View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Columbia Cascade | Methow | 100.00% |
Description: Page: 6 Photo 1: (Johnson 11/05) Arnie Pipkin removing the backing for placement of operable headgate. Project(s): 2005-009-00 Document: P107708 Dimensions: 1998 x 3012 Description: Page: 7 Photo 2: (Johnson 08/05) Pre-project Condition Stranded intake pipe visible middle of image post Spring High water damage. Staking upstream from intake marks project site for placement of new diversion headgate. Project(s): 2005-009-00 Document: P107708 Dimensions: 1504 x 1000 Description: Page: 7 Photo 3: (Johnson 11/05/05) Stripping forms from new diversion headgate structure. Forms are resting on coffer dam creating a walkable work area. BOR on-site staff inspects concrete finish prior to replacement of rock rip rap. Project(s): 2005-009-00 Document: P107708 Dimensions: 1501 x 996 Description: Page: 8 Photo 4: (Johnson 10/05) Site constraints required transfer of concrete from delivery truck to work site by excavator bucket. Project(s): 2005-009-00 Document: P107708 Dimensions: 1024 x 768 Description: Page: 8 Photo 5: (Johnson 10/05) Placement of concrete into headgate forms was completed by hand with site constructed funnels. All concrete work was mechanically vibrated after placement to ensure a uniform pour would be achieved given the small batch placement. Site constraints would not allow use of a pump truck. Project(s): 2005-009-00 Document: P107708 Dimensions: 1504 x 1000 Description: Page: 9 Photo 6: Johnson 08/05). Existing Dike Access Road prior to construction. Narrow width and unknown construction condition precluded use of the road for pump trucks. Project(s): 2005-009-00 Document: P107708 Dimensions: 1502 x 998 Description: Page: 9 Photo 7: (Johnson 11/05) Access road following completion of project. Surface was renewed and bladed as disposal site for waste material from headgate excavation. New dike surface provides improved access to the headgate for project maintenance. Note: Lack of tree/vegetation removal adjacent to dike access road. Project(s): 2005-009-00 Document: P107708 Dimensions: 1504 x 1000 Description: Page: 10 Photo 8: (Johnson 03/06) Culvert between Ponds 2 and 3 creates a barrier to upstream passage for all TES species. Project(s): 2005-009-00 Document: P107708 Dimensions: 1492 x 998 Description: Page: 10 Photo 9: (Johnson 08/07) Newly constructed connecting channel between Ponds 2 and 3 following removal of culvert. Excellent passage now exists for all TES species. Note: Net pen visible in pond in use by WDFW for steelhead pit tag project. Project(s): 2005-009-00 Document: P107708 Dimensions: 1504 x 1000 Description: Page: 11 Photo 10: (Johnson 08/06) Newly created side channel between Ponds 1 and 2 allows passage at all flows. A 28 foot section of 36” Dia. CMP provides vehicle access to the site. The Culvert was filled with cobbles following placement by means of a conveyor to ensure passage and bed roughness. Project(s): 2005-009-00 Document: P107708 Dimensions: 1504 x 1000 Description: Page: 11 Photo 11: (Johnson 06/08) Second year of vegetation growth on constructed connecting channel between Ponds 4 and 5. Rock weirs have been constructed to maintain channel bed and scour pools for fish staging. Project(s): 2005-009-00 Document: P107708 Dimensions: 1504 x 997 |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
24674 SOW | Methow Salmon Recovery Foundation | 200500900 EXP TWISP SIDE CHANNEL | History | $81,568 | 9/20/2005 - 8/31/2006 |
30075 SOW | Methow Salmon Recovery Foundation | 200500900 EXP TWISP SIDE CHANNEL PHASE 2 | History | $39,828 | 10/20/2006 - 9/30/2007 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 1 |
Completed: | 1 |
On time: | 1 |
Status Reports | |
---|---|
Completed: | 9 |
On time: | 2 |
Avg Days Late: | 54 |
Count of Contract Deliverables | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Earliest Contract | Subsequent Contracts | Title | Contractor | Earliest Start | Latest End | Latest Status | Accepted Reports | Complete | Green | Yellow | Red | Total | % Green and Complete | Canceled |
24674 | 30075 | 200500900 EXP TWISP SIDE CHANNEL PHASE 2 | Methow Salmon Recovery Foundation | 09/20/2005 | 09/30/2007 | History | 9 | 6 | 0 | 0 | 0 | 6 | 100.00% | 1 |
Project Totals | 9 | 6 | 0 | 0 | 0 | 6 | 100.00% | 1 |
Name | Role | Organization |
---|---|---|
Chris Johnson (Inactive) | Project Lead | Chewuch Basin Council |
Greg Knott (Inactive) | Project Lead | Pacific Northwest National Laboratory |
Chris Eliassen (Inactive) | Administrative Contact | Methow Salmon Recovery Foundation |
Cecilia Brown (Inactive) | Project Manager | Bonneville Power Administration |
Paul Krueger (Inactive) | Supervisor | Bonneville Power Administration |