Project Summary

Project 1991-071-00 - Sockeye Salmon Hab & Limnologi
Project Number:
1991-071-00
Title:
Sockeye Salmon Hab & Limnologi
Summary:
This project will monitor and enhance (if necessary) rearing conditions for juvenile Snake River sockeye salmon. We will also investigate competition, growth rates, and survival for progeny released from the captive broodstock program.
Proposer:
None
Proponent Orgs:
Shoshone-Bannock Tribes (Tribe)
Starting FY:
1992
Ending FY:
2011
Stage:
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Purpose:
Habitat
Emphasis:
RM and E
Focal Species:
Sockeye - Snake River ESU
Trout, Bull
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

No photos have been uploaded yet for this Project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

No Decided Budget Transfers

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2024
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
There are no cost share summaries to display from previous years.

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
4343 SOW Shoshone-Bannock Tribes 1991-071-00 SOCKEYE SALMON HABITAT & LIMNOLOGICA History $1,361,683 4/4/2001 - 11/30/2004
20474 SOW Shoshone-Bannock Tribes 1991-071-00 SNAKE RIVER SOCKEYE SALMON HABITAT AND LIMNOLOGICAL History $444,748 12/1/2004 - 11/30/2005
26989 SOW Shoshone-Bannock Tribes 1991-071-00 EXP SNAKE RIVER SOCKEYE SALMON HABITAT AND LIMNOLOGIC History $367,747 12/1/2005 - 11/30/2006



Annual Progress Reports
Expected (since FY2004):2
Completed:2
On time:2
Status Reports
Completed:6
On time:3
Avg Days Late:14

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
4343 20474, 26989, 30651, 35490, 40909, 45080, 50064, 55108, 60302, 63451, 67494, 71106, 74770, 77111 REL 1, 77111 REL 11, 77111 REL 20, 77111 REL 31, 77111 REL 41, 91369, 84068 REL 9 2007-402-00 EXP SBT SNAKE RIVER SOCKEYE M&E/HABITAT Shoshone-Bannock Tribes 04/04/2001 11/30/2024 Issued 75 212 10 0 12 234 94.87% 4
Project Totals 75 212 10 0 12 234 94.87% 4


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

Review: FY07-09 Solicitation Review

Council Recommendation

Assessment Number: 1991-071-00-NPCC-20090924
Project: 1991-071-00 - Sockeye Salmon Hab & Limnologi
Review: FY07-09 Solicitation Review
Approved Date: 10/23/2006
Recommendation: Fund
Comments: Need to prioritize work elements to support Redfish Lake Sockeye at this budget level (e.g., fertilization, carrying capacity, juv outmigration).

Independent Scientific Review Panel Assessment

Assessment Number: 1991-071-00-ISRP-20060831
Project: 1991-071-00 - Sockeye Salmon Hab & Limnologi
Review: FY07-09 Solicitation Review
Completed Date: 8/31/2006
Final Round ISRP Date: None
Final Round ISRP Rating: Meets Scientific Review Criteria
Final Round ISRP Comment:
The preliminary review recommendation for 199107100 (Snake River sockeye salmon habitat and limnological monitoring) was Not Fundable. This recommendation was based largely on this project's interrelationship with 199107200, the primary proposal to conduct the Redfish Lake sockeye salmon captive propagation program, which received a Not Fundable recommendation.

The ISRP also found deficiencies in the reporting of results in the proposal; however, this deficiency alone could have been resolved with a response.

Together with the other Redfish Lake sockeye salmon proposals, the ISRP carefully considered the response from the project sponsors. The response addressing the reporting of results and activities for this specific proposal was brief, but adequate.

Early results of productivity enhancement show increased survival of juveniles stocked in the test lakes, and residual sockeye have been observed spawning. Consequently, researchers now believe that with enhancement of habitat productivity, it may be possible to develop self-sustaining populations of residual sockeye salmon in the Stanley Basin lakes.

If the above hypothesis and its basis are true, the ISRP believes that with a rigorous monitoring program, assessment of the role of predators and competitors, and a defined end-point for testing the hypothesis, the project has scientific merit.

Preserving the Snake River sockeye salmon ESU will likely hinge on the status of residual sockeye in the Stanley Basin lakes. Whether the residual sockeye is preserving the population needs to be further explored.

Consequently the ISRP finds the project is justified and the final recommendation is Fundable. Contingent upon the final outcome of stocking activities under proposal 199107200, some work elements may need to be modified. Juvenile and adult monitoring and lake fertilization remain essential components of this project.
Documentation Links:

Legal Assessment (In-Lieu)

Assessment Number: 1991-071-00-INLIEU-20090521
Project Number: 1991-071-00
Review: FY07-09 Solicitation Review
Completed Date: 10/6/2006
In Lieu Rating: Problems Exist
Cost Share Rating: None
Comment: RM&E supporting SR sockeye; fishery managers authorized required as well; needs cost share or other remedy.

Capital Assessment

Assessment Number: 1991-071-00-CAPITAL-20090618
Project Number: 1991-071-00
Review: FY07-09 Solicitation Review
Completed Date: 2/27/2007
Capital Rating: Does Not Qualify for Capital Funding
Capital Asset Category: None
Comment: None

Project Relationships: This project Merged To 2007-402-00 effective on 7/2/2007
Relationship Description: All work and budgets from projects 1991-071-00 (EXP), 1991-072-00 (EXP & CAP), 1992-040-00 (EXP & CAP), 2005-012-00 (CAP) is moved to project 2007-402-00.


Name Role Organization
Doug Taki Project Lead Shoshone-Bannock Tribes
Gregory Baesler (Inactive) Project Manager Bonneville Power Administration