| Receipt of environmental compliance clearance from BPA. |
A: 165. Complete and/or initiate Environmental Permitting for Project Activities |
|
04/30/2015 |
04/30/2015 |
| Receipt of environmental compliance clearance from BPA. |
B: 165. Rock Creek Fish Habitat Enhancement Project EC requirements |
|
04/30/2015 |
04/30/2015 |
| All administrative tasks fulfilled with timely quality products |
C: 119. Phase 2 Rock Creek Project Administration |
|
11/14/2014 |
11/14/2014 |
| Install large wood complexes and habitat boulders to increase habitat complexity and diversity |
D: 29. Install Large Wood Complexes and habitat boulders along Rock Creek, Little Rock, and Sheep Creek |
|
04/30/2015 |
04/30/2015 |
| Remove Floodplain Levee |
E: 180. Remove Floodplain Levees on Rock Creek |
|
04/30/2015 |
04/30/2015 |
| Re-activate historic stream channel |
F: 30. Re-activate Graves Creek and Rock Creek Historic Channel Segments |
|
04/30/2015 |
04/30/2015 |
| Construct Riparian Conservation Easement Fences |
G: 40. Install Rock Creek Riparian Easement Fences |
|
04/30/2015 |
04/30/2015 |
| Construct Riparian Conservation Easement Fences |
H: 40. Install Catherine Creek (CC44) Riparian Easement Fences |
|
04/30/2015 |
04/30/2015 |
| Plant native trees, shrubs, and grass on Rock Creek Project |
I: 47. Plant native trees, shrubs, and grasses along Rock, Sheep, and Little Rock Creeks |
|
04/30/2015 |
04/30/2015 |
| Plant native trees, shrubs, and grass |
J: 47. Plant native trees, shrubs, and grasses along Catherine Creek |
|
11/28/2014 |
12/19/2014 |
| Install Sprinklers to Improve Irrigation Effie |
K: 150. Cost-Share Catherine Creek (CC44) Irrigation Efficiency Plan Install Sprinklers |
|
04/30/2015 |
04/30/2015 |
| Conduct Fish Salvage Operations |
L: 28. Conduct Fish Salvage operations on the Phase 2 CC44 and Rock Creek Projects |
|
10/15/2014 |
08/28/2014 |
| Replace undersized culvert on Ladd Creek and Highway 203 |
M: 184. Ladd Creek Highway 203 Culvert Replacement |
|
10/15/2014 |
10/15/2014 |
| Conduct project maintenance on McCoy, Dark Canyon, Meadow, Willow, Rock, Catherine & Wallowa Project |
N: 186. Maintain instream structures, fences, and off-channel water developments |
|
04/30/2015 |
04/30/2015 |
| Assist the Oregon Ag Foundation with planting & fence construction subcontract administration |
O: 119. Assist with managing & admin CREP fencing & planting plans on Willow Creek Project |
|
04/30/2015 |
04/30/2015 |
| Maintain vegetation and control Weeds on the Willow Creek Fish Habitat Enhancement Project |
P: 198. Maintain Vegetation and Control Weeds on the Willow Creek Project |
|
04/30/2015 |
04/30/2015 |
| Successfully Administer project |
Q: 119. Manage and Administer CTUIR GR Subbasin Restoration Project |
|
04/30/2015 |
04/30/2015 |
| Complete outreach & education activities |
R: 99. Public Outreach and Education |
|
04/30/2015 |
04/30/2015 |
| Conduct ongoing project development and coordination activities |
S: 114. CTUIR Grande Ronde Subbasin Restoration Coordination |
|
04/30/2015 |
04/30/2015 |
| BiOp Fish Habitat Project Opportunity Development and Review |
T: 114. Solicit, review and select BiOp expense & capital projects |
|
04/30/2015 |
04/30/2015 |
| Develop project design plan sets. |
U: 174. Develop project designs and produce plans |
|
04/30/2015 |
04/30/2015 |
| Upload 2014 Annual Report |
V: 132. Prepare FY2014 Annual Report - May 2014 - April 2015 |
|
04/30/2015 |
04/30/2015 |