Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 53200: 2010-072-00 EXP LEMHI RIVER RESTORATION PLANNING
Project Number:
Title:
Upper Salmon Basin Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
53200
Contract Title:
2010-072-00 EXP LEMHI RIVER RESTORATION PLANNING
Contract Continuation:
Previous: Next:
47379: 2008-602-00 EXP LEMHI RIVER RESTORATION PLANNING
  • 57487: 2010-072-00 EXP LEMHI RIVER RESTORATION PLANNING
Contract Status:
Closed
Contract Description:
The Lemhi River Restoration Planning contract provides the Idaho Office of Species Conservation (OSC) with funding to cover subcontracted expenses associated with on the ground implementation of salmon and steelhead recovery projects in the Lemhi watershed.  Habitat projects will be implemented for 2010-072-00 Lemhi River Restoration or other OSC-sponsored projects.  

In 2008, Idaho's Governor directed that all funding and contracting for Idaho's Accord projects was to go through the OSC.  OSC manages individual projects as needed to ensure adequate oversight and provide that all state agencies and their partners work in a coordinated fashion.  OSC will provide contract oversight.  Implementation work will be completed by a subcontractor, Lemhi Soil and Water Conservation District (District).  

Deliverables under the contract include project implementation support.  The subcontractor will also assist BPA's Environmental Compliance Lead to ensure that environmental compliance requirements are met during habitat project implementation.
Account Type(s):
Expense
Contract Start Date:
06/01/2011
Contract End Date:
05/31/2012
Current Contract Value:
$25,577
Expenditures:
$25,577

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Funding Package - Submit draft to COTR A: 119. Manage and Administer Lemhi River Restoration Planning contract 04/23/2012 04/30/2012
Provide project implementation support. B: 119. Manage and Administer Habitat Projects: Provide Project Implementation Support 05/31/2012 05/31/2012
Assist BPA's Environmental Compliance Lead to meet necessary environmental compliance requirements. C: 165. Environmental Compliance: Lemhi River Restoration 05/31/2012 05/31/2012
Participate in local planning meetings as needed D: 191. Participate in local planning meetings as needed 05/31/2012 05/31/2012
Attach Progress Report in Pisces F: 132. Submit Progress Report for the period (Jun 2011) to (May 2012) 05/01/2012 05/31/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage and Administer Lemhi River Restoration Planning contract 06/01/2011
B 119 Manage and Administer Habitat Projects: Provide Project Implementation Support 06/01/2011
C 165 Environmental Compliance: Lemhi River Restoration 06/01/2011
D 191 Participate in local planning meetings as needed 06/01/2011
E 185 Periodic Status Reports for BPA 06/01/2011
F 132 Submit Progress Report for the period (Jun 2011) to (May 2012) 06/01/2011