Summary:
The Power Act directs the ISRP to review projects that are proposed for Bonneville funding to implement the Council’s program. The Act specifies the review standards that the ISRP is to use and the kinds of recommendations to make to the Council. The Council must fully consider the ISRP’s report prior to making its funding recommendations to Bonneville, and must explain in writing wherever the Council’s recommendations differ from the ISRP’s.
Proposer:
None
Proponent Orgs:
Northwest Power and Conservation Council (Non-Profit)
Starting FY:
1998
Ending FY:
2019
BPA PM:
Stage:
Implementation - Project Status Report
Area:
Province Subbasin %
Basinwide - 100.00%
Purpose:
Programmatic
Emphasis:
Regional Coordination
Focal Species:
Chinook - All Populations
Chum - Columbia River ESU
Coho - Lower Columbia River ESU
Coho - Unspecified Population
Cutthroat Trout, Coastal - All Anadromous Populations
Lamprey, Pacific
Lamprey, River
Shad, American
Sockeye - All Populations
Steelhead - All Populations
Sturgeon, Green
Sturgeon, White - Lower Columbia River
Wildlife
Species Benefit:
Anadromous: 33.4%   Resident: 33.3%   Wildlife: 33.3%
Tags:
None
Special:
None
BiOp Association:
None

No photos have been uploaded yet for this project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

Expense SOY Budget Working Budget Contracted Amount Modified Contract Amount Expenditures *
FY2018 (Previous) $500,000 $500,000 $499,991 $499,991 $216,754

General $500,000 $499,991 $499,991 $216,754
FY2019 (Current) $500,000 $500,000 $499,994 $499,994 $78,296

General $500,000 $499,994 $499,994 $78,296
FY2020 (Next) $0 $0 $0 $0

* Expenditures data includes accruals and are based on data through 30-Nov-2018

Decided Budget Transfers  (FY2018 - FY2020)

Acct FY Acct Type Amount Fund Budget Decision Date
FY2018 Expense $500,000 From: General FY18 SOY Budgets 07/17/2017
FY2019 Expense $500,000 From: General FY19 Q1 SOY Transfers 09/19/2018

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2019   DRAFT
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2018
2017 $6,747 1 %
2016 $6,614 1 %
2015 $6,484 1 %
2014 $6,357 1 %
2013 $6,233 1 %
2012 $6,110 1 %
2011 $5,991 1 %
2010
2009 $5,758 1 %
2008 $5,644 1 %
2007 $5,427 1 %

Contracts

The table below contains contracts with the following statuses: Active, Complete, History, Issued.
Expense Contracts:
Number Contractor Name Title Status Contracted Amount Dates
CR-325045 SOW 1997-023-00 EXP INDEPENDENT SCIENTIFIC REVIEW PANEL Pending $1
CR-325046 SOW 1997-023-00 EXP INDEPENDENT SCIENTIFIC REVIEW PANEL Pending $1
77258 SOW Northwest Power and Conservation Council 1997-023-00 EXP INDEPENDENT SCIENTIFIC REVIEW PANEL Issued $499,991 10/1/2017 - 9/30/2018
80470 SOW Northwest Power and Conservation Council 1997-023-00 EXP INDEPENDENT SCIENTIFIC REVIEW PANEL Issued $499,994 10/1/2018 - 9/30/2019



Annual Progress Reports
Expected (since FY2004):14
Completed:14
On time:14
Status Reports
Completed:53
On time:47
Avg Days Early:2

Earliest Subsequent           Accepted Count of Contract Deliverables
Contract Contract(s) Title Contractor Start End Status Reports Complete Green Yellow Red Total % Green and Complete Canceled
4621 24576, 29578, 34626, 39177, 44106, 49526, 54790, 58844, 62680, 66758, 70518, 73870, 77258, 80470 1997-023-00 INDEPENDENT SCIENTIFIC REVIEW PANEL Northwest Power and Conservation Council 10/2001 10/2001 Issued 53 46 0 0 0 46 100.00% 0
Project Totals 53 46 0 0 0 46 100.00% 0


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

Review: FY07-09 Solicitation Review

Capital Assessment

Assessment Number: 1997-023-00-CAPITAL-20090618
Project Number: 1997-023-00
Review: FY07-09 Solicitation Review
Completed Date: 2/27/2007
Capital Rating: Does Not Qualify for Capital Funding
Capital Asset Category: None
Comment: None

Project Relationships: None

Name Role Organization
Erik Merrill Project Lead Northwest Power and Conservation Council
Kierstan Dodd (Inactive) Administrative Contact Northwest Power and Conservation Council
Tony Grover Supervisor Northwest Power and Conservation Council
Paul Krueger (Inactive) Supervisor Bonneville Power Administration
Scott Donahue Project Manager Bonneville Power Administration