View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Basinwide | - | 100.00% |
Description: Page: 27 Figure 1: Map of the 19 study streams in the Salmon River Basin in Idaho. Dots on individual streams identify the location of sampling reaches. Shading depicts National Forest land. Project(s): 2001-055-00 Document: P108490 Dimensions: 986 x 690 Description: Page: 73 Chapter 2-Figure 1: Map of study area in the Salmon River Basin, Idaho. Dots indicate streams with nutrient limitation experiments. Project(s): 2001-055-00 Document: P108490 Dimensions: 1005 x 773 Description: Page: 74 Chapter 2-Figure 2: Photo of a nutrient diffusing substrate experiment placed in-stream. Each wooden rack contained 6-8 replicate vials of four treatments (N, P, NP and Control); vials were attached to the rack using rubber bands. Racks were secured to the stream bottom using rebar and rubber bands. Project(s): 2001-055-00 Document: P108490 Dimensions: 648 x 486 Description: Page: 90 Chapter 3-Figure 1: Chinook and steelhead were sampled from 21 different tributaries in the Salmon River Basin, Idaho from 2003-2005. Tributaries include Beaver Creek (BEV), Bear Valley Creek (BVA), Camas Creek (CAM), Chamberlain Creek (CHA), Cape Horn Creek (CHO), Curtis Creek (CUR), Elk Creek (ELK), Elk Creek Tributary (ETR), Herd Creek (HER), Lake Creek (LAK), Lower Big Creek (LBG), Loon Creek (LOO), March Creek (MAR), Rush Creek (RUS), Secesh River (SEC), South Fork Salmon River (SFS), Sulphur Creek (Sullivan and Moncreiff), Summit Creek (SUM), Upper Big Creek (UBG), Valley Creek (VAL), West Fork Chamberlain (WFC). Project(s): 2001-055-00 Document: P108490 Dimensions: 1140 x 760 |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
5636 SOW | Washington Department of Fish and Wildlife (WDFW) | 2001-055-00 SALMONID RESPONSE TO FERTILIZATION - WDFW | History | $84,314 | 5/1/2001 - 9/30/2006 |
7534 SOW | Yakama Confederated Tribes | 2001-055-00 NUTRIENT ENHANCEMENT STUDIES - YIN | History | $56,932 | 5/1/2001 - 1/31/2005 |
7695 SOW | Bio-Oregon, Inc. | 2001-055-00 NUTRIENT ENHANCEMENT STUDIES - BIO-OREGON, INC. | History | $59,409 | 5/1/2001 - 6/30/2006 |
7621 SOW | National Oceanic and Atmospheric Administration | 2001-055-00 NUTRIENT ENHANCEMENT STUDIES - NMFS | Closed | $607,669 | 5/1/2001 - 9/30/2008 |
7848 SOW | Shoshone-Bannock Tribes | 2001-055-00 NUTRIENT ENHANCEMENT STUDIES - SHOSHONE BANNOCK TRIBE | History | $126,594 | 7/1/2001 - 6/30/2006 |
35430 SOW | Shoshone-Bannock Tribes | 2001-055-00 EXP SALMONID RESPONSE FERTILIZ- FINAL PUBLICATIONS | History | $20,269 | 10/16/2007 - 9/30/2008 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 5 |
Completed: | 3 |
On time: | 3 |
Status Reports | |
---|---|
Completed: | 17 |
On time: | 4 |
Avg Days Late: | 90 |
Count of Contract Deliverables | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Earliest Contract | Subsequent Contracts | Title | Contractor | Earliest Start | Latest End | Latest Status | Accepted Reports | Complete | Green | Yellow | Red | Total | % Green and Complete | Canceled |
5636 | 2001-055-00 SALMONID RESPONSE TO FERTILIZATION - WDFW | Washington Department of Fish and Wildlife (WDFW) | 05/01/2001 | 09/30/2006 | History | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
7621 | 2001-055-00 NUTRIENT ENHANCEMENT STUDIES - NMFS | National Oceanic and Atmospheric Administration | 05/01/2001 | 09/30/2008 | Closed | 12 | 5 | 0 | 0 | 0 | 5 | 100.00% | 0 | |
7848 | 35430 | 2001-055-00 EXP SALMONID RESPONSE FERTILIZ- FINAL PUBLICATIONS | Shoshone-Bannock Tribes | 07/01/2001 | 09/30/2008 | History | 5 | 5 | 0 | 0 | 3 | 8 | 62.50% | 0 |
Project Totals | 17 | 10 | 0 | 0 | 3 | 13 | 76.92% | 0 |
Assessment Number: | 2001-055-00-CAPITAL-20090618 |
---|---|
Project Number: | 2001-055-00 |
Review: | FY07-09 Solicitation Review |
Completed Date: | 2/27/2007 |
Capital Rating: | Does Not Qualify for Capital Funding |
Capital Asset Category: | None |
Comment: | None |
Name | Role | Organization |
---|---|---|
Beth Sanderson | Project Lead | National Oceanic and Atmospheric Administration |
Doug Taki | Project Lead | Shoshone-Bannock Tribes |
Todd Pearsons (Inactive) | Project Lead | Washington Department of Fish and Wildlife (WDFW) |
Peter Lofy | Project Manager | Bonneville Power Administration |