Close Message
CBFish website will be offline for approximately one hour starting at 5 PM today for maintenance. Thank you for your patience.
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 69193: 2008-527-00 EXP ZONE 6 FISHERIES CRITFC ACCORD PROJECT - FY2015
Project Number:
Title:
Zone 6 Fishery (Prosser Hatchery Upgrades)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mainstem - 100.00%
Contract Number:
69193
Contract Title:
2008-527-00 EXP ZONE 6 FISHERIES CRITFC ACCORD PROJECT - FY2015
Contract Continuation:
Previous: Next:
65421: 2008-527-00 EXP ZONE 6 FISHERIES CRITFC ACCORD PROJECT - FY2014
  • 72827: 2008-527-00 EXP ZONE 6 FISHERIES CRITFC ACCORD PROJECT
Contract Status:
Closed
Contract Description:
This project is a Zone 6 fisheries CRITFC Accord project which was given consideration for its relevance to the John Day Mitigation Reprogramming Plan that is being developed by the U.S. v. Oregon parties and the U.S. Army Corps of Engineers. CRITFC will develop a draft and final project plan; a feasibility study to further evaluate the project preferred alternative; a Statement of Work for FY16; an annual report; and Pisces quarterly status reports. CRITFC will coordinate with BPA and the Council on the appropriate level of scientific review necessary to implement a production or supplementation plan including necessary environmental clearances.

The Treaty Tribal fishery benefits directly from John Day Mitigation production, as the majority of returning adults must transit the entire Zone 6 fishery on their way back to release sites at Priest Rapids, Ringold Springs, and other JDM program release sites.  Maintaining the John Day Mitigation program fish production for the benefit of the Treaty Tribal fishery is a high priority for all of the Treaty tribes.  The CRITFC Commission has requested action on this Accords project to contribute to benefits of the Treaty Tribal fishery in Zone 6.

A Request for Quotations (RFQ) was developed in December 2011 to provide technical and planning support to the tribes through assistance provided by an engineering firm.  Because several concurrent projects had been developing independently, there was a need for a consulting engineering firm to assist CRITFC in disseminating information from these concurrent feasibility studies for the Zone 6 fisheries CRITFC Accords project.  Shortly after the RFQ submittal, a request to pull the RFQ from the FedBizOps website was submitted by staff of the CTUIR, with approval from the CTUIR Board of trustees and Fish & Wildlife Commission.  The reason provided for pulling the RFQ was based on historical interpretations of "ceded lands" between the CTUIR and the YN.  Given that the John Day Reprogramming (JDR) project proposal Option One included plans for building a fish propagation/release facility in the lower Yakima River basin, longstanding concerns regarding tribal jurisdiction over ceded lands provided the justification for pulling the RFQ until all four tribes had an opportunity to consult on the matter and develop an appropriate course of action.  The process for consultation and discussion was developed at the Policy level amongst tribal representatives.  Soon after the RFQ was pulled the CTUIR submitted an informal proposal to include a third JDR project option (Option Three).  This proposal called for a feasibility study to address alternative species propagation, specifically lamprey and sturgeon.  The basis for the proposal was founded on the principle that the original John day Mitigation program had not considered alternative species to fall Chinook.  BPA was engaged in these discussions and provided verbal approval for the project at the Policy level.  At the march 2012 CRITFC Commission meeting BPA's verbal approval was discussed, but the proposal had not yet been vetted through the Commission.  By the July 25th CRITFC Commission meeting the CTUIR alternative species proposal was included as an action item for CRITFC Commission approval.  The action item was deferred to the August Commission meeting, at which time the Commission called for a special Commission meeting on September 7, 2012 to address JDM and JDR issues.  Although in-depth discussions took place, no action was taken at that time.  However, the CTUIR committed to hosting meetings with the four tribal Chairmen to discuss the JDM/JDR issues in order to provide approval for the JDR project to move forward.  The issue of ceded lands formed the basis for primary discussions.  Again, the focus was on the siting of a future JDR fish facility in the lower Yakima River basin near the Horn Rapids area of the Columbia River, as well as discussions pertaining to future operational responsibilities for the proposed facilities.  The land areas referred to contain portions of the CTUIR's ceded lands, as well as YN lands, and discussions focused on historical perspectives and interpretations of these lands and jurisdiction thereof.  The four tribal Chairs met informally during the 2012 ATNI conference September 24-27 to further discuss the ceded lands issues and to come to a resolution on the matter.  These discussions resulted in the scheduling of another meeting amongst the four tribal Chairs at the CTUIR offices in Pendleton, OR during mid-October, 2012.  At this meeting the Chairs agreed that the project should not be put in jeopardy, and that it should move forward while the Tribes resolve who should operate the future proposed facilities.  Further, the Chairs and the CTUIR Board of Trustees concluded that "Matters between the four Tribes regarding sovereignty or ceded lands areas are not properly within the scope of CRITFC's function."  A letter filed on October 26, 2012 and signed by Les Minthorn, Chair of the CTUIR Board of Trustees, outlines the aforementioned conclusions and provides clearance for the JDR project to move forward.  

