Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 96660: 2007-398-00 EXP YAKIMA BASIN TRIBUTARY PASSAGE & FLOW
Project Number:
Title:
Yakima Basinwide Tributary Passage and Flow
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
96660
Contract Title:
2007-398-00 EXP YAKIMA BASIN TRIBUTARY PASSAGE & FLOW
Contract Continuation:
Previous: Next:
94307: 2007-398-00 EXP FY24 YTAHP
  • CR-380923: 2007-398-00 EXP YAKIMA BASINWIDE TRIBUTARY PASSAGE AND FLOW
Contract Status:
Issued
Contract Description:
Under CR-374074 the following work and services will be accomplished by the YTAHP Team:

BPA funding for FY 2025 will support the implementation of 7 fish passage and habitat restoration projects, ongoing riparian vegetation and site stewardship on 6 projects and provide significant work toward project development, permits, design and/or funding for an additional 9 projects. The projects completed in FY 2025 will cumulatively result in screening 28.5 cfs of diverted surface water, restore fish passage to 3.03 miles of tributary habitat and provide .28 of a mile of riparian vegetation maintenance on eight streams in the Yakima Basin.  

Project Background:

The Yakima Tributary Access & Habitat Program was formed in 2001 in response to the listing of Middle Columbia River steelhead and bull trout under the Endangered Species Act.  The objectives of the program are to screen surface water diversions, restore fish passage and enhance salmonid habitat.  The focus of the program is on Yakima River tributaries that historically supported salmonids and on riparian areas where fish passage is restored.  The YTAHP fills a unique and important role in salmonid recovery by facilitating a voluntary program in which private landowners can come into compliance with fish screening and passage laws.

In general, projects on tributaries are prioritized sequentially, in accordance with YTAHP's Stategic Plan, moving upstream from the confluence with the Yakima River; as projects are completed, the regained habitat is connected to the mainstem and available to anadromous fish. YTAHP has concentrated on tributaries upstream of Union Gap where salmonids are known to have occurred historically.  Streams have been surveyed for fish passage barriers, analyzed for screening of diversions, and assessed for habitat quality using WDFW’s Salmonid Screening, Habitat Enhancement, and Restoration (SSHEAR) protocol.  At times projects may appear out of sequence but do fit in the context of multi-year planning.  YTAHP uses BPA funds to leverage cost share funds from a variety of other sources, thus expanding the funding pie.  For passage projects, YTAHP works with local landowners and irrigation water delivery entities who voluntarily participate.  BPA funds are used only for planning, design, permitting and implementation.  There are no changes to facility ownership status or operation and maintenance responsibilities resulting from YTAHP work.  BPA takes on no responsibilities for ownership or O&M.

The Current YTAHP Roles and Responsibilities are as follows:
Brian Miller- Washington Resource & Conservation (RC&D) Council YTAHP Program Manager
Mike Tobin- North Yakima Conservation District (NYCD) District Manager
Justin Bader- NYCD Yakima Tributary Access and Habitat Program Coordinator
Anna Lael- Kittitas Conservation County District (KCCD) District Manager
Mark Crowley- KCCD Conservation Planner for YTAHP projects
Emma Olney- WDFW YTAHP Permitting, Environment Compliance & Watershed Project Coordination  
Account Type(s):
Expense
Contract Start Date:
04/01/2025
Contract End Date:
03/31/2026
Current Contract Value:
$836,741
Expenditures:
$423,499

