Project Summary

Project 2007-214-00 - Fender Mill Floodplain Restoration
Project Number:
2007-214-00
Title:
Fender Mill Floodplain Restoration
Summary:
See contract summary
Proposer:
None
Proponent Orgs:
Methow Salmon Recovery Foundation (Non-Profit)
Starting FY:
2007
Ending FY:
2011
Stage:
Area:
Province Subbasin %
Columbia Cascade Methow 100.00%
Purpose:
Habitat
Emphasis:
Restoration/Protection
Focal Species:
Chinook - Upper Columbia River Spring ESU
Coho - Unspecified Population
Cutthroat Trout, Westslope
Steelhead - Upper Columbia River DPS
Trout, Bull
Species Benefit:
Anadromous: 90.0%   Resident: 10.0%   Wildlife: 0.0%
Special:
None
BiOp Association:
FCRPS 2008 – view list of FCRPS 2008 BiOp Actions

Tributary Habitat Implementation 2007 to 2009,
Tributary Habitat Implementation 2007 to 2009,
Tributary Habitat Implementation 2007 to 2009

No photos have been uploaded yet for this Project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

No Decided Budget Transfers

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2024
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2010
2009 $34,540 59%
2008 $50,000 33%
2007 $0 0%

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
38435 SOW Methow Salmon Recovery Foundation 2007-214-00 EXP UPA FENDER MILL FLOODPLAIN History $23,691 6/26/2008 - 6/26/2009
6388 REL 101 SOW Applied Archaeological Research 2008 UPA FENDER MILL FLOODPLAIN PROJECT History $8,965 8/20/2008 - 9/30/2008



Annual Progress Reports
Expected (since FY2004):1
Completed:0
On time:0
Status Reports
Completed:4
On time:2
Avg Days Late:15

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
38435 2007-214-00 EXP UPA FENDER MILL FLOODPLAIN Methow Salmon Recovery Foundation 06/26/2008 06/26/2009 History 4 5 0 0 2 7 71.43% 0
Project Totals 4 5 0 0 2 7 71.43% 0


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

Review: FY07-09 Solicitation Review

Council Recommendation

Assessment Number: 2007-214-00-NPCC-20090924
Project: 2007-214-00 - Fender Mill Floodplain Restoration
Review: FY07-09 Solicitation Review
Approved Date: 10/23/2006
Recommendation: Fund Pending Available Funds
Comments: Tier 2. Fund at a level consistent with ISRP comments, as funds become available.

Independent Scientific Review Panel Assessment

Assessment Number: 2007-214-00-ISRP-20060831
Project: 2007-214-00 - Fender Mill Floodplain Restoration
Review: FY07-09 Solicitation Review
Completed Date: 8/31/2006
Final Round ISRP Date: None
Final Round ISRP Rating: Meets Scientific Review Criteria
Final Round ISRP Comment:
The project sponsors have provided a thorough and convincing response to the ISRP's questions. The clarification that the outlet of the Fender Mill side channel is perennially connected to the mainstem Methow addresses our concern about the possibility of juvenile stranding. The response that brook trout already spawn in the main Methow River and are free to move back and forth between the mainstem and the complex of side channels and ponds reduces our concern that the project could serve as a source of brook trout. Both the issues of monitoring and the relationship of this project to others nearby are adequately addressed. The inclusion of a more comprehensive outreach effort not only addresses an ISRP concern but should provide benefits for those planning to implement similar projects elsewhere in the basin. We also appreciate the overall emphasis on restoring natural channel processes and floodplain functions in a reach that is heavily used by salmon and steelhead. The sponsors are complimented for the completeness and professionalism of their response to the ISRP comments.
Documentation Links:

Legal Assessment (In-Lieu)

Assessment Number: 2007-214-00-INLIEU-20090521
Project Number: 2007-214-00
Review: FY07-09 Solicitation Review
Completed Date: 10/6/2006
In Lieu Rating: No Problems Exist
Cost Share Rating: None
Comment: Reconnect floodplain via dike removal etc; assume no entity already required to do.

Capital Assessment

Assessment Number: 2007-214-00-CAPITAL-20090618
Project Number: 2007-214-00
Review: FY07-09 Solicitation Review
Completed Date: 2/27/2007
Capital Rating: Does Not Qualify for Capital Funding
Capital Asset Category: None
Comment: None

Project Relationships: None

Name Role Organization
Cecilia Brown (Inactive) Project Manager Bonneville Power Administration
Chris Johnson Project Lead Methow Salmon Recovery Foundation
Chris Eliassen (Inactive) Administrative Contact Methow Salmon Recovery Foundation
Paul Krueger (Inactive) Supervisor Bonneville Power Administration