Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 4277: 1998-007-02 GRANDE RONDE SUPPLEMENTATION - O&M
Project Number:
Title:
Grande Ronde Supplementation Operations and Maintenance (O&M) and Monitoring and Evaluation (M&E) on Lostine River
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
4277
Contract Title:
1998-007-02 GRANDE RONDE SUPPLEMENTATION - O&M
Contract Continuation:
Previous: Next:
n/a
  • 25641: 1998 007 02 GRANDE RONDE SUPPLEMENTATION - LOSTINE O & M
Contract Status:
Closed
Contract Description:
Final Excersize May 2005
Grande Ronde Supplementation - Lostine River Spring Chinook
Statement of Work and Budget FY2005

BPA Project Number:  1998-007-02
BPA Project Title: Grande Ronde Supplementation - Lostine River Spring Chinook
Contract Number:  4277
Contract Title: 1998-007-02 Grande Ronde Supplementation
Performance/Budget Period: 01/01/00 - 12/31/05

AUTHORIZATION & RELATIONSHIP TO THE COLUMBIA BASIN FISH AND WILDLIFE PROGRAM: The Grande Ronde Supplementation - Lostine River Spring Chinook Operations and Maintenance program is a cooperative project between the NPT, ODFW, CTUIR, and USFWS.  This program was initiated in 1994 as a conservation measure in response to severely declining runs of chinook salmon in the Grande Ronde Basin.  The program utilizes supplementation with conventional and captive brood production to prevent extirpation and begin rebuilding of ESA listed spring chinook.

The Lostine River Chinook program relates to many of the Columbia Basin Fish and Wildlife Program (FWP) objectives and measures (NPPC 1994).  Measure 7.2D.1, encourages incorporating effective husbandry practices and Measure 7.2D.3 includes the investigation of hatchery rearing operations and release strategies to improve survival of propagated fish.  In addition, this project furthers development of FWP Measure 7.4D (Captive Brood Stocks), 7.4F (Portable Facilities for Adult Salmon Collection and Holding, and for Juvenile Salmon Acclimation), and 7.4O (Small-Scale Production Projects).  The monitoring and evaluation research outlined in this proposal is consistent with FWP Measure 7.1C (baseline data collection from naturally spawning populations), Measure 7.2A.6 which stresses the need for evaluating the genetic and ecological impacts of outplanting hatchery fish on wild populations, Measure 7.4L.1, which mandates evaluation of supplementation projects to increase production.  Finally, Measure 7.4D.3 encourages the study of hatchery rearing and release strategies to improve survival and adaptation of cultured fish.
The strength of these mandates is intensified by the inclusion of the Lostine River spring chinook population as listed under the Endangered Species Act on May 22, 1992. The facilities and activities associated with this program have been authorized under ESA Section 10 and Section 7 Permits and Biological Opinions.  These documents include ESA Section 10 Permit No. 973, Permit No. 1011 (ODFW 1996), Modification of Permit No. 1011, Permit No. 1149 (BIA 1998) and Permit No. 1164, FWS Section 7 Biological Opinion 501.1100,1-4-98-F4 (bull trout), and NMFS Section 10 Biological Opinion (1998).

RPA Discussion: The RPA that applies to this project is Hatchery Action #177.  The Lostine project is part of the safety net program identified in the Federal Columbia River Power System Biological Opinion.  The contract deliverables are:

* Develop Annual Operation Plan
* Acclimate and release approximately 250,000 smolts in natal basin.
* Trap adult Chinook across the entire run and distribute according to Monitoring and Evaluation program criteria. (Run size estimates unavailable at this time.)
* Retain and transport a portion of trapped adult Chinook to Lookingglass Fish Hatchery to be held for conventional program egg source.
* Spawn retained adult Chinook  at Lookingglass Fish Hatchery to provide eggs for conventional program.
* Provide egg care for Lostine River egg source including conventional program eggs  and captive brood program eggs for the entire Grande Ronde Supplementation project.