* Expenditures data includes accruals and are based on data through 31-Oct-2025.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Accrual Category:
Planning & Design
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration B: 119. RC&D management of the YTAHP program & subcontractor administrative work 03/31/2026
Watershed coordination activities have been completed. C: 191. Watershed Coordination 03/31/2026
Completed Progress (Annual) Report D: 132. Submit annual report for 04/01/2024 - 03/31/2025 (FY 2024) 09/01/2025 08/26/2025
Technical input into project development E: 122. Technical Review 03/31/2026
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish F: 114. Identify and Select projects 10/31/2025
Produce Environmental Compliance Documentation G: 165. Produce Environmental Compliance Documentation - Permitting 03/31/2026
Vegetation maintenance activities completed H: 198. Naches River RM 10.0- Edgar Riparian Protection and Enhancement- Phase 1- Maintain Vegetation (Continued from WE H on the FY 2024 Contract 94307) 03/31/2026
Vegetation maintenance activities completed I: 198. Naches River RM 10.0 - Edgar Riparian Protection and Enhancement- Phase 2- Maintain Vegetation (Continued from WE I on Contract 94307) 03/31/2026
Fish screen is installed. J: 208. Wenas Creek RM 11.0- Calver/Turner- Fish Screen (New) 01/01/2026
Fish screen is installed K: 208. Wenas Creek RM 8.5- Bassett- Fish Screen (New) 01/01/2026
Upload final design set L: 175. Wenas Creek RM 12 - Fish Passage and Screening Project- Produce Design (Continued from WE Q on Contract 94307) 03/31/2026
Upload final design set M: 175. Wenas Creek RM 11 - Haas Fish Screening and Passage- Produce Design (Continued from WE R on Contract 94307) 03/31/2026
Final Designs and Specifications N: 175. Coleman Creek RM 4.6 - Raap (continued from WE S in 2024 Contract 94307) 03/31/2026
Plans and Specifications Complete O: 175. Naneum Creek RM 4.7 - Ellensburg Water Company Intersection (continued from WE U in 2024 Contract 94307) 12/01/2025
60% Design Completed P: 175. Naneum Creek RM 3.75 - McCullough Rd Fish Passage (continued from WE W in 2024 Contract 94307) 03/31/2026
Final Designs Completed For Bid Package Preparation Q: 175. Cooke 4.25 - Fish Screen and Passage (continued from WE V in 2024 Contract 94307) 01/05/2026
Complete 30% Designs for Fish Passage & Screening R: 175. Cooke 3.85 - Fish Screen and Passage (continued from WE V in 2024 Contract 94307) 03/31/2026
Complete 30% Designs S: 175. Cooke 8.2 - Fish Screen (new) 03/31/2026
Final plans and specifications completed T: 175. Whiskey Creek Barriers RM 1.5-1.7 (connected to WE AL in 2024 Contract 94307) 01/05/2026
Vegetation maintenance activities completed U: 198. Parke Creek 1.01 Vegetation Maintenance (connected to WE X in 2023 contract 92053) 03/31/2026
Vegetation maintenance activities completed V: 198. Coleman 2.0 Vegetation Maintenance (connected to WE AA in 2024 Contract 94307) 03/31/2026
Vegetation maintenance activities completed W: 198. Naneum 2.9 Vegetation Maintenance (connected to WE AB in 2024 Contract 94307) 03/31/2026
Vegetation maintenance activities completed X: 198. Coleman Creek 4.4 (Schomer) Vegetation Maintenance (connected to WE AC in 2024 Contract 94307) 03/31/2026
Instream Work Complete Y: 85. Naneum 3.2 Fish Passage (continued from WE AE in 2024 Contract 94307) 03/31/2026
Fish passage restored and fish screen installed Z: 208. Cooke Creek 4.25 Fish Screen and Passage (connected to WE AG in 2024 Contract 94307) 03/31/2026
Fish screen and fish passage structures installed AA: 208. Cascade at Coleman Creek (RM 5.4) Fish Passage and Screening (connected to WE AH in 2024 Contract 94307) 03/31/2026
Fish passage restored AB: 208. Naneum Creek RM 4.7 - Ellensburg Water Company Intersection (connected to WE AI in 2024 Contract 94307) 03/31/2026
Fish screen and fish passage construction completed AC: 208. Whiskey Creek Barriers RM 1.5-1.7 (connected to WE AL in contract 92053) 03/31/2026

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 6 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 9 instances of WE 175 Produce Design
  • 6 instances of WE 208 Irrigation Infrastructure Construction or Replacement

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 RC&D management of the YTAHP program & subcontractor administrative work
C 191 Watershed Coordination
D 132 Submit annual report for 04/01/2024 - 03/31/2025 (FY 2024)
E 122 Technical Review
F 114 Identify and Select projects
G 165 Produce Environmental Compliance Documentation - Permitting
H 198 Naches River RM 10.0- Edgar Riparian Protection and Enhancement- Phase 1- Maintain Vegetation (Continued from WE H on the FY 2024 Contract 94307) 04/01/2025
I 198 Naches River RM 10.0 - Edgar Riparian Protection and Enhancement- Phase 2- Maintain Vegetation (Continued from WE I on Contract 94307) 04/01/2025
J 208 Wenas Creek RM 11.0- Calver/Turner- Fish Screen (New)
K 208 Wenas Creek RM 8.5- Bassett- Fish Screen (New) 09/18/2025
L 175 Wenas Creek RM 12 - Fish Passage and Screening Project- Produce Design (Continued from WE Q on Contract 94307) 04/09/2025
M 175 Wenas Creek RM 11 - Haas Fish Screening and Passage- Produce Design (Continued from WE R on Contract 94307) 04/01/2025
N 175 Coleman Creek RM 4.6 - Raap (continued from WE S in 2024 Contract 94307) 04/01/2025
O 175 Naneum Creek RM 4.7 - Ellensburg Water Company Intersection (continued from WE U in 2024 Contract 94307) 07/09/2025
P 175 Naneum Creek RM 3.75 - McCullough Rd Fish Passage (continued from WE W in 2024 Contract 94307) 04/01/2025
Q 175 Cooke 4.25 - Fish Screen and Passage (continued from WE V in 2024 Contract 94307) 04/01/2025
R 175 Cooke 3.85 - Fish Screen and Passage (continued from WE V in 2024 Contract 94307) 04/01/2025
S 175 Cooke 8.2 - Fish Screen (new)
T 175 Whiskey Creek Barriers RM 1.5-1.7 (connected to WE AL in 2024 Contract 94307) 09/10/2025
U 198 Parke Creek 1.01 Vegetation Maintenance (connected to WE X in 2023 contract 92053) 04/01/2025
V 198 Coleman 2.0 Vegetation Maintenance (connected to WE AA in 2024 Contract 94307) 04/01/2025
W 198 Naneum 2.9 Vegetation Maintenance (connected to WE AB in 2024 Contract 94307) 04/01/2025
X 198 Coleman Creek 4.4 (Schomer) Vegetation Maintenance (connected to WE AC in 2024 Contract 94307) 04/01/2025
Y 85 Naneum 3.2 Fish Passage (continued from WE AE in 2024 Contract 94307)
Z 208 Cooke Creek 4.25 Fish Screen and Passage (connected to WE AG in 2024 Contract 94307)
AA 208 Cascade at Coleman Creek (RM 5.4) Fish Passage and Screening (connected to WE AH in 2024 Contract 94307) 04/10/2025
AB 208 Naneum Creek RM 4.7 - Ellensburg Water Company Intersection (connected to WE AI in 2024 Contract 94307)
AC 208 Whiskey Creek Barriers RM 1.5-1.7 (connected to WE AL in contract 92053)