The JDR project was once again scheduled as an action item at the December CRITFC Commission meeting held on December 19-20, 2012.  The Commission voted to proceed with the JDR options as laid out in the October 26, 2012 letter from CTUIR Board of Trustees Chair Les Minthorn.  The options are as follows:

1)  Build an adult handling/acclimation site in the lower Yakima River. The Yakama Nation (YN) completed a feasibility study for fall Chinook lower river (Yakima R.) acclimation and adult holding under their Yakima River Master Plan.  This study was conducted by McMillen Engineering, LLC, and it compares acclimation and adult holding strategies for fall Chinook in the lower Yakima River basin.  Results from this study will provide input for the current Accords project as well, given that reprogramming fall Chinook in the lower Yakima River is a shared objective of both the YN Master Plan and the Accords project.  The current McMillen feasibility study developed concept designs to 15%.  

2)  Implement the first phase of the Confederated Tribes of the Warm Springs Reservation of Oregon (CTWSRO) proposal addressing implementation of a summer run component of the Deschutes fall Chinook population. The CTWSRO needs to further define what will be included in a feasibility study to meet the objective. The issue is highly politicized and potentially contentious. The planning phase was extended by five months to allow time for the CTWSRO proposal to develop. Depending on the level of development it may be included in this contract cycle or occur in a later contract.  

3)  At the beginning of 2012, CRITFC also received a request from the The Confederated Tribes of the Umatilla Indian Reservation (CTUIR) to develop a feasibility study assessing potential locations for sturgeon and lamprey propagation facilities and to provide designs for those facilities. The alternative species issue has not been vetted through the CRITFC and will be evaluated during the extended planning phase. It is included under the coordination and planning work element, and will consist of meetings.  The CTUIR proposal would mean adding additional project objectives to the draft Accords project plan to accommodate all interested tribal parties in a project carrying a capital budget of $4M. The tribes are currently consulting with each other at the policy level to determine next steps in the Zone 6 fisheries CRITFC Accords project planning process.

As of January 2013 the CTUIR has requested that the feasibility study for their proposal (JDR Option 3) be delayed for 1-2 years.  A copy of the email request is provided in the attachment section of this SOW. Therefore, the proposed feasibility study in support of JDR Option 3 will not be addressed during the course of this contract period.

During this time the USACE has been implementing its JDM Ringold Project plan.  The Final Alternatives Report was distributed on October 20, 2012 outlining the project's development to date.  The next phase will be marked by submission of the 90% DDR, which will encompass the final project design and specifications.  The Corps intends to submit final data for inclusion into the DDR by the end of March, 2013.  Monthly PAC/Corps meetings have been held, and progress has been characterized throughout the meetings schedule.  Although the Corps' engineers and consultants have been challenged in locating suitable broodstock-quality water resources at the Ringold site, the co-managers have provided significant input on the issue, and a workable broodstock management plan is taking shape.  The Corps has committed to build-outs at the Ringold site and at the I-182 site.  Thus, early concerns about the need for coordinated timelines between the Corps Ringold project and the CRITFC Accords have come to fruition.  

The nature and extent of the JDR project capital budget plan will necessarily depend on the nature and extent of planned facilities at the Ringold site. This being the case, the Ringold project 90% DDR submittal in March, 2013 will contain most of the final design elements and water resources should be sufficiently delineated by then.  This will enable PAC to finalize its draft production plans for the new facility.  By the April 2013 time frame the tribes will have Ringold data in hand and will be in a much better position to determine the size and scope of the JDR project.  Conversely, if federal funding constraints negatively impact the Ringold project and the Corps is not able to maintain the project schedule, then the tribes may want to move forward with two of the three JDR Plan options.  

JDR Option One  is currently being discussed at the Tribal Policy level, with respect to future operation and maintenance  of a proposed fish facility in the lower Yakima River.  
JDR Option Two  is currently being discussed amongst CTWSRO Policy members and CRITFC and tribal fishery staffs await results of those discussions for further project planning and implementation.
JDR Option Three is also currently being discussed at the CTUIR Policy level and staffs await guidance prior to commencing with a feasibility study.

CCR-35556  to add Work Elements J and K.

