Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74491: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT - CUSTER
Project Number:
Title:
Pahsimeroi River Habitat
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
74491
Contract Title:
2008-603-00 EXP PAHSIMEROI RIVER HABITAT - CUSTER
Contract Continuation:
Previous: Next:
70409: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT - CUSTER
  • 80477: 2008-603-00 EXP PAHSIMEROI WATERSHED HABITAT (CUSTER SWCD)
Contract Status:
Closed
Contract Description:
Work proposed in this statement of work will allow completion of three projects that are ongoing from contract 70409. The Environmental Assessment development by the BLM must be complete in order to install pipeline and diversion structure on BLM land. The work window for terrestrial species near P-17 will not allow  work to start until after July 15, 2017 which shortens the window of construction for both the on-farm work and the diversion. IDFG is also in the process of installing a fish screen as a component of this project but under a separate contract with IDFG. The screen must be  installed early in September in order to be able to complete installation of the on-farm work. This project will require the irrigators to shut down due the two properties that depend on the water through the end of irrigation season.  The riparian fence on the Pahsimeroi river at on private property will be delayed to this contract to allow all on farm irrigation infrastructure  work to be completed prior to constructing the fence.

P-17 diversion is immediately upstream from the P-16/Furey Lane project. The previous statement of work and this statement of work will address  planning and consultation for this project with implementation scheduled in 2017. The BLM and Custer SWCD have a good working template from the P-16 EA that will make consultation more streamlined but will still take at least a full year to complete. This project was one of the top priorities for the Upper Pahsimeroi work group. In addition the Custer SWCD would request support from OSC and BPA to complete the consultation through the Programmatic process in the same manner as the P-16 project was completed. This project will require a new diversion and instream work as well as address a water conservation pipeline to provide water savings and a fish screen installed by IDFG screen shop. This would be a combined partnership effort to complete this project much in the same way the P-16 project was implemented. NRCS would provide design and assist in implementation for the Irrigation infrastructure and IDFG would design and implement the fish screen. BLM would assist in a cultural survey with the remaining cultural on the private property completed through a contract for cultural.

There are also multiple opportunities for riparian fencing in the Pahsimeroi and Patterson/Big Springs Creek as the Custer SWCD continue to work with landowners. Custer SWCD will continue to work with the Pahsimeroi group to identify and prioritize these projects. Additional focus needs to be paid to those projects reaching their project life of 15 years and should be addressed for either future maintenance or re-construction. With a staff assistance the Custer SWCD will be able to better identify the projects that are in need of improvement.
Account Type(s):
Expense
Contract Start Date:
09/26/2016
Contract End Date:
09/25/2018
Current Contract Value:
$268,845
Expenditures:
$268,845

