Contract 56662 REL 240: 2008-465-00 EXP MRS COHO HATCHERY O&M
Project Number:
Title:
Melvin R Sampson (MRS) Coho Hatchery Operation & Maintenance (O&M)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
56662 REL 240
Contract Title:
2008-465-00 EXP MRS COHO HATCHERY O&M
Contract Continuation:
Previous: Next:
56662 REL 199: 2008-465-00 EXP COHO PROD. FACILITY & MARKING
Contract Status:
Issued
Contract Description:
This contract covers the Confederated Tribe of the Yakima Nation's (YN)  work to participate in finalizing the NPCC Step process, resulting in a hatchery plan, design, cost estimate and environmental clearance for the Melvin R. Simpson Coho Facility to proceed to construction.  Key deliverables of this contract include: finalize draft HGMP, provide input to EC (permitting, ESA, NEPA), input to/review of final design, input to NPCC Step 2 and the decision to move to Step 3 of SOW/Budget for YN work to track construction progress and prepare to assume O&M of the hatchery facilities.
Account Type(s):
Expense
Contract Start Date:
05/01/2021
Contract End Date:
04/30/2022
Current Contract Value:
$728,484
Expenditures:
$603,722

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shirley Alvarado Yakama Confederated Tribes Yes Administrative Contact shirley_alvarado@yakama.com (509) 865-5121x6304
Joe Blodgett Yakama Confederated Tribes Yes Supervisor joe_blodgett@yakama.com (509) 865-6262x6372
D.J. Brownlee Yakama Confederated Tribes Yes Contract Manager Daniel_Brownlee@Yakama.com (509) 674-9391
Dave Fast Yakama Confederated Tribes Yes Interested Party fast@yakama.com (509) 966-5291
Mark Johnston Yakama Confederated Tribes Yes Technical Contact mark_johnston@yakama.com (509) 945-1133
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Amy Mai Bonneville Power Administration Yes COR aemai@bpa.gov (503) 230-7349
Jennifer McKenna Bonneville Power Administration No CO Assistant jmmckenna@bpa.gov (503) 314-8915
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Charles Strom Yakama Confederated Tribes Yes Technical Contact osprey@qwestoffice.net (509) 674-3701
Andrew Traylor Bonneville Power Administration Yes Backup COR awtraylor@bpa.gov (503) 230-3268
Adrienne Wilson Yakama Confederated Tribes Yes Interested Party Adrienne_Wilson@Yakama.com (509) 865-5121x6306
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration B: 119. Routine and specific administrative tasks 04/15/2022
Provide input on EC activities as needed C: 165. Assist BPA EC lead with NEPA/ESA 03/31/2022 03/31/2022
Support and coordination of Step 2 and 3 D: 196. Input to Step 3 approval 03/31/2022 03/31/2022
Refined M&E Plan that meets Step 2 requirements E: 174. Develop a refined monitoring and evaluation plan for NPCC 04/15/2022
Development of Hatchery Production F: 176. Development of hatchery production for MRS Coho facility 03/31/2022 03/31/2022
Development of MRS coho facility maintenance G: 61. Development of hatchery maintenance protocol for MRS coho facility 03/31/2022 03/31/2022
Attach Annual Operation Plan in Pisces H: 174. Produce an Annual Operation Plan 07/01/2021 06/30/2021
Maintain Fish Health for all Coho Life Stages J: 60. USFWS to Maintain Fish Health: M.R.S Coho Facility 03/31/2022 03/31/2022

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 196 Council Step Process
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 60 Maintain Fish Health
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 2 instances of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 Routine and specific administrative tasks
C 165 Assist BPA EC lead with NEPA/ESA
D 196 Input to Step 3 approval
E 174 Develop a refined monitoring and evaluation plan for NPCC 03/08/2021
F 176 Development of hatchery production for MRS Coho facility 03/08/2021
G 61 Development of hatchery maintenance protocol for MRS coho facility 03/08/2021
H 174 Produce an Annual Operation Plan 03/08/2021
I 132 Annual report not required until Year 2 of operations
J 60 USFWS to Maintain Fish Health: M.R.S Coho Facility 03/08/2021