Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 44293: 200871000 EXP BIOP CHUM RESTORATION
Project Number:
Title:
Chum Salmon Restoration in the tributaries below Bonneville Dam
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
44293
Contract Title:
200871000 EXP BIOP CHUM RESTORATION
Contract Continuation:
Previous: Next:
n/a
  • 50204: 2008-710-00 EXP CHUM HABITAT RESTORE SUPPLEMENT
Contract Status:
Closed
Contract Description:
WDFW identified a phased approach for the implementation of this proposal (see attached Revised Proposal 6/5/09):
Phase 1: Development of an integrated program for chum salmon habitat restoration and supplementation/ reintroduction in FFY 2009;
Phase 2: Full implementation of the program in FFY 2010.  

Phase 1 -- Program development in FFY 2009
1)  An assessment of priority habitat restoration and/or chum channel sites;
2)  An updated stock status review of LCR chum salmon population structure and abundance necessary to prioritize restoration and guide future implementation of supplementation/reintroduction;
3)  Adaptive management of existing supplementation programs;
4)  Development of a stepwise enhancement program that utilizes supplementation/reintroduction to rebuild LCR chum populations;
5)  Development of a comprehensive program to monitor LCR chum salmon populations and evaluate the effectiveness of habitat restoration and supplementation/reintroduction actions .


Seven specific objectives were identified within the project components listed above:
Objective 1:  Habitat restoration and chum channel site assessment;
Objective 2:  Lower Columbia River chum salmon stock status review;
Objective 3:  Develop an integrated supplementation/ reintroduction strategy for Lower Columbia River chum salmon;
Objective 4:  Monitoring and evaluation program development within the context of an Adaptive Management Framework;
Objective 5:  Grays River chum salmon supplementation;
Objective 6:  Removal of invasive vegetation in Hamilton Spring channel; and
Objective 7:  Initiate Three Step Review for a least one top ranked project identified by the habitat restoration and chum channel site assessment.


The final NPCC recommendation for this 2008 FCRPS BiOp project was made on August 12, 2009 and indicated:

"The Council supports the project for implementation (i.e., Objectives 1,2,4 and 6) with the condition that the qualifications and responses identified by the ISRP (ISRP document 2009-29) for Objectives 3 and 5 be addressed as part of the anticipated Step Review associated with Objective 7. Full implementation of these objectives (i.e., Objectives 3,5 and 7) is dependent on future reviews of the ISRP and Council."  In addition, "The Council supports efforts at the Grays River Conservation hatchery at the proposed $35,000 funding level until these activities and other supplementation/reintroduction strategies are confirmed through the anticipated step review as outlined in Objective 7 of the project."

FINAL BUDGET:
Originally, the first year budget for this project to address Phase I tasks was $265,000 with an anticipated start date in early 2009.  Due to the review process (ISRP review, WDFW response, Council review and approval), the actual project start date was pushed to July 1, 2009, established by a pre-award from BPA to begin critical project work.  As a result of this,  on-going field activities proposed to be funded in the second year's budget (Phase 2) had to be moved into the first year's budget to prevent loss of continuity.  As a result, the $265,000 funding level for first year activities was increased to $496,852 to include these activities.  The following summarizes these additions:


Original budget:  $265,082
09 Grays Conservation Program: $35,000
Reinitiate Duncan Hatchery Supplementaion: $121,757
Grays Juvenile Chum  Trapping: $55,303
Additional staff time to cover added task/detail as recommended by ISRP: $19,710
TOTAL: $496,852
Account Type(s):
Expense
Contract Start Date:
07/01/2009
Contract End Date:
09/30/2010
Current Contract Value:
$496,841
Expenditures:
$496,841