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Wayne Baker Custer Soil and Water Conservation District (SWCD) No Supervisor SHARED_cswcd@custertel.net (208) 879-4428
Daniel Bertram Idaho Governor's Office of Species Conservation No Interested Party daniel.bertram@osc.idaho.gov (208) 756-6322
Karma Bragg Custer Soil and Water Conservation District (SWCD) Yes Contract Manager cswcd@custertel.net (208) 879-4428
Lisa Dexter Bonneville Power Administration No Interested Party lldexter@bpa.gov (503) 230-3893
Mike Edmondson Idaho Governor's Office of Species Conservation Yes Interested Party mike.edmondson@osc.idaho.gov (208) 334-2189
Amy Hines Idaho Governor's Office of Species Conservation Yes Administrative Contact amy.hines@osc.idaho.gov (208) 332-1557
Jennifer Lord Bonneville Power Administration Yes COR jklord@bpa.gov (503) 230-5192
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Robert Shull Bonneville Power Administration No Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Gregory Smith Bonneville Power Administration Yes Interested Party gmsmith@bpa.gov (503) 230-5049
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Obtain or complete Environmental consultation documents and provide to BPA B: 165. Produce EC documents on identified projects 08/31/2018
All administrative tasks fulfilled with timely quality products C: 119. Manage and administer projects within this contract for FY 15/16 09/25/2018 03/30/2018
Completed Annual Report D: 132. Submit Progress Report for the period September 26, 2015 thru September 25, 2016 09/30/2016 12/05/2016
Upload prioritized project list to Pisces E: 114. Identify and Select projects based on partnership coordination with Pahsimeroi Group 08/31/2018 08/09/2018
Produce Design and/or Specifications F: 175. Produce Design: P-17 pipeline and on-farm infrastructure 09/25/2018 03/30/2018
Purchase Pipe and install pipeline for the P-17 project G: 203. Purchase and install Pipe and stockwater for P-17 Water Conservation Project 09/25/2018
Install fish friendly diversion structure, remove and re-habilitate existing structure. H: 84. Install new fish friendly diversion barrier on P-17 09/21/2018
Install Irrigation well to provide 1.66 to 1.8 cfs to supplement or replace the surface water right I: 82. Install irrigation well to provide supplemental flows to the JP ranch 09/25/2018
Install Riparian Fence on Pahsimeroi on DR ranch J: 40. Install riparian fence along the Pahsimeroi on the DR ranch 09/25/2018 09/21/2018
Identify potential projects and develop conceptual designs for projects for future funding. K: 175. Produce conceptual designs on proposed project to provide options for out-year projects 09/21/2018 09/20/2018
Plant vegetation to re-habilitate the fords at the DR bridge locations L: 47. Plant Vegetation on DR bridge to re-vegetate closed ford locations 11/16/2017 11/16/2017
Install water control headgate and measuring device at the Mulvaney Ditch to reduce flowed directed away from Patterson/Big Springs M: 148. New: Install headgate and flow measuring device at Mulvaney Ditch to provide adequate flow into Patterson/Big Springs Creek 09/21/2018 09/20/2018
Complete repairs on P-16 diversion and headgate N: 84. New: Provide maintenance on Passage Structure damaged by high water at P-16 09/30/2017 09/30/2017
Re-install plug that washed out in high water this year. O: 85. New: Re-install plug from P-13 Ditch to ensure re-connect of Pahsimeroi River 09/30/2017 09/22/2017
Completed Annual Report P: 132. Submit Progress Report for the period Septemer 26, 2016 to September 25, 2017 09/25/2018 09/21/2018

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 2 instances of WE 84 Remove/Install Diversion
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 82 Install Well
  • 1 instance of WE 148 Install Flow Measuring Device
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 40 Install Fence
  • 2 instances of WE 84 Remove/Install Diversion
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 82 Install Well
  • 1 instance of WE 148 Install Flow Measuring Device

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 09/26/2016
B 165 Produce EC documents on identified projects 09/26/2016
C 119 Manage and administer projects within this contract for FY 15/16 09/26/2016
D 132 Submit Progress Report for the period September 26, 2015 thru September 25, 2016 09/26/2016
E 114 Identify and Select projects based on partnership coordination with Pahsimeroi Group 09/26/2016
F 175 Produce Design: P-17 pipeline and on-farm infrastructure 07/24/2017
G 203 Purchase and install Pipe and stockwater for P-17 Water Conservation Project
H 84 Install new fish friendly diversion barrier on P-17
I 82 Install irrigation well to provide supplemental flows to the JP ranch 07/24/2017
J 40 Install riparian fence along the Pahsimeroi on the DR ranch 07/24/2017
K 175 Produce conceptual designs on proposed project to provide options for out-year projects 02/28/2017
L 47 Plant Vegetation on DR bridge to re-vegetate closed ford locations 07/24/2017
M 148 New: Install headgate and flow measuring device at Mulvaney Ditch to provide adequate flow into Patterson/Big Springs Creek 06/01/2018
N 84 New: Provide maintenance on Passage Structure damaged by high water at P-16 08/28/2017
O 85 New: Re-install plug from P-13 Ditch to ensure re-connect of Pahsimeroi River 10/17/2017
P 132 Submit Progress Report for the period Septemer 26, 2016 to September 25, 2017 09/26/2016