In response to warming water temperatures and chronic production shortfalls at the sole production facility in the Warm Springs basin the Confederated Tribes of Warm Springs (CTWS) will use project funds to assess the feasibility of rearing a portion or all of the 1.2 m juvenile spring Chinook salmon currently reared at Warm Springs National Fish Hatchery (WSNFH) to location in the upper watershed that has optimal water temperatures for salmon aquaculture.  Concurrently, in cooperation with the U.S. Fish and Wildlife Service (USFWS), the CTWS will commission a study to determine the feasibility of converting the existing raceway systems at WSNFH to utilize partial water re-use system (PRAS) technology with chillers. The results of the two studies will provide the CTWS with options that will enable salmon rearing goals to be realized in the Warm Springs drainage in a warming climate.  Successful implementation of preferred option will create additional capacity at WSNFH to implement a future fall/ summer Chinook salmon sub-yearling re-introduction program.

The CTWS will assess the feasibility of siting a spring Chinook juvenile rearing facility in the upper Warm Springs watershed at Schoolie Spring (RM 37). The facility would be used to relocate all or a portion of juvenile rearing from WSNFH during May through September to remedy the WSNFH’s limiting factors of extremely poor summer water quality.  Approximately 1,000 gpm flow from Schoolie Spring at a year around temperatures of 47oF.   The potential to develop ground water is high and will be evaluated as part of this project.  An engineering firm with experience in salmonid aquaculture facility design will conduct a site assessment to evaluate water availability, site development potential and logistics  to rear all or a portion of the 1.2m basin spring Chinook program. A report identifying production options with site sketchs and preliminary cost estimates will be made available to the CTWS during the fall 2016.

Concurrently, in cooperation with the USFWS, the CTWS will commission a study to determine the feasibility of converting the existing raceway systems at WSNFH to dual-drain circular tanks supplied by PRAS with chilling to within Integrated Hatchery Operations Team (IHOT) parameters.  WNSFH utilizes a single-pass water delivery system that cannot effectively or efficiently reduce hatchery water temperatures when necessary. IHOT recommendations for spring Chinook water temperatures are <55 F. Lowering water temperatures and installing circular tank rearing containers should allow a portion of 1.2m juveniles to be reared on station in combination with the development of Schoolie Springs site described above.  Depending on the capacity of the Schoolie site to accommodate the 1.2m spring Chinook juveniles a PRAS for juvenile rearing should provide additional summertime rearing capacity to support a sub-yearling Chinook program.  An engineering firm specializing PRAS will conduct the study and issue a finding report, including capacity and preliminary cost estimates, to the CTWS in the fall, 2016.

This project will provide site and feasibility assessments of Schoolie Springs and WSNFH respectively with options for improving summer rearing of Chinook salmon production in the Warm Springs Basin in a warming climate. The results will enable the CTWS to select a preferred option for advancement to preliminary design and Tribal environmental permitting.
Account Type(s):
Expense
Contract Start Date:
06/01/2015
Contract End Date:
09/30/2016
Current Contract Value:
$78,048
Expenditures:
$78,048

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Hold and attend meetings with regional tribal fishery staffs to achieve tribal consensus. A: 189. Coordinate with tribal staff to develop consensus to select JDR Options 05/31/2016 05/31/2016
Retain an A&E firm to develop a feasibility study for the JDR Option One preferred alternative. B: 114. Retain an A&E firm in support of JDR Option One 05/31/2016
Conduct a feasibility study in coordination with the contracted A&E firm in support of JDR Opt. One C: 122. A&E firm will initiate a feasibility study for JDR Option One preferred alternative 05/31/2016
Retain an A&E firm in support of JDR Option Three F: 114. Retain an A&E firm in support of JDR Option Three 05/31/2016
All administrative tasks fulfilled with timely quality products H: 119. Development of FY 2016 project contract 09/30/2016 05/31/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 114 Identify and Select Projects
Chinook (O. tshawytscha) - Deschutes River Summer/Fall ESU
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 175 Produce Design
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 114 Identify and Select Projects
Sturgeon, White (A. transmontanus) - Lower Columbia River
  • 1 instance of WE 114 Identify and Select Projects

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 189 Coordinate with tribal staff to develop consensus to select JDR Options 06/01/2015
B 114 Retain an A&E firm in support of JDR Option One 06/01/2015
C 122 A&E firm will initiate a feasibility study for JDR Option One preferred alternative 06/01/2015
D 114 Retain and A&E Firm in support of JDR Option Two 06/01/2015
E 122 A&E firm will initiate a feasibility study for JDR Option Two 06/01/2015
F 114 Retain an A&E firm in support of JDR Option Three 06/01/2015
G 132 Submit Summary Progress Report for the period 6/1/2012) to (5/31/2015) 06/01/2015
H 119 Development of FY 2016 project contract 06/01/2015
I 185 Periodic Status Reports for BPA 06/01/2015
J 175 CTWS - Schoolie Springs Juvenile Salmon Summer Rearing Assessment
K 175 CTWS - Assess Feasibility of PRAS for juvenile rearing at WSNFH 06/01/2015
L 165 Coordinate with BPA EC Lead on Schoolie Springs and WSNFH Assessments 06/01/2015