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental compliance documents for Grays River chum salmon supplementation A: 165. Environmental compliance documents for Grays River chum salmon supplementation 06/30/2010 06/30/2010
Report on habitat restoration and chum channel site assessment B: 114. Habitat restoration and chum channel site assessment 09/30/2010 09/30/2010
Completed LCR chum salmon stock status review C: 162. Lower Columbia River (LCR) chum salmon stock status review 09/30/2010 09/30/2010
Release of thermally marked chum salmon fed-fry D: 176. Grays River chum supplementation program 05/01/2010 05/01/2010
Complete step 1 of a combined 3-Step Process for a Grays River chum salmon supplementation program E: 168. Initiate Council 3-Step process for Grays River chum salmon supplementation 09/30/2010 09/30/2010
Complete step 2 of a combined 3-Step Process for a Grays River chum salmon supplementation program F: 169. Complete Step 2 of Council 3-Step process for Grays River chum salmon supplementation 09/30/2010 09/30/2010
Complete step 3 of a combined 3-Step Process for a Grays River chum salmon supplementation program G: 170. Complete Step 3 of Council 3-Step process for Grays River chum salmon supplementation 09/30/2010 09/30/2009
Submit completed combined 3-Step review H: 174. Produce combined 3-Step review report for Grays River chum salmon supplementation 09/30/2010
Supplementation/reintroduction strategy for LCR chum salmon I: 174. Future supplementation/reintroduction strategy development 09/30/2010 09/30/2010
Step 1 initiated for a Council 3-Step review for a yet-to-be identified chum salmon project J: 168. Initiate a Council 3-Step review 09/30/2010
Draft plan K: 174. Population monitoring and evaluation program development 08/20/2010 09/30/2007
Removal of non-native vegetation in Hamilton Spring channel L: 53. Hamilton Spring Channel - remove canary reed grass 09/15/2009 09/25/2009
Seine adults for broodstock M: 66. Seining activities for adult broodstock collection for spawning at Washougal Hatchery 01/15/2010 12/31/2009
Adult data for artificial production N: 157. Sampling of adults used for artificial propagation 01/15/2010 12/31/2009
Fecundity estimates O: 157. Sampling of eggs for individual female fecundity 02/15/2010 02/15/2010
Fry data - ponding and thermal marking P: 157. Sampling of chum fry and collection of thermally marked voucher fry 04/30/2010 04/30/2010
Thermally marked chum salmon fed-fry for release at Duncan Creek Q: 176. Produce thermally marked chum salmon fed-fry for release into Duncan Creek 05/31/2010 05/14/2010
Fecundity Estimates R: 162. Analysis of hatchery data 06/30/2010 06/30/2010
Installation and removal of smolt trap S: 70. Install and remove Grays River smolt trap 08/04/2010 08/04/2010
Characterize life history diversity of juvenile salmonids trapped from the Grays River T: 157. Grays River Juvenile Monitoring 08/31/2010 08/20/2010
Characterize life history diversity of juvenile salmonids trapped from the Grays River U: 162. Analyze data collected from Grays River smolt trap 09/30/2010 09/30/2010
Successful Project/Contract Administration V: 119. Manage and administer project 09/30/2010 09/30/2010
Attach Annual Report in Pisces W: 132. Submit Progress Report - March 2009 to February 2010 09/25/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chum (Oncorhynchus keta) - Columbia River ESU (Threatened)
  • 1 instance of WE 53 Remove Vegetation
  • 2 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 3 instances of WE 174 Produce Plan
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 162 Analyze/Interpret Data
  • 2 instances of WE 168 Council 3-step Process: Step 1
  • 1 instance of WE 169 Council 3-step Process: Step 2
  • 1 instance of WE 170 Council 3-step Process: Step 3

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental compliance documents for Grays River chum salmon supplementation 02/09/2007
B 114 Habitat restoration and chum channel site assessment 02/09/2007
C 162 Lower Columbia River (LCR) chum salmon stock status review 07/01/2009
D 176 Grays River chum supplementation program 10/08/2009
E 168 Initiate Council 3-Step process for Grays River chum salmon supplementation 02/09/2007
F 169 Complete Step 2 of Council 3-Step process for Grays River chum salmon supplementation 02/09/2007
G 170 Complete Step 3 of Council 3-Step process for Grays River chum salmon supplementation 02/09/2007
H 174 Produce combined 3-Step review report for Grays River chum salmon supplementation 07/01/2009
I 174 Future supplementation/reintroduction strategy development 02/09/2007
J 168 Initiate a Council 3-Step review 02/09/2007
K 174 Population monitoring and evaluation program development 02/09/2007
L 53 Hamilton Spring Channel - remove canary reed grass 07/23/2009
M 66 Seining activities for adult broodstock collection for spawning at Washougal Hatchery 08/26/2009
N 157 Sampling of adults used for artificial propagation 08/26/2009
O 157 Sampling of eggs for individual female fecundity 08/26/2009
P 157 Sampling of chum fry and collection of thermally marked voucher fry 08/26/2009
Q 176 Produce thermally marked chum salmon fed-fry for release into Duncan Creek 08/26/2009
R 162 Analysis of hatchery data 02/09/2007
S 70 Install and remove Grays River smolt trap 08/26/2009
T 157 Grays River Juvenile Monitoring 08/26/2009
U 162 Analyze data collected from Grays River smolt trap 02/09/2007
V 119 Manage and administer project 02/09/2007
W 132 Submit Progress Report - March 2009 to February 2010 02/09/2007
X 185 Periodic Status Reports for BPA 02/09/2007