Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 53046: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Project Number:
Title:
Walla Walla River Basin Fish Habitat Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
53046
Contract Title:
1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
46692: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
  • 56348: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Contract Status:
Closed
Contract Description:
The CTUIR Walla Walla River Basin Fish Habitat Enhancement Project, initiated in 1996, is an ongoing effort to monitor, protect, enhance, and restore the natural form and function of rivers, floodplains, and native fish habitat.  

Major tasks to be completed by the project in this funding cycle include:  

1.  Hire a consultant to complete a restoration and design plan for approximately one mile of the mainstem Walla Walla River at the Kentch Property.

2. Coordinate with the Walla Walla Basin Watershed Council in the design of a passage barrier fix at the Smith sill drop-structure on the mainstem Walla Walla River. The project will be providing $10,000 in cost share for this work.  

3. Replace an undersized culvert that is currently a passage barrier on Couse Creek near the Konen Rock Pit with a new bridge.

4. Continue noxious weed control measures within approximately 10 stream miles of project areas.  

5. Collect and analyze project effectiveness monitoring data within a portion of the project areas.

6. Meet with private landowners, scope and develop conceptual plans for out-year restoration work with priority reaches of the basin.

7. Continue to provide technical support and coordination within the Mill Creek Working Group, Priority Projects Group, Snake River Recovery Board, Oregon Solutions Process, and others as needed.
Account Type(s):
Expense
Contract Start Date:
02/01/2011
Contract End Date:
01/31/2012
Current Contract Value:
$1,403,736
Expenditures:
$1,403,736

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Projects identified for out-years A: 114. Identify and select projects in Walla Walla Basin 08/31/2011 06/30/2011
Project summaries complete B: 115. Inventory project areas 07/30/2011 06/30/2011
All project admin activities managed D: 119. Conduct all management activities 01/31/2012 01/31/2012
Environmental compliance complete E: 165. Compliance for on-the-ground work 06/30/2011 06/30/2011
Provide technical support through interagency coordination and public forum F: 122. Provide technical support 01/31/2012 01/31/2012
Final design developed for mainstem Walla Walla River at mouth of Couse Creek G: 175. Develop assessment and design at mouth of Couse Creek 11/30/2011 11/30/2011
Instream enhancement complete H: 29. Instream work on Lampson-Walla Walla River 10/31/2011 10/31/2011
Maintenance of reintroduced native plants and control of noxious weeds J: 22. Control noxious weeds, replant veg within project areas 01/31/2012 12/30/2011
Remove false indigo and document BMP's for controlling the plant K: 53. Remove False Indigo on the Touchet River 12/31/2011 06/30/2011
Kentch house & out-buildings removed L: 27. Demolish and remove abandoned buildings at Kentch 06/30/2011 06/30/2011
Fences maintained at full functionality M: 186. Maintain Fences 01/31/2012 01/31/2012
Project effectiveness data collection complete N: 157. Field Data Collection 10/31/2011 10/31/2011
Document most effective methods for controlling False Indigo O: 157. Collect data concerning control methods for False Indigo 12/31/2011 06/30/2011
Data analysis complete P: 162. Project Monitoring Data Analysis 01/31/2012 12/31/2011
Attach Progress Report in Pisces Q: 132. Submit Progress Report for the period 2/1/2009 to 1/31/2010 04/30/2011 04/30/2011
Permanent Conservation Easement on Wolf Fork S: 92. Permanent conservation easement on Wolf Fork 12/15/2011 01/31/2012
Low elevation photos complete T: 157. Low elevation aerial flights on Walla Walla River 07/30/2011 06/30/2011
Mid basin assessment and action plan completed U: 115. Develop mid basin assessment and action plan 08/15/2011 08/15/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 27 Remove Debris
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 53 Remove Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 27 Remove Debris
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 53 Remove Vegetation
  • 1 instance of WE 92 Lease Land
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 27 Remove Debris
  • 1 instance of WE 53 Remove Vegetation
  • 1 instance of WE 92 Lease Land
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 53 Remove Vegetation
  • 1 instance of WE 92 Lease Land
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Trout, Interior Redband (O. mykiss gairdnerii)
  • 1 instance of WE 53 Remove Vegetation
  • 1 instance of WE 92 Lease Land
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 114 Identify and select projects in Walla Walla Basin 02/01/2011
B 115 Inventory project areas 02/01/2011
C 185 Periodic Status Reports for BPA 02/01/2011
D 119 Conduct all management activities 02/01/2011
E 165 Compliance for on-the-ground work 02/01/2011
F 122 Provide technical support 02/01/2011
G 175 Develop assessment and design at mouth of Couse Creek 02/01/2011
H 29 Instream work on Lampson-Walla Walla River 06/07/2011
I 175 Develop final site assessment and restoration plan at Kentch 02/01/2011
J 22 Control noxious weeds, replant veg within project areas 03/29/2011
K 53 Remove False Indigo on the Touchet River 03/29/2011
L 27 Demolish and remove abandoned buildings at Kentch 03/11/2011
M 186 Maintain Fences 02/01/2011
N 157 Field Data Collection 02/01/2011
O 157 Collect data concerning control methods for False Indigo 02/01/2011
P 162 Project Monitoring Data Analysis 02/01/2011
Q 132 Submit Progress Report for the period 2/1/2009 to 1/31/2010 02/01/2011
R 132 Submit Progress Report for the period 2/1/2010 to 1/31/2011 02/01/2011
S 92 Permanent conservation easement on Wolf Fork 12/22/2011
T 157 Low elevation aerial flights on Walla Walla River 02/01/2011
U 115 Develop mid basin assessment and action plan 02/01/2011