PROJECT SUMMARY:

The Grande Ronde River subbasin historically supported large runs of wild chinook salmon.  Adult returns to the Grande Ronde in the late 1950's were estimated at more than 10,000 fish per year.  Escapement levels have since declined to what co-managers have determined is an emergency situation.  The Upper Grande Ronde River, Catherine Creek and the Lostine River were historically three of the most productive spawning and rearing areas in the Grande Ronde basin.  In 1958, 893 spring chinook redds were counted in the Lostine River.  In contrast, 16 redds were counted in 1994 and 11 redds in 1995.

In 1994, fisheries co-managers, Oregon Department of Fish and Wildlife (ODFW), Nez Perce Tribe (NPT), and Confederated Tribes of the Umatilla Indian Reservation (CTUIR) implemented a supplementation program utilizing indigenous stock in the Upper Grande Ronde, Catherine Creek, and Lostine River.  This project was identified by tribal, state and federal managers as one of the 15 high priority projects warranting immediate implementation.  The NPT, in coordination with ODFW, is responsible for operating supplementation facilities (adult collection and holding and juvenile acclimation and release) on the Lostine River.  

Lostine River Acclimation Facility

The Lostine River acclimation facility was constructed in 1998 and is located approximately twelve miles upstream from the mouth.  Facility design capacity is approximately 250,000 fish at 20 fish/lb with a density index of 0.28.  The facility consists of a water supply intake, supply pipeline, four raceways, drain/release pipes and in-line PIT tag detection devices.

Lostine River Adult Monitoring and Collection Facility

Beginning in 1997, the project has operated the adult weir facility located approximately one mile upstream from the mouth for the collection of broodstock and baseline data on adult chinook escapement to the Lostine River. The adult weir facility consists of a collapsible panel weir which spans the entire width of the river and a trap unit to ensure fullest collection of returning adult chinook. Adult trapping has ranged from 13 to 1,091 fish annually with about 65% of the run being trapped each of the last four years.

Smolt to adult survival rate to the Lostine River for the complete set of adult returns from the conventionally produced fish released in 1999 was slightly greater than 1%. As a result of our activities, the 5 females removed from the natural population for the supplementation program in 1997 resulted in at least a total of 44 females returning to the Lostine River in 2001and 2002. These returning adults provided 34 females for natural spawning and 8 females that survived to contribute to the conventional supplementation program. Final numbers are not available at this time to provide updates to the actual program SAR for this document.

COORDINATION:

The Nez Perce Tribe, Oregon Department of Fish and Wildlife and the Confederated Tribes of the Umatilla Indian Reservation, developed the Grande Ronde Supplementation - Lostine River Spring Chinook Operations and Maintenance program cooperatively. All activities involving the program (operation and monitoring/evaluation), i.e., spawning ground surveys, adult trapping, spawning, incubation, juvenile rearing, juvenile tagging and marking, and smolt release will be coordinated among the co-managers.  Documents cooperatively prepared describing program operations include: ESA Section 10 permit applications (ODFW1996, ODFW 1998, BIA 1998) and LSRCP Annual Operating Plans (AOP).

Forums that the co-managers participate in to coordinate operations are LSRCP Evaluation Coordination Committee, Columbia Basin Fish and Wildlife Authority, Conservation Planning Oversight Committee, Captive/Conventional Broodstock Technical Oversight Team, and the U.S. v. Oregon Production and Policy Committees.  All activities are permitted under the ESA Section 10 Permit process.  Funding and program oversight is through BPA.  Other entities involved in the project include USFWS, NMFS, NPPC, CBFWA.  Coordination also occurs with landowners leasing property for facilities and cultural resource, construction and engineer consultants involved in developing and operating the adult and juvenile facilities.
Coordination internally for Nez Perce Tribe includes attending all relevant Inter- and Intra-agency meetings as required to coordinate activities and share project information. Included are internal coordination meetings to abide by the Nez Perce Tribe policies and procedures as required (Human Resources, Finance, Resolutions, Administrative Actions, etc.) and with all other policy personnel directions.

PROJECT GOALS AND 2005 OBJECTIVES

The overall goal of this supplementation program is; 1) to prevent extinction, 2) to provide a future basis to reverse the decline in stock abundance, and 3) to ensure a high probability of population persistence.  The Nez Perce Tribe is responsible for implementation, coordination, and facilitation of the Lostine River component of the Grande Ronde Supplementation projects.  Activities conducted under this project are associated with operations and maintenance.

