Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 58324: 2002-059-00 EXP YANKEE FORK SIDE CHANNEL RESTORATION - SERIES 3
Project Number:
Title:
Yankee Fork Salmon River Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
58324
Contract Title:
2002-059-00 EXP YANKEE FORK SIDE CHANNEL RESTORATION - SERIES 3
Contract Continuation:
Previous: Next:
n/a
Contract Status:
History
Contract Description:
This contract covers efforts by the Idaho Office of Species Conservation (OSC) to implement the first year of Yankee Fork Pond Series 3 (PS3) Side Channel activity.  The contract covers administration, construction management, environmental compliance, outreach, and habitat improvement activity in PS3.  

The Shoshone-Bannock Tribes’ (Tribes) have been working on the Yankee Fork Salmon River since 1984 under BPA Project # 83-359, Salmon River Habitat Enhancement.  The Tribes work on the Yankee Fork continued in 2005 under BPA Project #2002-059-00, Yankee Fork Salmon River Dredge Tailings Restoration.

In May of 2008 the Tribes submitted the Yankee Fork Floodplain Restoration Implementation Plan for 2008 - 2018 to the Northwest Power and Conservation Council (Council).  This plan was reviewed by the ISRP and comments were provided in Review Memorandum ISRP 2008-11 (2) with a Does Not Meet Scientific Criteria recommendation.  The Council also recommended that Project #2002-059-00 be subject to the Three-Step Review Process.

The 2008 Columbia Basin Fish Accord Agreement with the Tribes (Accord) included the Yankee Fork Floodplain Restoration Project # 2002-059-00 in Attachment A and the Project Narratives Appendix B.  In addition, the 2009 Columbia River Basin Fish and Wildlife Program recognized the Accord commitments for BPA to fund multi-year implementation plans.  The Council also agreed to work with BPA to estimate budgets and secure adequate funding for multi-year implementation plans.

On February 14, 2012, the Tribes submitted a response to the ISRP 2008-11 Memorandum and requested review of a revised proposal and supporting appendices for the Tribes Project # 2002-059-00. The revised proposal included two habitat improvement activities in Pond Series 2 and Pond Series 3.  These two activities were identified in the Accord multi-year implementation plan.   The February 2012 submittal was reviewed by the ISRP and comments were provided in Review Memorandum ISRP 2012-5 with a Meets Scientific Review Criteria (Qualified) recommendation.

The current proposal in response to ISRP 2012-5 Memorandum is for habitat improvement activity in Pond Series 3 identified in the Accord multi-year implementation plan.  This contract will accomplish the first portion of the project to be funded through the Accord.  Future habitat improvement activities are being developed into a programmatic multi-year implementation plan.  A separate programmatic proposal with supporting documentation will be prepared and submitted to the Council for ISRP review.

Tuan
Account Type(s):
Expense
Contract Start Date:
08/15/2012
Contract End Date:
09/30/2013
Current Contract Value:
$1,318,468
Expenditures:
$1,318,468

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Sue Christensen Trout Unlimited (TU) No Interested Party schristensen@tu.org (208) 552-0891x717
Chad Colter Shoshone-Bannock Tribes No Interested Party ccolter@sbtribes.com (208) 239-4553
Joe Deherrera Bonneville Power Administration Yes COR jldeherrera@bpa.gov (503) 230-3442
Paul Drury US Bureau of Reclamation (BOR) Yes Interested Party pdrury@usbr.gov (208) 378-5076
Israel Duran Bonneville Power Administration No Env. Compliance Lead induran@bpa.gov (503) 230-3967
Mike Edmondson Idaho Governor's Office of Species Conservation Yes Supervisor mike.edmondson@osc.idaho.gov (208) 334-2189
Evelyn Galloway Shoshone-Bannock Tribes Yes Technical Contact egalloway@sbtribes.com (208) 239-4570
Abbie Gongloff Idaho Governor's Office of Species Conservation Yes Technical Contact abbie.gongloff@osc.idaho.gov (208) 756-6322
Jim Gregory Trout Unlimited (TU) No Interested Party gregory_jim@yahoo.com (208) 390-5306
Amy Hines Idaho Governor's Office of Species Conservation Yes Contract Manager amy.hines@osc.idaho.gov (208) 332-1557
Hans Koenig Idaho Governor's Office of Species Conservation No Technical Contact hans.koenig@osc.idaho.gov (208) 756-6322
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Jerry Myers Trout Unlimited (TU) No Interested Party jmyers@tu.org (208) 394-2111
Kim Trotter Trout Unlimited (TU) No Interested Party ktrotter@tu.org (208) 552-0891x712
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit draft to COTR A: 119. Manage and Administer Project 06/03/2013
Complete all required EC and obtain site specific permits prior to implementation of project actions B: 165. Environmental Compliance 06/07/2013 06/07/2013
Construction Management Complete C: 100. Construction management for Pond Series 3 09/30/2013 09/30/2013
As built record drawings submitted to BPA. D: 181. Create, Restore and/or Enhance Wetlands at Pond Series 3 08/14/2013 06/10/2013
As built record drawings submitted to BPA. E: 180. Enhance floodplain/remove, modify breach dike at Pond Series 3 08/14/2013 06/10/2013
As built record drawings submitted to BPA. F: 52. Remove mine tailings at Pond Series 3 08/14/2013 06/10/2013
As built record drawings submitted to BPA. G: 30. Create channel at Pond Series 3 08/14/2013 06/10/2013
As built record drawings submitted to BPA. H: 29. Increase complexity at Pond Series 3 09/30/2013 06/10/2013
As built record drawings submitted to BPA. I: 85. Remove barriers at Pond Series 3 08/14/2013 06/10/2013
Plant vegetation at PS3: aquatic, wetland, riparian, and upland species J: 47. Plant vegetation at Pond Series 3 09/30/2013 06/07/2013
As built record drawings submitted. K: 55. Construction Site Best Management Practices 08/14/2013 06/10/2013
Attach Progress Report in Pisces M: 132. Submit Progress Report for the period August 2012 thru September 2013 09/20/2013
Utilize temporary sprinkler system to conduct 2013 field season revegetation irrigation N: 150. Install sprinkler system for 2013 field season revegetation irrigation 09/30/2013 09/13/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 52 Remove Mine Tailings
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 150 Install Sprinkler
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage and Administer Project 03/15/2012
B 165 Environmental Compliance 03/15/2012
C 100 Construction management for Pond Series 3 03/15/2012
D 181 Create, Restore and/or Enhance Wetlands at Pond Series 3 08/17/2015
E 180 Enhance floodplain/remove, modify breach dike at Pond Series 3 08/27/2012
F 52 Remove mine tailings at Pond Series 3 08/27/2012
G 30 Create channel at Pond Series 3 08/27/2012
H 29 Increase complexity at Pond Series 3 08/27/2012
I 85 Remove barriers at Pond Series 3 05/29/2017
J 47 Plant vegetation at Pond Series 3 08/27/2012
K 55 Construction Site Best Management Practices 08/27/2012
L 185 Periodic Status Reports for BPA 03/15/2012
M 132 Submit Progress Report for the period August 2012 thru September 2013 03/15/2012
N 150 Install sprinkler system for 2013 field season revegetation irrigation 08/29/2012