RSS Feed for updates to Project 2024-001-00 - Coeur d'Alene Anadromous & Resident Hatchery Planning & Design Follow this via RSS feed. Help setting up RSS feeds?

Project Summary

Project 2024-001-00 - Coeur d'Alene Anadromous & Resident Hatchery Planning & Design

Please Note: This project is the product of one or more merges and/or splits from other projects. Historical data automatically included here are limited to the current project and previous generation (the “parent” projects) only. The Project Relationships section details the nature of the relationships between this project and the previous generation. To learn about the complete ancestry of this project, please review the Project Relationships section on the Project Summary page of each parent project.

Project Number:
2024-001-00
Project Title:
Coeur d'Alene Anadromous & Resident Hatchery Planning & Design
Summary:
This project, established 2/22/24 in the CDA Accord, was modified 5/28/26 to include the scope of project 2024-007-00. Both projects entail the scoping/planning, design, and environmental compliance tasks consistent with the Step Process. In order to maximize planning efficiencies, resident and anadromous teams are working together. This may result in a shared, central facility however this will be determined through forthcoming on-the-ground findings. The projects will support the Coeur d'Alene Tribe's participation in regional anadromous and resident fisheries research and management forums, including but not limited to: The US Army Corps NWD Technical Management Team, Northwest Power and Conservation Council's Fish & Wildlife Program, Hatchery and Genetics Management Planning, ESA Planning, environmental compliance, and other processes associated to mitigation programs under the Northwest Power Act. Once hatchery operations are underway, this project will also support an anadromous hatchery evaluation and harvest monitoring program. Post-construction resident hatchery evaluation and harvest monitoring program work will reside in a different Project, such as 1990-044-00, however has not been confirmed.
Effective 5/28/26: Project 2024-007-00 will merge into 2024-001-00 in order to plan and design both hatcheries under one project.
Proposer:
Proponent Org:
Coeur D'Alene Tribe (Tribe)
Starting FY:
2024
Ending FY:
2033
BPA PM:
Project Stage:
Implementation - Project Status Report
Project Area:
Province Subbasin %
Intermountain Coeur D'Alene 100.00%
Purpose:
Artificial Production
Emphasis:
Supplementation
Focal Species:
Chinook - Upper Columbia River Spring ESU
Chinook - Upper Columbia River Summer/Fall ESU
Coho - Unspecified Population
Sockeye - Okanogan River ESU
Steelhead - Upper Columbia River DPS
Species Benefit:
Anadromous: 0.0%   Resident: 100.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

No photos have been uploaded yet for this Project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

Decided Budget Transfers  (FY2025 - FY2027)

Acct FY Acct Type Amount Fund Budget Decision Date
FY2025 Expense $269,885 From: LTFA - Coeur d'Alene Fish Accord - Coeur d'Alene (2/22/2024) 02/22/2024
FY2025 Expense $269,885 To: LTFA - Coeur d'Alene Accord Transfers (CDA-Multi-Year) 12/12/25 12/15/2025
FY2026 Expense $276,632 From: LTFA - Coeur d'Alene Fish Accord - Coeur d'Alene (2/22/2024) 02/22/2024
FY2027 Expense $283,548 From: LTFA - Coeur d'Alene Fish Accord - Coeur d'Alene (2/22/2024) 02/22/2024

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2026
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2024 (Draft)

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
84053 REL 11 SOW Coeur D'Alene Tribe 2024-001-00 EXP PLAN & DESIGN ANADROMOUS HATCHERY Issued $1,416,649 9/1/2024 - 8/31/2026
CR-384924 Coeur D'Alene Tribe EXP ANADROMOUS/RESIDENT HATCHERY PLANNING Pending $2,453,517 9/1/2026 - 8/31/2028



Annual Progress Reports
Expected (since FY2004):0
Completed:0
On time:0
Status Reports
Completed:7
On time:7
Avg Days Early:5

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
84053 REL 11 CR-384924 EXP ANADROMOUS/RESIDENT HATCHERY PLANNING Coeur D'Alene Tribe 09/01/2024 08/31/2028 Pending 6 0 4 0 0 4 100.00% 0
Project Totals 6 0 4 0 0 4 100.00% 0


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

No assessments are available for this project.
Project Relationships: This project Merged From 2024-007-00 effective on 5/28/2026
Relationship Description: The decision was made to combine the hatchery planning and design projects for the Coeur d'Alene anadromous and resident facilities.

This project Enables 2026-001-00 effective on 5/28/2026
Relationship Description: The planning and design for this hatchery will be completed under project 2024-001-00.

This project Enables 2027-002-00 effective on 5/28/2026
Relationship Description: The planning and design for this hatchery will be completed under project 2024-001-00.


Name Role Organization
Angelo Vitale Technical Contact Coeur D'Alene Tribe
Cajeton Matheson Supervisor Coeur D'Alene Tribe
Ralph Allan Interested Party Coeur D'Alene Tribe
Thomas Biladeau Technical Contact Coeur D'Alene Tribe
Mary Haight Project SME Bonneville Power Administration
Jon Firehammer Technical Contact Coeur D'Alene Tribe
Edward Gresh Env. Compliance Lead Bonneville Power Administration
Mary Haight Project Manager Bonneville Power Administration
Aaron Penney Project Lead Coeur D'Alene Tribe
Jenna Peterson Interested Party Bonneville Power Administration