Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 72827: 2008-527-00 EXP ZONE 6 FISHERIES CRITFC ACCORD PROJECT
Project Number:
Title:
Zone 6 Fishery (Prosser Hatchery Upgrades)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mainstem - 100.00%
Contract Number:
72827
Contract Title:
2008-527-00 EXP ZONE 6 FISHERIES CRITFC ACCORD PROJECT
Contract Continuation:
Previous: Next:
69193: 2008-527-00 EXP ZONE 6 FISHERIES CRITFC ACCORD PROJECT - FY2015
  • 76699: 2008-527-00 EXP ZONE 6 FISHERIES CRITFC ACCORD PROJECT
Contract Status:
Closed
Contract Description:
The nature and extent of the JDR project capital budget plan will necessarily depend on the nature and extent of planned facilities at the Ringold site. Federal funding constraints seem to negatively impact the Ringold project and the USACE is so far unable to maintain the project schedule. Because of the numerous delays, the tribes are considering how best to move forward with two of the three JDR Plan options.  

JDR Option One: currently being discussed at the Tribal Policy level, with respect to future operation and maintenance of a proposed fish facility in the lower Yakima River.
  
JDR Option Two: currently being pursued for FY15 as a subcontract of this project until the end of September 2016 upon which the CTWSRO will contract directly with BPA for continuation in October 2016. Briefly, the CTWSRO will use funds to i.) assess the feasibility of rearing a portion or all of the 1.2 m juvenile spring Chinook salmon currently reared at Warm Springs National Fish Hatchery (WSNFH) to Schoolie Springs in the upper Warm Springs watershed, and ii.) commission a study to determine the feasibility of converting the existing raceway systems at WSNFH to utilize partial water re-use system technology with chillers. This project will provide site and feasibility assessments of Schoolie Springs and WSNFH respectively with options for improving summer rearing of Chinook salmon production in the Warm Springs Basin in a warming climate.

JDR Option Three: A feasibility study for future production of alternative species (i.e., lamprey, white sturgeon, freshwater mussels) by CTUIR will be pursued via a direct contract of $150K with BPA in October 2016.

A Tribal Fish Health Master Plan will be developed using $30K from FY16 funds.

CRITFC will develop a draft and final project plan; a feasibility study to further evaluate the project preferred alternative; a Statement of Work for FY17; an annual report; and Pisces quarterly status reports. CRITFC will coordinate with BPA and the Council on the appropriate level of scientific review necessary to implement a production or supplementation plan including necessary environmental clearances.
Account Type(s):
Expense
Contract Start Date:
06/01/2016
Contract End Date:
05/31/2017
Current Contract Value:
$190,819
Expenditures:
$190,819

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
EC Documents in support of Tribal Fish Health Master Plan A: 165. Produce documentation in support of Tribal Fish Health Master Plan 05/31/2017 09/30/2016
Hold and attend meetings with regional tribal fishery staffs to achieve tribal consensus. B: 189. Coordinate with tribal staff to develop consensus to select JDR Options 05/31/2017 05/26/2017
Retain an A&E firm to develop a feasibility study for the JDR Option One preferred alternative C: 114. Retain an A&E firm in support of JDR Option One 04/15/2017
Conduct a feasibility study in coordination with the contracted A&E firm in support of JDR Opt D: 122. A&E firm will initiate a feasibility study for JDR Option One preferred alternative 05/31/2017
Completed Annual Report E: 132. Submit Summary Progress Report for the period 6/1/2012) to (5/31/2016) 12/30/2016 05/31/2016
Development of an Tribal Fish Health Master Plan F: 174. Development of an Tribal Fish Health Master Plan 05/31/2017
All administrative tasks fulfilled with timely quality products G: 119. Development of FY 2017 project contract 05/31/2017 05/31/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 174 Produce Plan
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 114 Identify and Select Projects
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 174 Produce Plan
Sockeye (Oncorhynchus nerka) - All Populations
  • 1 instance of WE 174 Produce Plan
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 174 Produce Plan
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 174 Produce Plan
Sturgeon, White (A. transmontanus) - Lower Columbia River
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce documentation in support of Tribal Fish Health Master Plan 06/01/2016
B 189 Coordinate with tribal staff to develop consensus to select JDR Options 06/01/2016
C 114 Retain an A&E firm in support of JDR Option One 06/01/2016
D 122 A&E firm will initiate a feasibility study for JDR Option One preferred alternative 06/01/2016
E 132 Submit Summary Progress Report for the period 6/1/2012) to (5/31/2016) 06/01/2016
F 174 Development of an Tribal Fish Health Master Plan 06/01/2016
G 119 Development of FY 2017 project contract 06/01/2016
H 185 Periodic Status Reports for BPA 06/01/2016