Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
RSS Feed for updates to Project 2008-601-00 - Upper Lemhi River-Acquisition Follow this via RSS feed. Help setting up RSS feeds?

Project Summary

Project 2008-601-00 - Upper Lemhi River-Acquisition
Project Number:
2008-601-00
Title:
Upper Lemhi River-Acquisition
Summary:
The Upper Lemhi River Acquisition Project seeks to acquire interests in land and water in the Upper Lemhi Watershed.
Proposer:
None
Proponent Orgs:
Idaho Governor's Office of Species Conservation (Govt - State)
Starting FY:
2008
Ending FY:
2032
Stage:
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Purpose:
Habitat
Emphasis:
Restoration/Protection
Focal Species:
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

No photos have been uploaded yet for this Project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

No Decided Budget Transfers

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2024
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2010
2009

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
BPA-004574 Bonneville Power Administration Anadromous Fish Land Acquisitions Active $0 10/1/2008 - 9/30/2009
BPA-005764 Bonneville Power Administration Realty Svcs Active $6,027 10/1/2009 - 9/30/2010



Annual Progress Reports
Expected (since FY2004):0
Completed:0
On time:0
Status Reports
Completed:0
On time:0
Avg Days Late:None

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
BPA-5764 Realty Svcs Bonneville Power Administration 10/01/2009 09/30/2010 Active 0 0 0 0 0 0 0
Project Totals 0 0 0 0 0 0 0


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

Review: Fish Accord ISRP Review

Independent Scientific Review Panel Assessment

Assessment Number: 2008-601-00-ISRP-20100323
Project: 2008-601-00 - Upper Lemhi River-Acquisition
Review: Fish Accord ISRP Review
Completed Date: None
First Round ISRP Date: 1/27/2010
First Round ISRP Rating: Response Requested
First Round ISRP Comment:

There seems to be a high probability that the acquisitions/easements proposed for this project will benefit anadromous fish populations in the Lemhi River. Increasing flow in tributaries and reconnecting them with the mainstem Lemhi River alone may confer very substantial benefits. However, there was not enough detail provided in the proposal to conduct a thorough technical assessment. In addition, the closely linked nature of this proposal for acquisitions and conservation easements with the project that will implement restoration actions at these sites (Upper Lemhi River Restoration Project #2008-602-00) suggests that the two projects should be reviewed in tandem or combined into a single project. In addition, the following items should be included in a revised proposal: • A set of maps that clearly indicates the location of the project properties and the location of the restoration projects to be implemented on the properties • More detail on the guidance given to those who participated in prioritizing acquisition/easement projects • A list of scores for all properties assessed and an explanation why the selected properties were considered the best options • More detail on how improvements in Chinook and steelhead egg-smolt survival rates were estimated • A description of how the proportion of a limiting factor within the watershed addressed with the application of each restoration action was estimated and how these improvements are translated into benefits for the fish • A better description of the linkage between this project and ISEMP and other ongoing M&E efforts in the Lemhi watershed • A clear description of the role each participating organization plays in this project

Documentation Links:

Project Relationships: This project Merged To 2010-088-00 effective on 8/6/2010
Relationship Description: Projects 2008-601-00 and 2008-605-00 are combined into project 2010-088-00 for contract/project implementation efficiencies.


Name Role Organization
Joe Deherrera (Inactive) Project Manager Bonneville Power Administration
Amy Hines Administrative Contact Idaho Governor's Office of Species Conservation
Mike Edmondson Project Lead Idaho Governor's Office of Species Conservation
Paul Krueger (Inactive) Supervisor Bonneville Power Administration
Donald Rose (Inactive) Env. Compliance Lead Bonneville Power Administration