RPA 42.3 from consideration is applicable.  However, the Colville Tribes is concerned that omitting RPA 42.3 from the project proposal will result in a misconstrued determination that this project has no BiOp association at all, which is not the case.  The goal of this project at full implementation is to preserve and rebuild genetic resources through safety-net and conservation actions to reduce short-term extinction risk and promote recovery.  Further, the development of a program to recondition natural origin kelts and develop local broodstocks to accelerate steelhead recovery in the Okanogan Basin is identified in Hatchery Strategy 2; Action 42.3

Finally, during the Colville Tribes development of the responses to the RM&E Workgroup comments, it became evident that there may be a link to RM&E RPAs 63.1; 63.2 and 64.2. Although this project is not specifically identified in an RM&E RPA, the Colville Tribes anticipate that data sets, synthesis of data resulting from full implementation of this project will be applicable to the action agencies assessment of hatchery effectiveness of safety-net and conservation programs have on the viability and recovery of target populations of salmon and steelhead (RPA 63.1), in determining the effect of hatchery reform actions have on the recovery of target salmon and steelhead populations (RPA 63.2) and in determining if properly designed intervention programs using artificial production make a positive contribution to recovery of listed populations (RPA 64.2).  The Colville Tribes would appreciate the opinion of the RM&E Workgroup relative to inclusion of RPAs 63.1, 63.2 and 64.2.

Council Recommendation

Assessment Number: 2007-212-00-NPCC-20101105
Project: 2007-212-00 - Okanogan Basin Locally Adapted Steelhead Broodstock Step 1 and 2 (Casimer Bar)
Review: RME / AP Category Review
Proposal: RMECAT-2007-212-00
Proposal State: Pending BPA Response
Approved Date: 6/10/2011
Recommendation: Under Review
Comments: Implement through outcome of Step Review process (see ISRP doc 2009-15): Sponsor to revise Step 1 Master Plan. Implementation subject to regional hatchery effects evaluation process described in programmatic recommendation #4.
Conditions:
Council Condition #1 Programmatic Issue: RMECAT #4 Hatchery Effectiveness—subject to regional hatchery effects evaluation process
Review: FY07-09 Solicitation Review

Legal Assessment (In-Lieu)

Assessment Number: 2007-212-00-INLIEU-20090521
Project Number: 2007-212-00
Review: FY07-09 Solicitation Review
Completed Date: 10/6/2006
In Lieu Rating: No Problems Exist
Cost Share Rating: None
Comment: Evaluate expansion of Cassimer Bar hatchery for steelhead supplementation; assume in mitigation for FCRPS.

Capital Assessment

Assessment Number: 2007-212-00-CAPITAL-20090618
Project Number: 2007-212-00
Review: FY07-09 Solicitation Review
Completed Date: 2/27/2007
Capital Rating: Does Not Qualify for Capital Funding
Capital Asset Category: None
Comment: None

Independent Scientific Review Panel Assessment

Assessment Number: 2007-212-00-ISRP-20060831
Project: 2007-212-00 - Okanogan Basin Locally Adapted Steelhead Broodstock Step 1 and 2 (Casimer Bar)
Review: FY07-09 Solicitation Review
Completed Date: 8/31/2006
Final Round ISRP Date: None
Final Round ISRP Rating: Meets Scientific Review Criteria - In Part
Final Round ISRP Comment:
The ISRP recommends funding this project at a base level in order to proceed with the Three-Step process and development of the Step One documents and analysis. The Three-Step process will provide an opportunity for the review team to examine the proposed project in considerably greater detail than is possible in the FY 2007 process. The in-depth review process by the Three-Step process is appropriate and should lead to recommendations on how and whether to proceed into implementation.

The project has demonstrated some early results of returns to Omak Creek that appear on the surface to be positive. Of course numerous questions arise such as "have these returns led to any increase in natural production?" and other related concerns the ISRP/ISAB have identified with supplementation. Does the OSP have EDT or other analysis that identify major limitations? The sponsors should consider including include AHA modeling in the Three-Step process.
Documentation Links:

Council Recommendation

Assessment Number: 2007-212-00-NPCC-20090924
Project: 2007-212-00 - Okanogan Basin Locally Adapted Steelhead Broodstock Step 1 and 2 (Casimer Bar)
Review: FY07-09 Solicitation Review
Approved Date: 10/23/2006
Recommendation: Fund
Comments: ISRP fundable in part: funding contingent on favorable step review. Capitalize construction. As funds become available, provide for the expense portion of this project.

Project Relationships: None

Name Role Organization
Chris Fisher Interested Party Colville Confederated Tribes
Dan Warren Technical Contact D J Warren and Associates, Inc.
Christine Read Technical Contact Bonneville Power Administration
Nikki Dick Administrative Contact Colville Confederated Tribes
Peter Lofy Supervisor Bonneville Power Administration
Kirk Truscott Project Lead Colville Confederated Tribes
Jenna Peterson Interested Party Bonneville Power Administration
Kary Nichols Interested Party Colville Confederated Tribes
Ted Gresh Env. Compliance Lead Bonneville Power Administration
Randy Friedlander Supervisor Colville Confederated Tribes
David Roberts (Inactive) Project Manager Bonneville Power Administration