Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
RSS Feed for updates to Project 2009-011-00 - Leaburg Dam Fish Sorter Follow this via RSS feed. Help setting up RSS feeds?

Project Summary

Project 2009-011-00 - Leaburg Dam Fish Sorter
Project Number:
2009-011-00
Title:
Leaburg Dam Fish Sorter
Summary:
This project will be completed to comply with RPA XXX of the Willamette BiOp.
Proposer:
Proponent Orgs:
Bonneville Power Administration (Govt - Federal)
Starting FY:
2010
Ending FY:
2014
Stage:
Area:
Province Subbasin %
Lower Columbia Willamette 100.00%
Purpose:
Habitat
Emphasis:
Restoration/Protection
Focal Species:
Chinook - Upper Willamette River ESU
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

No photos have been uploaded yet for this Project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

No Decided Budget Transfers

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2024
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2012
2011

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
23394 REL 1 SOW R2 Resource Consultants (R2) 2009-011-00 EXP LEABURG DAM FISH SORTER History $35,499 3/11/2011 - 7/31/2012
23394 REL 2 SOW R2 Resource Consultants (R2) 2009-011-00 MCKENZIE LEABURG HATCHERY ADULT ATTRACTION History $64,329 3/11/2011 - 7/31/2012



Annual Progress Reports
Expected (since FY2004):2
Completed:0
On time:0
Status Reports
Completed:0
On time:0
Avg Days Late:None

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
23394 REL 1 2009-011-00 EXP LEABURG DAM FISH SORTER R2 Resource Consultants (R2) 03/11/2011 07/31/2012 History 0 0 0 0 0 0 0
23394 REL 2 2009-011-00 MCKENZIE LEABURG HATCHERY ADULT ATTRACTION R2 Resource Consultants (R2) 03/11/2011 07/31/2012 History 0 0 0 0 0 0 0
Project Totals 0 0 0 0 0 0 0


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

No assessments are available for this project.
Project Relationships: None

Name Role Organization
Cecilia Brown (Inactive) Project Manager Bonneville Power Administration
Paul Krueger (Inactive) Interested Party Bonneville Power Administration
Rosemary Mazaika (Inactive) Interested Party Bonneville Power Administration
Ronald Costello (Inactive) Interested Party Bonneville Power Administration
Edward Gresh Env. Compliance Lead Bonneville Power Administration