View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Mountain Columbia | Kootenai | 100.00% |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Acct FY | Acct Type | Amount | Fund | Budget Decision | Date |
---|---|---|---|---|---|
FY2024 | Expense | $79,179 | From: Fish Accord - Kootenai | Kootenai Tribe of Idaho (KToI) 2023-2025 MOA Extension | 09/30/2022 |
FY2025 | Expense | $81,159 | From: Fish Accord - Kootenai | Kootenai Tribe of Idaho (KToI) 2023-2025 MOA Extension | 09/30/2022 |
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
63354 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF IDAHO REGIONAL COORDINATION | Closed | $46,049 | 11/1/2013 - 3/31/2015 |
68205 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF IDAHO REGIONAL COORDINATION | Closed | $37,927 | 4/1/2015 - 3/31/2016 |
71453 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF ID REGIONAL COORDINATION | Closed | $69,840 | 4/1/2016 - 3/31/2017 |
75608 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF ID REGIONAL COORDINATION | Closed | $62,178 | 4/1/2017 - 3/31/2018 |
76826 REL 2 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF ID REGIONAL COORDINATION | Closed | $55,705 | 4/1/2018 - 3/31/2019 |
76826 REL 11 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF ID REGIONAL COORDINATION | Closed | $58,942 | 4/1/2019 - 3/31/2020 |
76826 REL 17 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF ID REGIONAL COORDINATION | Closed | $59,710 | 4/1/2020 - 3/31/2021 |
76826 REL 24 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF ID REGIONAL COORDINATION | Closed | $66,345 | 4/1/2021 - 3/31/2022 |
76826 REL 30 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF ID REGIONAL COORDINATION | Closed | $75,606 | 4/1/2022 - 3/31/2023 |
84055 REL 4 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF ID REGIONAL COORDINATION | Closed | $77,199 | 4/1/2023 - 3/31/2024 |
84055 REL 9 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF ID REGIONAL COORDINATION | Issued | $79,179 | 4/1/2024 - 3/31/2025 |
CR-374682 SOW | Kootenai Tribe | 2013-006-00 EXP KOOTENAI TRIBE OF ID REGIONAL COORDINATION | Pending | $158,340 | 4/1/2025 - 3/31/2027 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 10 |
Completed: | 10 |
On time: | 10 |
Status Reports | |
---|---|
Completed: | 44 |
On time: | 17 |
Avg Days Late: | 4 |
Count of Contract Deliverables | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Earliest Contract | Subsequent Contracts | Title | Contractor | Earliest Start | Latest End | Latest Status | Accepted Reports | Complete | Green | Yellow | Red | Total | % Green and Complete | Canceled |
63354 | 68205, 71453, 75608, 76826 REL 2, 76826 REL 11, 76826 REL 17, 76826 REL 24, 76826 REL 30, 84055 REL 4, 84055 REL 9, CR-374682 | 2013-006-00 EXP KOOTENAI TRIBE OF ID REGIONAL COORDINATION | Kootenai Tribe | 11/01/2013 | 03/31/2027 | Pending | 44 | 32 | 4 | 0 | 0 | 36 | 100.00% | 0 |
Project Totals | 44 | 32 | 4 | 0 | 0 | 36 | 100.00% | 0 |
Name | Role | Organization |
---|---|---|
Virgil Watts III | Interested Party | Bonneville Power Administration |
David Kaplowe | Supervisor | Bonneville Power Administration |
Ashley Gray | Administrative Contact | Kootenai Tribe |
Jennifer Plemons | Project Manager | Bonneville Power Administration |
Gary Aitken, Jr | Supervisor | Kootenai Tribe |
Shelby Therrian | Project Lead | Kootenai Tribe |
Nathan Jensen | Interested Party | Kootenai Tribe |