View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Please Note: This project is the product of one or more merges and/or splits from other projects. Historical data automatically included here are limited to the current project and previous generation (the “parent” projects) only. The Project Relationships section details the nature of the relationships between this project and the previous generation. To learn about the complete ancestry of this project, please review the Project Relationships section on the Project Summary page of each parent project.
| Province | Subbasin | % |
|---|---|---|
| Intermountain | Coeur D'Alene | 100.00% |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
| Acct FY | Acct Type | Amount | Fund | Budget Decision | Date |
|---|---|---|---|---|---|
| FY2025 | Expense | $269,885 | From: LTFA - Coeur d'Alene | Fish Accord - Coeur d'Alene (2/22/2024) | 02/22/2024 |
| FY2025 | Expense | $269,885 | To: LTFA - Coeur d'Alene | Accord Transfers (CDA-Multi-Year) 12/12/25 | 12/15/2025 |
| FY2026 | Expense | $276,632 | From: LTFA - Coeur d'Alene | Fish Accord - Coeur d'Alene (2/22/2024) | 02/22/2024 |
| FY2027 | Expense | $283,548 | From: LTFA - Coeur d'Alene | Fish Accord - Coeur d'Alene (2/22/2024) | 02/22/2024 |
| Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
|---|---|---|---|---|---|
|
84053 REL 11
|
Coeur D'Alene Tribe | 2024-001-00 EXP PLAN & DESIGN ANADROMOUS HATCHERY | Issued | $1,416,649 | 9/1/2024 - 8/31/2026 |
| CR-384924 | Coeur D'Alene Tribe | EXP ANADROMOUS/RESIDENT HATCHERY PLANNING | Pending | $2,453,517 | 9/1/2026 - 8/31/2028 |
| Annual Progress Reports | |
|---|---|
| Expected (since FY2004): | 0 |
| Completed: | 0 |
| On time: | 0 |
| Status Reports | |
|---|---|
| Completed: | 7 |
| On time: | 7 |
| Avg Days Early: | 5 |
| Count of Contract Deliverables | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Earliest Contract | Subsequent Contracts | Title | Contractor | Earliest Start | Latest End | Latest Status | Accepted Reports | Complete | Green | Yellow | Red | Total | % Green and Complete | Canceled |
| 84053 REL 11 | CR-384924 | EXP ANADROMOUS/RESIDENT HATCHERY PLANNING | Coeur D'Alene Tribe | 09/01/2024 | 08/31/2028 | Pending | 6 | 0 | 4 | 0 | 0 | 4 | 100.00% | 0 |
| Project Totals | 6 | 0 | 4 | 0 | 0 | 4 | 100.00% | 0 | ||||||
| Project Relationships: |
This project Merged From 2024-007-00 effective on 5/28/2026
Relationship Description: The decision was made to combine the hatchery planning and design projects for the Coeur d'Alene anadromous and resident facilities. This project Enables 2026-001-00 effective on 5/28/2026 Relationship Description: The planning and design for this hatchery will be completed under project 2024-001-00. This project Enables 2027-002-00 effective on 5/28/2026 Relationship Description: The planning and design for this hatchery will be completed under project 2024-001-00. |
|---|
| Name | Role | Organization |
|---|---|---|
| Angelo Vitale | Technical Contact | Coeur D'Alene Tribe |
| Cajeton Matheson | Supervisor | Coeur D'Alene Tribe |
| Ralph Allan | Interested Party | Coeur D'Alene Tribe |
| Thomas Biladeau | Technical Contact | Coeur D'Alene Tribe |
| Mary Haight | Project SME | Bonneville Power Administration |
| Jon Firehammer | Technical Contact | Coeur D'Alene Tribe |
| Edward Gresh | Env. Compliance Lead | Bonneville Power Administration |
| Mary Haight | Project Manager | Bonneville Power Administration |
| Aaron Penney | Project Lead | Coeur D'Alene Tribe |
| Jenna Peterson | Interested Party | Bonneville Power Administration |