O&M Goal:  Operate and maintain adult collection and juvenile acclimation and release facilities necessary to implement the Lostine River portion of the Grande Ronde  Supplementation - Lostine River Spring Chinook Operations and Maintenance program  and achieve the overall program goal of increasing adult returns.
Account Type(s):
Expense
Contract Start Date:
01/01/2000
Contract End Date:
12/31/2005
Current Contract Value:
$1,624,938
Expenditures:
$1,624,938

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Mickey Carter Bonneville Power Administration No Env. Compliance Lead macarter@bpa.gov (503) 230-5885
Rex Graham Nez Perce Tribe No Administrative Contact rexg@nezperce.org (206) 843-7319
James Harbeck Nez Perce Tribe No Interested Party jimh@nezperce.org (541) 432-2501
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
Rebecca Johnson Nez Perce Tribe No Supervisor beckyj@nezperce.org (208) 621-4629
Kenneth Kirkman Bonneville Power Administration Yes COR kckirkmam@bpa.gov (503) 230-5557
Ed Larson Nez Perce Tribe Yes Supervisor edl@nezperce.org (208) 843-7320x4630
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Bruce McLeod Nez Perce Tribe Yes Interested Party brucem@nezperce.org (208) 843-7320x4628
Sam Onjukka Oregon Department of Fish and Wildlife No Interested Party
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Kelly Wasson Nez Perce Tribe No Administrative Contact kellyw@nezperce.org (208) 843-7317
Rick Zollman Nez Perce Tribe Yes Contract Manager rickz@nezperce.org (541) 432-2505


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Deliverable complete A: 118. Lostine River O&M Project Coordination 12/31/2005 12/31/2005
Deliverable complete B: 174. Develop Annual Operation Plan For Northeast Oregon Region 02/28/2005 09/30/2005
Deliverable complete C: 56. Acclimate and Release Spring/Summer Smolts from Lostine River Acclimation Facility 04/28/2005 09/30/2005
Deliverable complete D: 61. Lostine River O&M Facility Maintenance 12/31/2005 12/31/2005
Deliverable complete E: 70. Lostine River Adult Monitoring and Evaluation 12/31/2005 10/16/2005
Deliverable complete F: 66. Collect Spring/Summer Chinook at Lostine River Adult Facility 12/31/2005 10/31/2005
Deliverable complete G: 64. Lookingglass Hatchery Adult Spring/Summer Chinook Care and Spawning 12/31/2005 09/30/2005
Deliverable complete H: 99. Educational Tours Of Lostine River Facilities. 12/31/2005 12/31/2005
Deliverable complete I: 141. Status Reports 01/07/2006 12/31/2005
Deliverable complete J: 132. Grande Ronde Supplementation - Lostine River Spring/Summer Chinook Reporting 02/15/2006 12/31/2005
Deliverable complete K: 165. Assist BPA NEPA Group in Obtaining Permits 12/31/2005 12/31/2005
Deliverable complete L: 119. Manage and Administer Project 12/31/2005 12/31/2005

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 64 Spawn Fish
  • 1 instance of WE 56 Acclimate Juvenile Fish
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 118 Lostine River O&M Project Coordination
B 174 Develop Annual Operation Plan For Northeast Oregon Region
C 56 Acclimate and Release Spring/Summer Smolts from Lostine River Acclimation Facility
D 61 Lostine River O&M Facility Maintenance
E 70 Lostine River Adult Monitoring and Evaluation
F 66 Collect Spring/Summer Chinook at Lostine River Adult Facility
G 64 Lookingglass Hatchery Adult Spring/Summer Chinook Care and Spawning
H 99 Educational Tours Of Lostine River Facilities.
I 141 Status Reports
J 132 Grande Ronde Supplementation - Lostine River Spring/Summer Chinook Reporting
K 165 Assist BPA NEPA Group in Obtaining Permits
L 119 Manage and Administer Project
M 185